Project overview

Maitri Enclave is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800053925. Maitri Enclave is located at 2865Y, 2912 To 2921, 2933,2969, 2970 To 2978. This is a New being developed by Atharva Enterprises.

Maitri Enclave has 1 BHK Apartments with carpet areas ranging from 297 to 441 Sq.ft. Carpet. The Project has total 35 of which 35 are currently available for sale.

Maitri Enclave is being developed on a total land area of 20221 Sq.ft. out of which 2911 Sq.ft. i.e 14% is reserved for recreational purposes. Maitri Enclave has 3 Wings / Towers Maitri Enclave - Wing A,Maitri Enclave - Wing B,Maitri Enclave - Wing C

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Maitri Enclave
  • Location:
  • 2865Y, 2912 To 2921, 2933,2969, 2970 To 2978
  • Const. Stage:
    New
  • Possession:
    31 Dec 2026
Developer Details

  • Developer:
    Atharva Enterprises
  • Phone:
  • Address:
  • Atharva House
Project RERA Details
MAHA REARA No: P51800053925
Project Type Residential / Group Housing
RERA Project Status New
Architect Ar. Sumedha Gore
Funding Bank BANK OF MAHARASHTRA
Proposed Possession 31 Dec 2026
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 11 Dec 2023
Last Retrived 26 Jul 2025
Maitri Enclave QR Code
Maitri Enclave
MahaRERA - P51800053925
Apartment Details & Configuration
TypeArea
2 BHK49.86 Sq.mts. ( 537 Sq.ft. )
2 BHK50.36 Sq.mts. ( 542 Sq.ft. )
2 BHK50.53 Sq.mts. ( 544 Sq.ft. )
2 BHK50.82 Sq.mts. ( 547 Sq.ft. )
1 BHK31.55 Sq.mts. ( 340 Sq.ft. )
1 BHK40.84 Sq.mts. ( 440 Sq.ft. )
1 BHK45.15 Sq.mts. ( 486 Sq.ft. )
1 BHK61.49 Sq.mts. ( 662 Sq.ft. )
2 BHK65.81 Sq.mts. ( 708 Sq.ft. )
2 BHK53.96 Sq.mts. ( 581 Sq.ft. )
1 BHK27.55 Sq.mts. ( 297 Sq.ft. )
1 BHK30.91 Sq.mts. ( 333 Sq.ft. )
1 BHK31.12 Sq.mts. ( 335 Sq.ft. )
1 BHK35.73 Sq.mts. ( 385 Sq.ft. )
1 BHK40.94 Sq.mts. ( 441 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Maitri Enclavelast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Substation. Electric Meter Room Will Be Provided
Energy management
Na
Fire Protection And Fire Safety Requirements
As Per Cfo Noc. Yet To Start
Landscaping & Tree Planting
As Per Tree Noc
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Yet To Start
Solid Waste Management And Disposal
As Per Swm Noc
Storm Water Drains
Yet To Start
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Na
Water Supply
Subject To Water Mode Available Bymcgm.Yet Tostart
Buildings / Wings in Maitri Enclave
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Maitri Enclave by Atharva Enterpriseslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

20221 Sq. ft.

Project Area

2911 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

35 apartments in total
Total
35
Booked
0
Available
35

Saleable Area Statistics (Sq. ft.)

17512 Total
Total
17512
Booked
0
Available
17512
Total 35 apartments in project. 0 apartments booked. 0% apartments booked.
Total 17512 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.

Maitri Enclave - Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Maitri Enclave - Wing ADec 202651110019
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK49.86 Sq.mts. ( 537 Sq.ft. )4
None Booked0% Booked
0% Booked
2 BHK50.36 Sq.mts. ( 542 Sq.ft. )5
None Booked0% Booked
0% Booked
2 BHK50.53 Sq.mts. ( 544 Sq.ft. )4
None Booked0% Booked
0% Booked
2 BHK50.82 Sq.mts. ( 547 Sq.ft. )5
None Booked0% Booked
0% Booked
18 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Maitri Enclave - Wing ACompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Maitri Enclave - Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Maitri Enclave - Wing BDec 202621110017
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.55 Sq.mts. ( 340 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK40.84 Sq.mts. ( 440 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK45.15 Sq.mts. ( 486 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK61.49 Sq.mts. ( 662 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK65.81 Sq.mts. ( 708 Sq.ft. )2
None Booked0% Booked
0% Booked
2 BHK53.96 Sq.mts. ( 581 Sq.ft. )2
None Booked0% Booked
0% Booked
10 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Maitri Enclave - Wing BCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Maitri Enclave - Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Maitri Enclave - Wing CDec 202621110016
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK27.55 Sq.mts. ( 297 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK30.91 Sq.mts. ( 333 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK31.12 Sq.mts. ( 335 Sq.ft. )3
None Booked0% Booked
0% Booked
1 BHK35.73 Sq.mts. ( 385 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK40.94 Sq.mts. ( 441 Sq.ft. )1
None Booked0% Booked
0% Booked
7 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Maitri Enclave - Wing CCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Atharva Enterprises
for Project
Maitri Enclave
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation