Project overview

Mahindra Happinest Palghar Phase - Iii is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000016671. Mahindra Happinest Palghar Phase - Iii is located at 158 183 P 183 P Plot No 1. This is a New being developed by Mahindra Happinest Developers Limited(Formerly Known As Mahindra Happinest Developers Pvt. Ltd).

Mahindra Happinest Palghar Phase - Iii has 1 BHK, 1 BHK G, 1 BHK GF, 2 BHK & 2 BKH GF Apartments with carpet areas ranging from 328 to 515 Sq.ft. Carpet. The Project has total 120 of which 43 are currently available for sale.

Mahindra Happinest Palghar Phase - Iii is being developed on a total land area of 35854 Sq.ft. Mahindra Happinest Palghar Phase - Iii has 3 Wings / Towers Block 10,Block 11,Block No 2

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Mahindra Happinest Palghar Phase - Iii
  • Location:
  • 158 183 P 183 P Plot No 1
  • Const. Stage:
    New
  • Possession:
    30 Sep 2022
Developer Details

  • Developer:
    Mahindra Happinest Developers Limited(Formerly Known As Mahindra Happinest Developers Pvt. Ltd)
  • Phone:
  • Address:
  • Mahindra Towers
Project RERA Details
MAHA REARA No: P99000016671
Project Type Residential / Group Housing
RERA Project Status New
Architect Ashok B Lall Architects
Funding Bank HDFC BANK
Proposed Possession 30 Sep 2022
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 18 Dec 2021
Last Retrived 28 Jul 2025
Mahindra Happinest Palghar Phase - Iii QR Code
Mahindra Happinest Palghar Phase - Iii
MahaRERA - P99000016671
Apartment Details & Configuration
TypeArea
1 BHK30.44 Sq.mts. ( 328 Sq.ft. )
1 BHK G34.3 Sq.mts. ( 369 Sq.ft. )
1 BHK GF36.35 Sq.mts. ( 391 Sq.ft. )
2 BHK44 Sq.mts. ( 474 Sq.ft. )
2 BHK GF47.84 Sq.mts. ( 515 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Mahindra Happinest Palghar Phase - Iiilast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Sub Station Work Completed
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Not Yet Started
Open Parking
Not Yet Started
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Stp Work Completed
Solid Waste Management And Disposal100% completed
95% Complete
Completed
Storm Water Drains
Not Yet Started
Street Lighting
Not Yet Started
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Completed
Water Conservation, Rain water Harvesting100% completed
95% Complete
Completed
Water Supply
Not Yet Started
Buildings / Wings in Mahindra Happinest Palghar Phase - Iii
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Mahindra Happinest Palghar Phase - Iii by Mahindra Happinest Developers Limited(Formerly Known As Mahindra Happinest Developers Pvt. Ltd)last updated on 28 Jul 2025 as per information obtained from MARA RERA.

35854 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

120 apartments in total
Total
120
Booked
77
Available
43

Saleable Area Statistics (Sq. ft.)

48898 Total
Total
48898
Booked
29923
Available
18975
Total 120 apartments in project. 77 apartments booked. 64% apartments booked.
Total 48898 Sq.ft. saleable area. 29923 saleable area booked.
61% area booked.

Block 10

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Block 10Sep 20215100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK30.44 Sq.mts. ( 328 Sq.ft. )16
15 Booked93% Booked
93% Booked
1 BHK G34.3 Sq.mts. ( 369 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK GF36.35 Sq.mts. ( 391 Sq.ft. )4
1 Booked25% Booked
25% Booked
2 BHK44 Sq.mts. ( 474 Sq.ft. )16
11 Booked68% Booked
68% Booked
2 BHK GF47.84 Sq.mts. ( 515 Sq.ft. )3
None Booked0% Booked
0% Booked
40 total apartments / 27 apartments booked. 67% apartments booked.
Work Description in Building Block 10Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor

Block 11

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Block 11Sep 20215100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK30.44 Sq.mts. ( 328 Sq.ft. )16
16 Booked100% Booked
100% Booked
1 BHK G34.3 Sq.mts. ( 369 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK GF36.35 Sq.mts. ( 391 Sq.ft. )4
1 Booked25% Booked
25% Booked
2 BHK44 Sq.mts. ( 474 Sq.ft. )16
14 Booked87% Booked
87% Booked
2 BHK GF47.84 Sq.mts. ( 515 Sq.ft. )3
None Booked0% Booked
0% Booked
40 total apartments / 31 apartments booked. 77% apartments booked.
Work Description in Building Block 11Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor

Block No 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Block No 2Sep 20215100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK30.44 Sq.mts. ( 328 Sq.ft. )16
12 Booked75% Booked
75% Booked
1 BHK G34.3 Sq.mts. ( 369 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK GF36.35 Sq.mts. ( 391 Sq.ft. )4
None Booked0% Booked
0% Booked
2 BHK44 Sq.mts. ( 474 Sq.ft. )16
6 Booked37% Booked
37% Booked
2 BKH GF47.84 Sq.mts. ( 515 Sq.ft. )3
None Booked0% Booked
0% Booked
40 total apartments / 19 apartments booked. 47% apartments booked.
Work Description in Building Block No 2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Channel Partners
Channel Partners Registered by Developer
Mahindra Happinest Developers Limited(Formerly Known As Mahindra Happinest Developers Pvt. Ltd)
for Project
Mahindra Happinest Palghar Phase - Iii
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation