Project overview
Medinee Niketan is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800017639. Medinee Niketan is located at Bamanwada. This is a New Project being developed by Ss Enterprise.
Medinee Niketan has 1, 2, 3, 4, 5, 6 & 7 Apartments with carpet areas ranging from 346 to 559 Sq.ft. Carpet. The Project has total 57 of which 56 are currently available for sale.
Medinee Niketan is being developed on a total land area of 21119 Sq.ft. Medinee Niketan has 4 Wings / Towers A,B,C,D
| Project | Developer | Location | Possession |
-
Project:
Medinee Niketan
-
Location:
-
Bamanwada
-
Const. Stage:
New Project
-
Possession:
30 Dec 2021
-
Developer:
Ss Enterprise
-
Phone:
-
Address:
-
Office 7, Floor 1, Shantinath Shopping Center, Sv Road, Shantinath Shopping Center, Malad (W), 400064
| MAHA REARA No: |
P51800017639 |
| Project Type |
Residential |
| RERA Project Status |
New Project |
| Funding Bank |
IDBI BANK |
| Proposed Possession |
30 Dec 2021 |
| Revised Possession |
|
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
14 Feb 2023 |
| Last Retrived |
28 Jul 2025 |
Medinee Niketan QR Code
Medinee Niketan
MahaRERA - P51800017639
| Type | Area |
| 3 | 54.93 Sq.mts. ( 591 Sq.ft. ) |
| 6 | 47.59 Sq.mts. ( 512 Sq.ft. ) |
| 1 | 35.73 Sq.mts. ( 385 Sq.ft. ) |
| 2 | 38.18 Sq.mts. ( 411 Sq.ft. ) |
| 3 | 52.1 Sq.mts. ( 561 Sq.ft. ) |
| 4 | 37.35 Sq.mts. ( 402 Sq.ft. ) |
| 1 | 38.53 Sq.mts. ( 415 Sq.ft. ) |
| 2 | 32.13 Sq.mts. ( 346 Sq.ft. ) |
| 3 | 37.62 Sq.mts. ( 405 Sq.ft. ) |
| 4 | 38.55 Sq.mts. ( 415 Sq.ft. ) |
| 5 | 51.97 Sq.mts. ( 559 Sq.ft. ) |
| 6 | 38.68 Sq.mts. ( 416 Sq.ft. ) |
| 7 | 40.34 Sq.mts. ( 434 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Medinee Niketanlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station
|
|
Prior To Oc |
|
|
|
Prior To Oc |
Fire Protection And Fire Safety
Requirements
|
|
Prior To Oc |
Landscaping & Tree Planting50% completed
|
|
Prior To Oc |
|
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
|
|
Complete |
Solid Waste Management And Disposal
|
|
Prior To Oc |
Storm Water Drains90% completed
|
|
Nearing Completion |
|
|
|
Na |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Prior To Oc |
Water Conservation, Rain water Harvesting90% completed
|
|
Neraing Completion |
|
|
|
Prior To Oc |
Buildings / Wings in Medinee Niketan
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Medinee Niketan by Ss Enterpriselast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
57
apartments in total
Saleable Area Statistics (Sq. ft.)
25871
Total
Total 57 apartments in project. 1 apartments booked. 1% apartments booked.
Total 25871 Sq.ft. saleable area. 434 saleable area booked.
2% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| A | Dec 2020 | 8 | 1 | 0 | 1 | 0 | 0 | 1 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 3 | 54.93 Sq.mts. ( 591 Sq.ft. ) | 1 | |
1 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building A | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| B | Dec 2020 | 8 | 1 | 0 | 1 | 0 | 0 | 1 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 6 | 47.59 Sq.mts. ( 512 Sq.ft. ) | 1 | |
1 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building B | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| C | Dec 2020 | 8 | 1 | 0 | 0 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 | 35.73 Sq.mts. ( 385 Sq.ft. ) | 1 | |
| 2 | 38.18 Sq.mts. ( 411 Sq.ft. ) | 8 | |
| 3 | 52.1 Sq.mts. ( 561 Sq.ft. ) | 7 | |
| 4 | 37.35 Sq.mts. ( 402 Sq.ft. ) | 7 | |
23 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building C | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| D | Dec 2020 | 8 | 1 | 0 | 0 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 | 38.53 Sq.mts. ( 415 Sq.ft. ) | 1 | |
| 2 | 32.13 Sq.mts. ( 346 Sq.ft. ) | 1 | |
| 3 | 37.62 Sq.mts. ( 405 Sq.ft. ) | 1 | |
| 4 | 38.55 Sq.mts. ( 415 Sq.ft. ) | 8 | |
| 5 | 51.97 Sq.mts. ( 559 Sq.ft. ) | 7 | |
| 6 | 38.68 Sq.mts. ( 416 Sq.ft. ) | 7 | |
| 7 | 40.34 Sq.mts. ( 434 Sq.ft. ) | 7 | |
32 total apartments / 1 apartments booked. 3% apartments booked. |
| Work Description in Building D | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Ss Enterprise
for Project
Medinee Niketan
last updated on
28 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |