Project overview
Mahavir Kalp is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000021428. Mahavir Kalp is located at 190A1a11, 835. This is a New being developed by Rajesh Builders.
Mahavir Kalp has 1 BHK, 2 BHK & Shop Apartments with carpet areas ranging from 282 to 532 Sq.ft. Carpet. The Project has total 42 of which 42 are currently available for sale.
Mahavir Kalp is being developed on a total land area of 21530 Sq.ft. out of which 2153 Sq.ft. i.e 10% is reserved for recreational purposes. Mahavir Kalp has 1 Wings / Towers Mahavir Kalp
| Project | Developer | Location | Possession |
-
Project:
Mahavir Kalp
-
Location:
-
190A1a11, 835
-
Const. Stage:
New
-
Possession:
30 Jun 2024
-
Developer:
Rajesh Builders
-
Phone:
-
Address:
-
Mapmc
| MAHA REARA No: |
P99000021428 |
| Project Type |
Residential / Group Housing |
| RERA Project Status |
New |
| Architect |
Nishant Prabhakar Patil |
| Funding Bank |
HDFC BANK |
| Proposed Possession |
30 Jun 2024 |
| Revised Possession |
|
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
16 Jul 2019 |
| Last Retrived |
28 Jul 2025 |
Mahavir Kalp QR Code
Mahavir Kalp
MahaRERA - P99000021428
| Type | Area |
| 1 BHK | 33.13 Sq.mts. ( 357 Sq.ft. ) |
| 1 BHK | 33.86 Sq.mts. ( 364 Sq.ft. ) |
| 1 BHK | 34.11 Sq.mts. ( 367 Sq.ft. ) |
| 1 BHK | 34.4 Sq.mts. ( 370 Sq.ft. ) |
| 2 BHK | 49.42 Sq.mts. ( 532 Sq.ft. ) |
| Shop | 35.81 Sq.mts. ( 385 Sq.ft. ) |
| Shop | 41.52 Sq.mts. ( 447 Sq.ft. ) |
| Shop | 26.24 Sq.mts. ( 282 Sq.ft. ) |
| Shop | 27.69 Sq.mts. ( 298 Sq.ft. ) |
| Shop | 30.35 Sq.mts. ( 327 Sq.ft. ) |
| Shop | 31.82 Sq.mts. ( 343 Sq.ft. ) |
| Shop | 32.87 Sq.mts. ( 354 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Mahavir Kalplast updated on 28 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station100% completed
|
|
Provided |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements100% completed
|
|
Provided |
Landscaping & Tree Planting100% completed
|
|
Provided |
Open Parking100% completed
|
|
Provided |
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
|
|
Provided |
Solid Waste Management And Disposal100% completed
|
|
Provided |
Storm Water Drains100% completed
|
|
Provided |
Street Lighting100% completed
|
|
Provided |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting100% completed
|
|
Provided |
Water Supply100% completed
|
|
Provided |
Buildings / Wings in Mahavir Kalp
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Mahavir Kalp by Rajesh Builderslast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
42
apartments in total
Saleable Area Statistics (Sq. ft.)
16385
Total
Total 42 apartments in project. 0 apartments booked. 0% apartments booked.
Total 16385 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Mahavir Kalp | Jun 2023 | 8 | 1 | 0 | 1 | 0 | 10 | 4 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 33.13 Sq.mts. ( 357 Sq.ft. ) | 7 | |
| 1 BHK | 33.86 Sq.mts. ( 364 Sq.ft. ) | 1 | |
| 1 BHK | 34.11 Sq.mts. ( 367 Sq.ft. ) | 13 | |
| 1 BHK | 34.4 Sq.mts. ( 370 Sq.ft. ) | 7 | |
| 2 BHK | 49.42 Sq.mts. ( 532 Sq.ft. ) | 7 | |
| Shop | 35.81 Sq.mts. ( 385 Sq.ft. ) | 1 | |
| Shop | 41.52 Sq.mts. ( 447 Sq.ft. ) | 1 | |
| Shop | 26.24 Sq.mts. ( 282 Sq.ft. ) | 1 | |
| Shop | 27.69 Sq.mts. ( 298 Sq.ft. ) | 1 | |
| Shop | 30.35 Sq.mts. ( 327 Sq.ft. ) | 1 | |
| Shop | 31.82 Sq.mts. ( 343 Sq.ft. ) | 1 | |
| Shop | 32.87 Sq.mts. ( 354 Sq.ft. ) | 1 | |
42 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Mahavir Kalp | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
Channel Partners Registered by Developer
Rajesh Builders
for Project
Mahavir Kalp
last updated on
28 Jul 2025 as per information obtained from MARA RERA.