Moreshwar Niwas is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000012305. Moreshwar Niwas is located at 3A/5. This is a Ongoing being developed by Shriya Builders & Land Developers.

Moreshwar Niwas has 1 Apartments with carpet areas ranging from 1052 to 1052 Sq.ft. Carpet. The Project has total 31 of which 2 are currently available for sale.

Moreshwar Niwas is being developed on a total land area of 9946 Sq.ft. Moreshwar Niwas has 3 Wings / Towers Building No 1,Building No 2,Bungalow

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Moreshwar Niwas
  • Location:
  • 3A/5
  • Const. Stage:
    Ongoing
  • Possession:
    30 Mar 2021
Developer Details

  • Developer:
    Shriya Builders & Land Developers
  • Phone:
  • Address:
  • Umela Park
Project RERA Details
MAHA REARA No: P99000012305
Project Type Others
RERA Project Status Ongoing
Architect Ajay Wade & Associates
Funding Bank BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession 30 Mar 2021
Revised Possession 30 Mar 2021
Extended Possession 31 Dec 2025
Litigations No Litigations
Last Modified 10 Jan 2023
Last Retrived 28 Jul 2025
Moreshwar Niwas QR Code
Moreshwar Niwas
MahaRERA - P99000012305
Apartment Details & Configuration
TypeArea
121.12 Sq.mts. ( 227 Sq.ft. )
224.03 Sq.mts. ( 259 Sq.ft. )
324.24 Sq.mts. ( 261 Sq.ft. )
424.95 Sq.mts. ( 269 Sq.ft. )
535.97 Sq.mts. ( 387 Sq.ft. )
537.33 Sq.mts. ( 402 Sq.ft. )
637.47 Sq.mts. ( 403 Sq.ft. )
738.97 Sq.mts. ( 419 Sq.ft. )
SHOP 18.55 Sq.mts. ( 92 Sq.ft. )
SHOP 27.05 Sq.mts. ( 76 Sq.ft. )
SHOP 311.4 Sq.mts. ( 123 Sq.ft. )
SHOP 410.22 Sq.mts. ( 110 Sq.ft. )
SHOP 58.58 Sq.mts. ( 92 Sq.ft. )
SHOP 613.92 Sq.mts. ( 150 Sq.ft. )
124.93 Sq.mts. ( 268 Sq.ft. )
224.94 Sq.mts. ( 268 Sq.ft. )
325.25 Sq.mts. ( 272 Sq.ft. )
433.99 Sq.mts. ( 366 Sq.ft. )
534.86 Sq.mts. ( 375 Sq.ft. )
197.69 Sq.mts. ( 1052 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Moreshwar Niwaslast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
-
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting100% completed
95% Complete
Facility Available In Larger Layout
Open Parking100% completed
95% Complete
-
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
-
Solid Waste Management And Disposal
-
Storm Water Drains100% completed
95% Complete
Facility Available In Larger Layout
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
-
Water Supply50% completed
50% Complete
Will Start Once Vvcmc Water Supply Commences
Buildings / Wings in Moreshwar Niwas
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Moreshwar Niwas by Shriya Builders & Land Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

9946 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

31 apartments in total
Total
31
Booked
29
Available
2

Saleable Area Statistics (Sq. ft.)

9273 Total
Total
9273
Booked
9031
Available
242
Total 31 apartments in project. 29 apartments booked. 93% apartments booked.
Total 9273 Sq.ft. saleable area. 9031 saleable area booked.
97% area booked.

Building No 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 1Sep 20204101011
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
121.12 Sq.mts. ( 227 Sq.ft. )1
1 Booked100% Booked
100% Booked
224.03 Sq.mts. ( 259 Sq.ft. )2
2 Booked100% Booked
100% Booked
324.24 Sq.mts. ( 261 Sq.ft. )3
3 Booked100% Booked
100% Booked
424.95 Sq.mts. ( 269 Sq.ft. )1
1 Booked100% Booked
100% Booked
535.97 Sq.mts. ( 387 Sq.ft. )2
2 Booked100% Booked
100% Booked
537.33 Sq.mts. ( 402 Sq.ft. )1
1 Booked100% Booked
100% Booked
637.47 Sq.mts. ( 403 Sq.ft. )2
2 Booked100% Booked
100% Booked
738.97 Sq.mts. ( 419 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP 18.55 Sq.mts. ( 92 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP 27.05 Sq.mts. ( 76 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP 311.4 Sq.mts. ( 123 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP 410.22 Sq.mts. ( 110 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP 58.58 Sq.mts. ( 92 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP 613.92 Sq.mts. ( 150 Sq.ft. )1
None Booked0% Booked
0% Booked
19 total apartments / 17 apartments booked. 89% apartments booked.
Work Description in Building Building No 1Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 2Sep 20204100010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
124.93 Sq.mts. ( 268 Sq.ft. )1
1 Booked100% Booked
100% Booked
224.94 Sq.mts. ( 268 Sq.ft. )3
3 Booked100% Booked
100% Booked
325.25 Sq.mts. ( 272 Sq.ft. )3
3 Booked100% Booked
100% Booked
433.99 Sq.mts. ( 366 Sq.ft. )1
1 Booked100% Booked
100% Booked
534.86 Sq.mts. ( 375 Sq.ft. )3
3 Booked100% Booked
100% Booked
11 total apartments / 11 apartments booked. 100% apartments booked.
Work Description in Building Building No 2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Bungalow

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
BungalowSep 20202100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
197.69 Sq.mts. ( 1052 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 total apartments / 1 apartments booked. 100% apartments booked.
Work Description in Building BungalowCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Shriya Builders & Land Developers
for Project
Moreshwar Niwas
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation