Project overview
Mangal Villa C.H.S is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700028805. Mangal Villa C.H.S is located at Mangal Villa Co.Op Housing Society Badlapur, 421503, Opp Water Supply Office. This is a New Project being developed by Shree Sai Enterprises.
Mangal Villa C.H.S has 1 BHK, 1RK & Shop Apartments with carpet areas ranging from 1300 to 1060 Sq.ft. Carpet. The Project has total 18 of which 8 are currently available for sale.
Mangal Villa C.H.S is being developed on a total land area of 5543 Sq.ft. out of which 5543 Sq.ft. i.e 100% is reserved for recreational purposes. Mangal Villa C.H.S has 1 Wings / Towers Mangal Villa Chs
| Project | Developer | Location | Possession |
-
Developer:
Shree Sai Enterprises
-
Phone:
-
Address:
-
A 203, Harsh Sagar Society C.H.S, Shiv Mandir Road, Opp Kunal Ice-Cream, Shiv Basav Nagar, 421501
| MAHA REARA No: |
P51700028805 |
| Project Type |
Residential |
| RERA Project Status |
New Project |
| Funding Bank |
CORPORATION BANK |
| Proposed Possession |
02 Sep 2022 |
| Revised Possession |
|
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
20 Oct 2023 |
| Last Retrived |
28 Jul 2025 |
Mangal Villa C.H.S QR Code
Mangal Villa C.H.S
MahaRERA - P51700028805
| Type | Area |
| 1 BHK | 120.76 Sq.mts. ( 1300 Sq.ft. ) |
| 1 BHK | 274.96 Sq.mts. ( 2960 Sq.ft. ) |
| 1 BHK | 28.8 Sq.mts. ( 310 Sq.ft. ) |
| 1RK | 98.44 Sq.mts. ( 1060 Sq.ft. ) |
| Shop | 9.95 Sq.mts. ( 107 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Mangal Villa C.H.Slast updated on 28 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Water Conservation, Rain water Harvesting100% completed
|
|
Rain Water Harvesting Only |
Water Supply100% completed
|
|
As Per Water Supply Norms |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
|
|
|
Na |
Storm Water Drains100% completed
|
|
As Per Storm Water Norms |
Solid Waste Management And Disposal
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
|
|
Direct To Municipal Sewer Line |
|
|
|
Na |
Landscaping & Tree Planting
|
|
Na |
Fire Protection And Fire Safety
Requirements
|
|
Na |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station100% completed
|
|
Only Space For Electric Meters |
|
|
|
Na |
Aggregate area of recreational Open Space
|
|
Na |
Buildings / Wings in Mangal Villa C.H.S
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Mangal Villa C.H.S by Shree Sai Enterpriseslast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
18
apartments in total
Saleable Area Statistics (Sq. ft.)
33532
Total
Total 18 apartments in project. 10 apartments booked. 55% apartments booked.
Total 33532 Sq.ft. saleable area. 20337 saleable area booked.
61% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Mangal Villa Chs | Feb 2022 | 5 | 1 | 0 | 0 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 120.76 Sq.mts. ( 1300 Sq.ft. ) | 4 | |
| 1 BHK | 274.96 Sq.mts. ( 2960 Sq.ft. ) | 8 | |
| 1 BHK | 28.8 Sq.mts. ( 310 Sq.ft. ) | 1 | |
| 1RK | 98.44 Sq.mts. ( 1060 Sq.ft. ) | 4 | |
| Shop | 9.95 Sq.mts. ( 107 Sq.ft. ) | 1 | |
18 total apartments / 10 apartments booked. 55% apartments booked. |
| Work Description in Building Mangal Villa Chs | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Shree Sai Enterprises
for Project
Mangal Villa C.H.S
last updated on
28 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |