Project overview

Midtown Bay is a MahaRERA Registered Project bearing MahaRERA Registration Number P51900030390. Midtown Bay is located at Final Plot No.646. This is a New being developed by Rising Sun Impex Private Limited.

Midtown Bay has 1 BHK & 2 BHK Apartments with carpet areas ranging from 365 to 580 Sq.ft. Carpet. The Project has total 446 of which 166 are currently available for sale.

Midtown Bay is being developed on a total land area of 29968 Sq.ft. out of which 4099 Sq.ft. i.e 14% is reserved for recreational purposes. Midtown Bay has 1 Wings / Towers Midtown Bay

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Midtown Bay
  • Location:
  • Final Plot No.646
  • Const. Stage:
    New
  • Possession:
    31 Dec 2027
Developer Details

  • Developer:
    Rising Sun Impex Private Limited
  • Phone:
  • Address:
  • Building No.3, A-Wing
Project RERA Details
MAHA REARA No: P51900030390
Project Type Residential / Group Housing
RERA Project Status New
Funding Bank ICICI BANK LIMITED
Proposed Possession 31 Dec 2027
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 17 Aug 2021
Last Retrived 26 Jul 2025
Midtown Bay QR Code
Midtown Bay
MahaRERA - P51900030390
Apartment Details & Configuration
TypeArea
1 BHK33.91 Sq.mts. ( 365 Sq.ft. )
1 BHK34.18 Sq.mts. ( 368 Sq.ft. )
1 BHK39.2 Sq.mts. ( 422 Sq.ft. )
2 BHK52.03 Sq.mts. ( 560 Sq.ft. )
2 BHK52.4 Sq.mts. ( 564 Sq.ft. )
2 BHK53.88 Sq.mts. ( 580 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Midtown Baylast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
As Per Approved Plans
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
As Per Approved Plans
Energy management
As Per Approved Plans
Fire Protection And Fire Safety Requirements
As Per Approved Plans
Landscaping & Tree Planting
As Per Approved Plans
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
As Per Approved Plans
Solid Waste Management And Disposal
As Per Approved Plans
Storm Water Drains
As Per Approved Plans
Street Lighting
As Per Approved Plans
Swimming Pool and Fitness Center
As Per Approved Plans
Treatment And Disposal Of Sewage And Sullage Water
As Per Approved Plans
Water Conservation, Rain water Harvesting
As Per Approved Plans
Water Supply
As Per Approved Plans
Buildings / Wings in Midtown Bay
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Midtown Bay by Rising Sun Impex Private Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

29968 Sq. ft.

Project Area

4099 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

446 apartments in total
Total
446
Booked
280
Available
166

Saleable Area Statistics (Sq. ft.)

222640 Total
Total
222640
Booked
135238
Available
87403
Total 446 apartments in project. 280 apartments booked. 62% apartments booked.
Total 222640 Sq.ft. saleable area. 135238 saleable area booked.
61% area booked.

Midtown Bay

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Midtown BayDec 202738120110432
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK33.91 Sq.mts. ( 365 Sq.ft. )112
100 Booked89% Booked
89% Booked
1 BHK34.18 Sq.mts. ( 368 Sq.ft. )40
16 Booked40% Booked
40% Booked
1 BHK39.2 Sq.mts. ( 422 Sq.ft. )5
5 Booked100% Booked
100% Booked
2 BHK52.03 Sq.mts. ( 560 Sq.ft. )104
66 Booked63% Booked
63% Booked
2 BHK52.4 Sq.mts. ( 564 Sq.ft. )38
10 Booked26% Booked
26% Booked
2 BHK53.88 Sq.mts. ( 580 Sq.ft. )147
83 Booked56% Booked
56% Booked
446 total apartments / 280 apartments booked. 62% apartments booked.
Work Description in Building Midtown BayCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress85% done
85% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress65% done
65% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress63% done
63% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress60% done
60% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress70% done
70% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
work-in-progress95% done
95% Booked
Channel Partners
Channel Partners Registered by Developer
Rising Sun Impex Private Limited
for Project
Midtown Bay
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation