Mohak Oyster Living is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000011119. Mohak Oyster Living is located at 317/12. This is a Ongoing being developed by Oyster Corporation.

Mohak Oyster Living has 1 BHK Apartments with carpet areas ranging from 9802 to 9802 Sq.ft. Carpet. The Project has total 61 of which 25 are currently available for sale.

Mohak Oyster Living is being developed on a total land area of 26695 Sq.ft. out of which 2408 Sq.ft. i.e 9% is reserved for recreational purposes. Mohak Oyster Living has 3 Wings / Towers A Wing,B Wing,C Wing

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Mohak Oyster Living
  • Location:
  • 317/12
  • Const. Stage:
    Ongoing
  • Possession:
    30 Jun 2018
Developer Details

  • Developer:
    Oyster Corporation
  • Phone:
  • Address:
  • Western Edge 1
Project RERA Details
MAHA REARA No: P99000011119
Project Type Others
RERA Project Status Ongoing
Architect Encon Project Consultant
Funding Bank AXIS BANK
Proposed Possession 30 Jun 2018
Revised Possession 30 Jun 2018
Extended Possession 30 Jun 2023
Litigations No Litigations
Last Modified 22 Apr 2022
Last Retrived 28 Jul 2025
Mohak Oyster Living QR Code
Mohak Oyster Living
MahaRERA - P99000011119
Apartment Details & Configuration
TypeArea
SHOP311.1 Sq.mts. ( 3349 Sq.ft. )
1 BHK702.01 Sq.mts. ( 7556 Sq.ft. )
2 BHK321.05 Sq.mts. ( 3456 Sq.ft. )
1 BHK910.6 Sq.mts. ( 9802 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Mohak Oyster Livinglast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Work Not Yet Started
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station90% completed
90% Complete
Work In Progress
Energy management90% completed
90% Complete
Work In Progress
Fire Protection And Fire Safety Requirements90% completed
90% Complete
Work In Progress
Landscaping & Tree Planting90% completed
90% Complete
Work In Progress
Open Parking
Work Not Yet Started
Sewerage (Chamber, Lines, Septic Tank , STP)90% completed
90% Complete
Work In Progress
Solid Waste Management And Disposal90% completed
90% Complete
Work In Progress
Storm Water Drains90% completed
90% Complete
Work Completed
Street Lighting90% completed
90% Complete
Work In Progress
Treatment And Disposal Of Sewage And Sullage Water90% completed
90% Complete
Work In Progress
Water Conservation, Rain water Harvesting90% completed
90% Complete
Work In Progress
Water Supply90% completed
90% Complete
Work Not Yet Started
Buildings / Wings in Mohak Oyster Living
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Mohak Oyster Living by Oyster Corporationlast updated on 28 Jul 2025 as per information obtained from MARA RERA.

26695 Sq. ft.

Project Area

2408 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

61 apartments in total
Total
61
Booked
36
Available
25

Saleable Area Statistics (Sq. ft.)

463406 Total
Total
463406
Booked
283352
Available
180054
Total 61 apartments in project. 36 apartments booked. 59% apartments booked.
Total 463406 Sq.ft. saleable area. 283352 saleable area booked.
61% area booked.

A Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A WingJan 190015101051
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
SHOP311.1 Sq.mts. ( 3349 Sq.ft. )7
None Booked0% Booked
0% Booked
7 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building A WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
work-in-progress50% done
50% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure

B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
B WingJan 19008101031
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK702.01 Sq.mts. ( 7556 Sq.ft. )20
14 Booked70% Booked
70% Booked
2 BHK321.05 Sq.mts. ( 3456 Sq.ft. )7
6 Booked85% Booked
85% Booked
27 total apartments / 20 apartments booked. 74% apartments booked.
Work Description in Building B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

C Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
C WingJan 19008101071
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK910.6 Sq.mts. ( 9802 Sq.ft. )27
16 Booked59% Booked
59% Booked
27 total apartments / 16 apartments booked. 59% apartments booked.
Work Description in Building C WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Oyster Corporation
for Project
Mohak Oyster Living
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation