Project overview

Mirador Utsav Phase 1 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700012454. Mirador Utsav Phase 1 is located at 128/1,128/2,128/3. This is a Ongoing being developed by Mirador Dewellers Pvt Ltd.

Mirador Utsav Phase 1 has 1 BHK & 2 BHK Apartments with carpet areas ranging from 346 to 539 Sq.ft. Carpet. The Project has total 314 of which 94 are currently available for sale.

Mirador Utsav Phase 1 is being developed on a total land area of 142085 Sq.ft. out of which 18003 Sq.ft. i.e 13% is reserved for recreational purposes. Mirador Utsav Phase 1 has 13 Wings / Towers A,B,C,D,E,F,G,H,I,K,L,M,N

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Mirador Utsav Phase 1
  • Location:
  • 128/1,128/2,128/3
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2021
Developer Details

  • Developer:
    Mirador Dewellers Pvt Ltd
  • Phone:
  • Address:
  • H No 240
Project RERA Details
MAHA REARA No: P51700012454
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Aarif Punjabi
Funding Bank IDFC First Bank Ltd
Proposed Possession 30 Dec 2021
Revised Possession 30 Dec 2021
Extended Possession 31 Dec 2025
Litigations No Litigations
Last Modified 10 Oct 2023
Last Retrived 26 Jul 2025
Mirador Utsav Phase 1 QR Code
Mirador Utsav Phase 1
MahaRERA - P51700012454
Apartment Details & Configuration
TypeArea
1 BHK30.72 Sq.mts. ( 331 Sq.ft. )
1 BHK28.84 Sq.mts. ( 310 Sq.ft. )
1 BHK29.33 Sq.mts. ( 316 Sq.ft. )
1 BHK29.43 Sq.mts. ( 317 Sq.ft. )
1 BHK29.55 Sq.mts. ( 318 Sq.ft. )
1 BHK29.34 Sq.mts. ( 316 Sq.ft. )
1 BHK29.4 Sq.mts. ( 316 Sq.ft. )
1 BHK29.47 Sq.mts. ( 317 Sq.ft. )
1 BHK29.6 Sq.mts. ( 319 Sq.ft. )
1 BHK33.12 Sq.mts. ( 357 Sq.ft. )
2 BHK44.25 Sq.mts. ( 476 Sq.ft. )
1 BHK29.91 Sq.mts. ( 322 Sq.ft. )
1 BHK30.19 Sq.mts. ( 325 Sq.ft. )
1 BHK31.09 Sq.mts. ( 335 Sq.ft. )
1 BHK31.12 Sq.mts. ( 335 Sq.ft. )
1 BHK26.41 Sq.mts. ( 284 Sq.ft. )
1 BHK26.48 Sq.mts. ( 285 Sq.ft. )
1 BHK26.52 Sq.mts. ( 285 Sq.ft. )
1 BHK26.71 Sq.mts. ( 288 Sq.ft. )
1 BHK26.74 Sq.mts. ( 288 Sq.ft. )
1 BHK26.77 Sq.mts. ( 288 Sq.ft. )
1 BHK27 Sq.mts. ( 291 Sq.ft. )
1 BHK26.45 Sq.mts. ( 285 Sq.ft. )
1 BHK26.5 Sq.mts. ( 285 Sq.ft. )
1 BHK26.51 Sq.mts. ( 285 Sq.ft. )
1 BHK26.53 Sq.mts. ( 286 Sq.ft. )
1 BHK26.63 Sq.mts. ( 287 Sq.ft. )
1 BHK26.67 Sq.mts. ( 287 Sq.ft. )
1 BHK30.13 Sq.mts. ( 324 Sq.ft. )
1 BHK30.16 Sq.mts. ( 325 Sq.ft. )
1 BHK42.42 Sq.mts. ( 457 Sq.ft. )
1 BHK21.03 Sq.mts. ( 226 Sq.ft. )
1 BHK32.55 Sq.mts. ( 350 Sq.ft. )
Shop11.77 Sq.mts. ( 127 Sq.ft. )
Shop12.04 Sq.mts. ( 130 Sq.ft. )
Shop15.79 Sq.mts. ( 170 Sq.ft. )
Shop16.06 Sq.mts. ( 173 Sq.ft. )
1 BHK31.44 Sq.mts. ( 338 Sq.ft. )
Shop10.27 Sq.mts. ( 111 Sq.ft. )
Shop11.22 Sq.mts. ( 121 Sq.ft. )
Shop15.56 Sq.mts. ( 167 Sq.ft. )
1 BHK30.39 Sq.mts. ( 327 Sq.ft. )
1 BHK31.23 Sq.mts. ( 336 Sq.ft. )
1 BHK32.46 Sq.mts. ( 349 Sq.ft. )
1 BHK32.69 Sq.mts. ( 352 Sq.ft. )
1 BHK32.11 Sq.mts. ( 346 Sq.ft. )
1 BHK32.33 Sq.mts. ( 348 Sq.ft. )
1 BHK33.11 Sq.mts. ( 356 Sq.ft. )
1 BHK33.22 Sq.mts. ( 358 Sq.ft. )
1 BHK35.63 Sq.mts. ( 384 Sq.ft. )
1 BHK42.33 Sq.mts. ( 456 Sq.ft. )
2 BHK45.96 Sq.mts. ( 495 Sq.ft. )
2 BHK46.24 Sq.mts. ( 498 Sq.ft. )
2 BHK50.12 Sq.mts. ( 539 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Mirador Utsav Phase 1last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space25% completed
25% Complete
Balance Work In Progress
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station25% completed
25% Complete
Work In Progress
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting25% completed
25% Complete
Planted Trees And Shrubs On Site
Open Parking40% completed
40% Complete
Available On Site
Sewerage (Chamber, Lines, Septic Tank , STP)10% completed
10% Complete
Through Septic Tank
Solid Waste Management And Disposal
Na
Storm Water Drains
Na
Street Lighting50% completed
50% Complete
Main Road Internal Road Street Light Done
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting10% completed
10% Complete
Work In Progress
Water Supply20% completed
20% Complete
Borewell And Grampanchayat Water
Buildings / Wings in Mirador Utsav Phase 1
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Mirador Utsav Phase 1 by Mirador Dewellers Pvt Ltdlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

142085 Sq. ft.

Project Area

18003 Sq. ft.

Recreational Open Space

Total 13

Wings / Towers in Project

Apartments Statistics

314 apartments in total
Total
314
Booked
220
Available
94

Saleable Area Statistics (Sq. ft.)

107104 Total
Total
107104
Booked
74529
Available
32575
Total 314 apartments in project. 220 apartments booked. 70% apartments booked.
Total 107104 Sq.ft. saleable area. 74529 saleable area booked.
70% area booked.

A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
ADec 20215100050
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK30.72 Sq.mts. ( 331 Sq.ft. )18
14 Booked77% Booked
77% Booked
18 total apartments / 14 apartments booked. 77% apartments booked.
Work Description in Building ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress75% done
75% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress35% done
35% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress80% done
80% Booked
Stilt Floor
Completed 100% done
100% Booked

B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
BDec 202151000100
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.84 Sq.mts. ( 310 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK29.33 Sq.mts. ( 316 Sq.ft. )4
3 Booked75% Booked
75% Booked
1 BHK29.43 Sq.mts. ( 317 Sq.ft. )5
4 Booked80% Booked
80% Booked
1 BHK29.55 Sq.mts. ( 318 Sq.ft. )5
5 Booked100% Booked
100% Booked
18 total apartments / 16 apartments booked. 88% apartments booked.
Work Description in Building BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress75% done
75% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress45% done
45% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress80% done
80% Booked
Stilt Floor

C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
CDec 20215100040
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.34 Sq.mts. ( 316 Sq.ft. )4
3 Booked75% Booked
75% Booked
1 BHK29.4 Sq.mts. ( 316 Sq.ft. )5
4 Booked80% Booked
80% Booked
1 BHK29.47 Sq.mts. ( 317 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK29.6 Sq.mts. ( 319 Sq.ft. )5
4 Booked80% Booked
80% Booked
18 total apartments / 15 apartments booked. 83% apartments booked.
Work Description in Building CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress80% done
80% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress20% done
20% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress80% done
80% Booked
Stilt Floor

D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
DDec 20215100050
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK33.12 Sq.mts. ( 357 Sq.ft. )9
6 Booked66% Booked
66% Booked
2 BHK44.25 Sq.mts. ( 476 Sq.ft. )5
4 Booked80% Booked
80% Booked
14 total apartments / 10 apartments booked. 71% apartments booked.
Work Description in Building DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress80% done
80% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress45% done
45% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress80% done
80% Booked
Stilt Floor
Completed 100% done
100% Booked

E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
EDec 20215100050
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.91 Sq.mts. ( 322 Sq.ft. )5
5 Booked100% Booked
100% Booked
1 BHK30.19 Sq.mts. ( 325 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK31.09 Sq.mts. ( 335 Sq.ft. )5
3 Booked60% Booked
60% Booked
1 BHK31.12 Sq.mts. ( 335 Sq.ft. )4
4 Booked100% Booked
100% Booked
18 total apartments / 16 apartments booked. 88% apartments booked.
Work Description in Building ECompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

F

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
FDec 20211100020
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.41 Sq.mts. ( 284 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK26.48 Sq.mts. ( 285 Sq.ft. )5
5 Booked100% Booked
100% Booked
1 BHK26.52 Sq.mts. ( 285 Sq.ft. )5
5 Booked100% Booked
100% Booked
1 BHK26.71 Sq.mts. ( 288 Sq.ft. )5
3 Booked60% Booked
60% Booked
1 BHK26.74 Sq.mts. ( 288 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK26.77 Sq.mts. ( 288 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK27 Sq.mts. ( 291 Sq.ft. )4
4 Booked100% Booked
100% Booked
28 total apartments / 26 apartments booked. 92% apartments booked.
Work Description in Building FCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

G

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
GDec 20215100020
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.45 Sq.mts. ( 285 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK26.5 Sq.mts. ( 285 Sq.ft. )5
5 Booked100% Booked
100% Booked
1 BHK26.51 Sq.mts. ( 285 Sq.ft. )5
5 Booked100% Booked
100% Booked
1 BHK26.53 Sq.mts. ( 286 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK26.63 Sq.mts. ( 287 Sq.ft. )5
5 Booked100% Booked
100% Booked
1 BHK26.67 Sq.mts. ( 287 Sq.ft. )5
5 Booked100% Booked
100% Booked
28 total apartments / 28 apartments booked. 100% apartments booked.
Work Description in Building GCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

H

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
HDec 20215100050
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK30.13 Sq.mts. ( 324 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK30.16 Sq.mts. ( 325 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK42.42 Sq.mts. ( 457 Sq.ft. )5
5 Booked100% Booked
100% Booked
13 total apartments / 13 apartments booked. 100% apartments booked.
Work Description in Building HCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

I

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
IDec 20215100020
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK21.03 Sq.mts. ( 226 Sq.ft. )9
7 Booked77% Booked
77% Booked
1 BHK32.55 Sq.mts. ( 350 Sq.ft. )17
11 Booked64% Booked
64% Booked
Shop11.77 Sq.mts. ( 127 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop12.04 Sq.mts. ( 130 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop15.79 Sq.mts. ( 170 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop16.06 Sq.mts. ( 173 Sq.ft. )1
1 Booked100% Booked
100% Booked
30 total apartments / 21 apartments booked. 70% apartments booked.
Work Description in Building ICompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress40% done
40% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

K

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
KDec 20215100020
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.44 Sq.mts. ( 338 Sq.ft. )17
Shop10.27 Sq.mts. ( 111 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop11.22 Sq.mts. ( 121 Sq.ft. )2
1 Booked50% Booked
50% Booked
Shop15.56 Sq.mts. ( 167 Sq.ft. )2
None Booked0% Booked
0% Booked
22 total apartments / 2 apartments booked. 9% apartments booked.
Work Description in Building KCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

L

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
LDec 20215100020
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK30.39 Sq.mts. ( 327 Sq.ft. )5
3 Booked60% Booked
60% Booked
1 BHK31.23 Sq.mts. ( 336 Sq.ft. )13
8 Booked61% Booked
61% Booked
18 total apartments / 11 apartments booked. 61% apartments booked.
Work Description in Building LCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

M

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
MDec 20215100020
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.46 Sq.mts. ( 349 Sq.ft. )9
5 Booked55% Booked
55% Booked
1 BHK32.69 Sq.mts. ( 352 Sq.ft. )10
5 Booked50% Booked
50% Booked
19 total apartments / 10 apartments booked. 52% apartments booked.
Work Description in Building MCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

N

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
NDec 202181010010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.11 Sq.mts. ( 346 Sq.ft. )7
None Booked0% Booked
0% Booked
1 BHK32.33 Sq.mts. ( 348 Sq.ft. )7
3 Booked42% Booked
42% Booked
1 BHK33.11 Sq.mts. ( 356 Sq.ft. )7
2 Booked28% Booked
28% Booked
1 BHK33.22 Sq.mts. ( 358 Sq.ft. )7
5 Booked71% Booked
71% Booked
1 BHK35.63 Sq.mts. ( 384 Sq.ft. )7
3 Booked42% Booked
42% Booked
1 BHK42.33 Sq.mts. ( 456 Sq.ft. )14
10 Booked71% Booked
71% Booked
2 BHK45.96 Sq.mts. ( 495 Sq.ft. )7
3 Booked42% Booked
42% Booked
2 BHK46.24 Sq.mts. ( 498 Sq.ft. )7
6 Booked85% Booked
85% Booked
2 BHK50.12 Sq.mts. ( 539 Sq.ft. )7
6 Booked85% Booked
85% Booked
70 total apartments / 38 apartments booked. 54% apartments booked.
Work Description in Building NCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Channel Partners
Channel Partners Registered by Developer
Mirador Dewellers Pvt Ltd
for Project
Mirador Utsav Phase 1
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation