Project overview

MAITRY HEIGHTS is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000005628. MAITRY HEIGHTS is located at 65,46,66 Part. This is a Ongoing being developed by RAJ MAITRY & ESKON DEVELOPERS.

MAITRY HEIGHTS has 1 BHK Apartments with carpet areas ranging from 329 to 367 Sq.ft. Carpet. The Project has total 437 of which 99 are currently available for sale.

MAITRY HEIGHTS is being developed on a total land area of 44391 Sq.ft. out of which 6144 Sq.ft. i.e 14% is reserved for recreational purposes. MAITRY HEIGHTS has 5 Wings / Towers Wing A,Wing B,Wing C,Wing D,Wing E

ProjectDeveloperLocationPossession
Project Details
  • Project:
    MAITRY HEIGHTS
  • Location:
  • 65,46,66 Part
  • Const. Stage:
    Ongoing
  • Possession:
    31 Jul 2019
Developer Details

  • Developer:
    RAJ MAITRY & ESKON DEVELOPERS
  • Phone:
  • Address:
  • Maitry Heights
Project RERA Details
MAHA REARA No: P99000005628
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Ajay Wade And Associates
Funding Bank
Proposed Possession 31 Jul 2019
Revised Possession 31 Jul 2019
Extended Possession 31 Dec 2024
Litigations No Litigations
Last Modified 25 May 2022
Last Retrived 14 Feb 2026
MAITRY HEIGHTS QR Code
MAITRY HEIGHTS
MahaRERA - P99000005628
Apartment Details & Configuration
TypeArea
1 BHK36.39 Sq.mts. ( 392 Sq.ft. )
1 BHK37.78 Sq.mts. ( 407 Sq.ft. )
2 BHK41.88 Sq.mts. ( 451 Sq.ft. )
2 BHK42.66 Sq.mts. ( 459 Sq.ft. )
2 BHK44.46 Sq.mts. ( 479 Sq.ft. )
2 BHK44.94 Sq.mts. ( 484 Sq.ft. )
2 BHK45.17 Sq.mts. ( 486 Sq.ft. )
2 BHK45.73 Sq.mts. ( 492 Sq.ft. )
SHOP NO 0124.28 Sq.mts. ( 261 Sq.ft. )
SHOP NO 0617.47 Sq.mts. ( 188 Sq.ft. )
SHOP NO 0713.38 Sq.mts. ( 144 Sq.ft. )
SHOP NO 1016.11 Sq.mts. ( 173 Sq.ft. )
SHOPNO2.3.4.5.8.915.29 Sq.mts. ( 165 Sq.ft. )
1 BHK34.54 Sq.mts. ( 372 Sq.ft. )
1 BHK35.3 Sq.mts. ( 380 Sq.ft. )
2 BHK46.31 Sq.mts. ( 498 Sq.ft. )
2 BHK46.85 Sq.mts. ( 504 Sq.ft. )
SHOP NO 12.1514.26 Sq.mts. ( 153 Sq.ft. )
SHOP NO 1841.32 Sq.mts. ( 445 Sq.ft. )
SHOP NO 1916.45 Sq.mts. ( 177 Sq.ft. )
SHOP NO 2015.28 Sq.mts. ( 164 Sq.ft. )
SHOP NO 2115.76 Sq.mts. ( 170 Sq.ft. )
SHOPNO11.13.14.16.1715.35 Sq.mts. ( 165 Sq.ft. )
1 BHK32.99 Sq.mts. ( 355 Sq.ft. )
1 BHK33.77 Sq.mts. ( 364 Sq.ft. )
1 BHK35.37 Sq.mts. ( 381 Sq.ft. )
1 BHK35.48 Sq.mts. ( 382 Sq.ft. )
1 BHK35.91 Sq.mts. ( 387 Sq.ft. )
1 BHK36.69 Sq.mts. ( 395 Sq.ft. )
2 BHK45.63 Sq.mts. ( 491 Sq.ft. )
SHOP NO 2216.54 Sq.mts. ( 178 Sq.ft. )
SHOP NO 2314.58 Sq.mts. ( 157 Sq.ft. )
SHOP NO 24.2514.46 Sq.mts. ( 156 Sq.ft. )
SHOP NO 2613.43 Sq.mts. ( 145 Sq.ft. )
SHOP NO 2717.56 Sq.mts. ( 189 Sq.ft. )
1 BHK32.82 Sq.mts. ( 353 Sq.ft. )
1 BHK32.96 Sq.mts. ( 355 Sq.ft. )
1 BHK33.27 Sq.mts. ( 358 Sq.ft. )
1 BHK34.03 Sq.mts. ( 366 Sq.ft. )
1 BHK35.34 Sq.mts. ( 380 Sq.ft. )
2 BHK42.98 Sq.mts. ( 463 Sq.ft. )
SHOP NO 2817.58 Sq.mts. ( 189 Sq.ft. )
SHOP NO 2914.99 Sq.mts. ( 161 Sq.ft. )
SHOP NO 3015.32 Sq.mts. ( 165 Sq.ft. )
SHOP NO 3114.49 Sq.mts. ( 156 Sq.ft. )
SHOP NO 3213.46 Sq.mts. ( 145 Sq.ft. )
SHOP NO 3315.87 Sq.mts. ( 171 Sq.ft. )
1 BHK30.53 Sq.mts. ( 329 Sq.ft. )
1 BHK32.68 Sq.mts. ( 352 Sq.ft. )
1 BHK32.9 Sq.mts. ( 354 Sq.ft. )
1 BHK34.06 Sq.mts. ( 367 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of MAITRY HEIGHTSlast updated on 14 Feb 2026 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Work In Progress
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Work In Progress
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Work In Progress
Landscaping & Tree Planting100% completed
95% Complete
Facility Available In Larger Layout
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Work In Progress
Solid Waste Management And Disposal100% completed
95% Complete
Work In Progress
Storm Water Drains100% completed
95% Complete
Facility Available In Larger Layout
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Work In Progress
Water Conservation, Rain water Harvesting100% completed
95% Complete
Work In Progress
Water Supply100% completed
95% Complete
Facility Will Start Vvcmc Watersupply Commences
Buildings / Wings in MAITRY HEIGHTS
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of MAITRY HEIGHTS by RAJ MAITRY & ESKON DEVELOPERSlast updated on 14 Feb 2026 as per information obtained from MARA RERA.

44391 Sq. ft.

Project Area

6144 Sq. ft.

Recreational Open Space

Total 5

Wings / Towers in Project

Apartments Statistics

437 apartments in total
Total
437
Booked
338
Available
99

Saleable Area Statistics (Sq. ft.)

161977 Total
Total
161977
Booked
125038
Available
36939
Total 437 apartments in project. 338 apartments booked. 77% apartments booked.
Total 161977 Sq.ft. saleable area. 125038 saleable area booked.
77% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing AJul 201917101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36.39 Sq.mts. ( 392 Sq.ft. )15
11 Booked73% Booked
73% Booked
1 BHK37.78 Sq.mts. ( 407 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK41.88 Sq.mts. ( 451 Sq.ft. )13
13 Booked100% Booked
100% Booked
2 BHK42.66 Sq.mts. ( 459 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK44.46 Sq.mts. ( 479 Sq.ft. )16
13 Booked81% Booked
81% Booked
2 BHK44.94 Sq.mts. ( 484 Sq.ft. )16
14 Booked87% Booked
87% Booked
2 BHK45.17 Sq.mts. ( 486 Sq.ft. )15
14 Booked93% Booked
93% Booked
2 BHK45.73 Sq.mts. ( 492 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP NO 0124.28 Sq.mts. ( 261 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP NO 0617.47 Sq.mts. ( 188 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP NO 0713.38 Sq.mts. ( 144 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP NO 1016.11 Sq.mts. ( 173 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOPNO2.3.4.5.8.915.29 Sq.mts. ( 165 Sq.ft. )6
6 Booked100% Booked
100% Booked
88 total apartments / 74 apartments booked. 84% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress75% done
75% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress70% done
70% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress70% done
70% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress62% done
62% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress75% done
75% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress75% done
75% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress75% done
75% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BJul 201917101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK34.54 Sq.mts. ( 372 Sq.ft. )59
50 Booked84% Booked
84% Booked
1 BHK35.3 Sq.mts. ( 380 Sq.ft. )3
None Booked0% Booked
0% Booked
2 BHK46.31 Sq.mts. ( 498 Sq.ft. )15
15 Booked100% Booked
100% Booked
2 BHK46.85 Sq.mts. ( 504 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP NO 12.1514.26 Sq.mts. ( 153 Sq.ft. )2
2 Booked100% Booked
100% Booked
SHOP NO 1841.32 Sq.mts. ( 445 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP NO 1916.45 Sq.mts. ( 177 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP NO 2015.28 Sq.mts. ( 164 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP NO 2115.76 Sq.mts. ( 170 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOPNO11.13.14.16.1715.35 Sq.mts. ( 165 Sq.ft. )5
5 Booked100% Booked
100% Booked
89 total apartments / 76 apartments booked. 85% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress50% done
50% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CJul 201917101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.99 Sq.mts. ( 355 Sq.ft. )15
8 Booked53% Booked
53% Booked
1 BHK33.77 Sq.mts. ( 364 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK35.37 Sq.mts. ( 381 Sq.ft. )14
12 Booked85% Booked
85% Booked
1 BHK35.48 Sq.mts. ( 382 Sq.ft. )16
12 Booked75% Booked
75% Booked
1 BHK35.91 Sq.mts. ( 387 Sq.ft. )14
8 Booked57% Booked
57% Booked
1 BHK36.69 Sq.mts. ( 395 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK45.63 Sq.mts. ( 491 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP NO 2216.54 Sq.mts. ( 178 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP NO 2314.58 Sq.mts. ( 157 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP NO 24.2514.46 Sq.mts. ( 156 Sq.ft. )2
2 Booked100% Booked
100% Booked
SHOP NO 2613.43 Sq.mts. ( 145 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP NO 2717.56 Sq.mts. ( 189 Sq.ft. )1
1 Booked100% Booked
100% Booked
68 total apartments / 46 apartments booked. 67% apartments booked.
Work Description in Building Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress50% done
50% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing DJul 201917101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.82 Sq.mts. ( 353 Sq.ft. )30
20 Booked66% Booked
66% Booked
1 BHK32.96 Sq.mts. ( 355 Sq.ft. )16
8 Booked50% Booked
50% Booked
1 BHK33.27 Sq.mts. ( 358 Sq.ft. )27
21 Booked77% Booked
77% Booked
1 BHK34.03 Sq.mts. ( 366 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK35.34 Sq.mts. ( 380 Sq.ft. )16
13 Booked81% Booked
81% Booked
2 BHK42.98 Sq.mts. ( 463 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP NO 2817.58 Sq.mts. ( 189 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP NO 2914.99 Sq.mts. ( 161 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP NO 3015.32 Sq.mts. ( 165 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP NO 3114.49 Sq.mts. ( 156 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP NO 3213.46 Sq.mts. ( 145 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP NO 3315.87 Sq.mts. ( 171 Sq.ft. )1
1 Booked100% Booked
100% Booked
98 total apartments / 69 apartments booked. 70% apartments booked.
Work Description in Building Wing DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress50% done
50% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing EJul 201917101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK30.53 Sq.mts. ( 329 Sq.ft. )30
21 Booked70% Booked
70% Booked
1 BHK32.68 Sq.mts. ( 352 Sq.ft. )16
13 Booked81% Booked
81% Booked
1 BHK32.82 Sq.mts. ( 353 Sq.ft. )16
12 Booked75% Booked
75% Booked
1 BHK32.9 Sq.mts. ( 354 Sq.ft. )16
12 Booked75% Booked
75% Booked
1 BHK34.06 Sq.mts. ( 367 Sq.ft. )16
15 Booked93% Booked
93% Booked
94 total apartments / 73 apartments booked. 77% apartments booked.
Work Description in Building Wing ECompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress50% done
50% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
RAJ MAITRY & ESKON DEVELOPERS
for Project
MAITRY HEIGHTS
last updated on 14 Feb 2026 as per information obtained from MARA RERA.
Name Company Location Mobile Designation