Project overview
Mahindra Happinest Palghar-2 Phase 1 is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000026225. Mahindra Happinest Palghar-2 Phase 1 is located at 158/ 183 P/ 183 P/ Plot No. 2. This is a New being developed by Mahindra Happinest Developers Limited(Formerly Known As Mahindra Happinest Developers Pvt. Ltd).
Mahindra Happinest Palghar-2 Phase 1 has 1 BHK A & STUDIO Apartments with carpet areas ranging from 157 to 290 Sq.ft. Carpet. The Project has total 485 of which 164 are currently available for sale.
Mahindra Happinest Palghar-2 Phase 1 is being developed on a total land area of 152161 Sq.ft. out of which 17665 Sq.ft. i.e 12% is reserved for recreational purposes. Mahindra Happinest Palghar-2 Phase 1 has 7 Wings / Towers Block 5 Wing A,Block 5 Wing B,Block 6 Wing A,Block 7 Wing A,Block 7 Wing B,Block 8 Wing A,Block 8 Wing B
| Project | Developer | Location | Possession |
| MAHA REARA No: |
P99000026225 |
| Project Type |
Residential / Group Housing |
| RERA Project Status |
New |
| Funding Bank |
HDFC BANK |
| Proposed Possession |
30 Dec 2024 |
| Revised Possession |
|
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
05 Dec 2024 |
| Last Retrived |
28 Jul 2025 |
Mahindra Happinest Palghar-2 Phase 1 QR Code
Mahindra Happinest Palghar-2 Phase 1
MahaRERA - P99000026225
| Type | Area |
| 1 BHK B | 36.28 Sq.mts. ( 391 Sq.ft. ) |
| 1 BHK C | 34.35 Sq.mts. ( 370 Sq.ft. ) |
| 2 BHK A | 50.36 Sq.mts. ( 542 Sq.ft. ) |
| 2 BHK B | 47.89 Sq.mts. ( 515 Sq.ft. ) |
| 2 BHK C | 47.98 Sq.mts. ( 516 Sq.ft. ) |
| 2 BHK D | 50.5 Sq.mts. ( 544 Sq.ft. ) |
| 1 BHK A | 26.96 Sq.mts. ( 290 Sq.ft. ) |
| STUDIO | 14.63 Sq.mts. ( 157 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Mahindra Happinest Palghar-2 Phase 1last updated on 28 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Not Yet Started |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station
|
|
Not Yet Started |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements
|
|
Na |
Landscaping & Tree Planting
|
|
Not Yet Started |
|
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)75% completed
|
|
Not Yet Started |
Solid Waste Management And Disposal
|
|
Not Yet Started |
Storm Water Drains10% completed
|
|
Not Yet Started |
|
|
|
Not Yet Started |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting
|
|
Not Yet Started |
|
|
|
Not Yet Started |
Buildings / Wings in Mahindra Happinest Palghar-2 Phase 1
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Mahindra Happinest Palghar-2 Phase 1 by Mahindra Happinest Developers Limited(Formerly Known As Mahindra Happinest Developers Pvt. Ltd)last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
485
apartments in total
Saleable Area Statistics (Sq. ft.)
120267
Total
Total 485 apartments in project. 321 apartments booked. 66% apartments booked.
Total 120267 Sq.ft. saleable area. 76453 saleable area booked.
64% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Block 5 Wing A | Jun 2024 | 5 | 1 | 0 | 0 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK B | 36.28 Sq.mts. ( 391 Sq.ft. ) | 30 | |
| 1 BHK C | 34.35 Sq.mts. ( 370 Sq.ft. ) | 1 | |
| 2 BHK A | 50.36 Sq.mts. ( 542 Sq.ft. ) | 8 | |
| 2 BHK B | 47.89 Sq.mts. ( 515 Sq.ft. ) | 1 | |
40 total apartments / 25 apartments booked. 62% apartments booked. |
| Work Description in Building Block 5 Wing A | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Block 5 Wing B | Jun 2024 | 5 | 1 | 0 | 0 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK B | 36.28 Sq.mts. ( 391 Sq.ft. ) | 45 | |
| 1 BHK C | 34.35 Sq.mts. ( 370 Sq.ft. ) | 1 | |
| 2 BHK A | 50.36 Sq.mts. ( 542 Sq.ft. ) | 4 | |
| 2 BHK C | 47.98 Sq.mts. ( 516 Sq.ft. ) | 1 | |
| 2 BHK D | 50.5 Sq.mts. ( 544 Sq.ft. ) | 4 | |
55 total apartments / 37 apartments booked. 67% apartments booked. |
| Work Description in Building Block 5 Wing B | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Block 6 Wing A | Jun 2024 | 5 | 1 | 0 | 0 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK A | 26.96 Sq.mts. ( 290 Sq.ft. ) | 59 | |
59 total apartments / 34 apartments booked. 57% apartments booked. |
| Work Description in Building Block 6 Wing A | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Block 7 Wing A | Jun 2024 | 5 | 1 | 0 | 0 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK A | 26.96 Sq.mts. ( 290 Sq.ft. ) | 25 | |
| STUDIO | 14.63 Sq.mts. ( 157 Sq.ft. ) | 64 | |
89 total apartments / 41 apartments booked. 46% apartments booked. |
| Work Description in Building Block 7 Wing A | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Block 7 Wing B | Jun 2024 | 5 | 1 | 0 | 0 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK A | 26.96 Sq.mts. ( 290 Sq.ft. ) | 15 | |
| STUDIO | 14.63 Sq.mts. ( 157 Sq.ft. ) | 54 | |
69 total apartments / 63 apartments booked. 91% apartments booked. |
| Work Description in Building Block 7 Wing B | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Block 8 Wing A | Jun 2024 | 5 | 1 | 0 | 0 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK A | 26.96 Sq.mts. ( 290 Sq.ft. ) | 15 | |
| STUDIO | 14.63 Sq.mts. ( 157 Sq.ft. ) | 54 | |
69 total apartments / 58 apartments booked. 84% apartments booked. |
| Work Description in Building Block 8 Wing A | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Block 8 Wing B | Jun 2024 | 5 | 1 | 0 | 0 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK A | 26.96 Sq.mts. ( 290 Sq.ft. ) | 30 | |
| STUDIO | 14.63 Sq.mts. ( 157 Sq.ft. ) | 74 | |
104 total apartments / 63 apartments booked. 60% apartments booked. |
| Work Description in Building Block 8 Wing B | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
Channel Partners Registered by Developer
Mahindra Happinest Developers Limited(Formerly Known As Mahindra Happinest Developers Pvt. Ltd)
for Project
Mahindra Happinest Palghar-2 Phase 1
last updated on
28 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |