Project overview
Madhuban F1 F2 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700002614. Madhuban F1 F2 is located at 142 Hissa No 1. This is a Ongoing being developed by Abhilasha Venture.
Madhuban F1 F2 has 1 BHK Apartments with carpet areas ranging from 358 to 358 Sq.ft. Carpet. The Project has total 56 of which 26 are currently available for sale.
Madhuban F1 F2 is being developed on a total land area of 26372 Sq.ft. out of which 13466 Sq.ft. i.e 51% is reserved for recreational purposes. Madhuban F1 F2 has 2 Wings / Towers F1,F2
| Project | Developer | Location | Possession |
| Hira Park | M/S Hira Housing Construction Co. | 8 | 30-06-2027 00:00:00 |
| Om Sai Sankul | Om Sai Constructions | S 76/4 | 28-02-2022 00:00:00 |
| Sai Sahara Phase 1 Wing B And C | Sai Jyot Enterprises | 15/11 | 31-07-2018 00:00:00 |
| Omkar Heights | Swati Enterprises | Survey No 183 Hissa No 7,Survey No-230 Hissa No-A,B | 31-12-2017 00:00:00 |
| Charms Heights Phase-I B1-B4 | Charms Developers | S No-130 , Hissa No. 1-2 | 31-03-2018 00:00:00 |
| Charms Heights Phase-Iii B2-B3 | Charms Developers | S No-130 , Hissa No. 1-2 | 30-06-2022 00:00:00 |
| Panchamrut Bldg. No. 1 | Shree Abhilasha Nirmiti | 172/5C, 6, 7 | 31-03-2018 00:00:00 |
| Charms City Phase Ii | Gurukripa Landholding Llp | 164/2 | 31-07-2022 00:00:00 |
| Avishi Skyline Complex | J M Skyline Group | 421605, Thane | 31-07-2024 00:00:00 |
| Siddheshwar Heights A Wing From 2Nd To 14Th Floor | Shree Jai Malhar Enterprises | S No 26 Hissa No 1 To 6 | 31-12-2024 00:00:00 |
| Rusttagi Aarambha Phase-Iii | Rustagi Estates Private Limited | 83/1/B/2, 77/4/C/78/2/C, 77/4/A/78/2/A, 77/4/P/78/2/D, 77/4/B/78/2/B, 77/4/E/78/2/E, 77/4/L/78/2/L, 77/4/P/78/2/P, 77/4/J/78/2/J | 22-02-2027 00:00:00 |
| Madhuban F1 F2 | Abhilasha Venture | 142 Hissa No 1 | 31-03-2019 00:00:00 |
| Charms Heights Phase-Ii A1-A2 | Charms Developers | S.No-130, Hissa No-1/2 | 31-03-2019 00:00:00 |
| Om Sai Vihar | Jai Mahalaxmi Enterprises | Survey No 162A Hissa No 1 Plus 2 Part, Cts No 953 | 31-05-2018 00:00:00 |
| Sai Sahara Phase 2 Wing A | Sai Jyot Enterprises | 421605, Thane, Titwala | 30-12-2023 00:00:00 |
| Sai Kanhujipolice Sankul | Harshad Balu Gawade | Survey No 56 Hiss No 36, Survey No 56 Hissa No 37A, Survey No 56 Hissa 37B | 30-05-2024 00:00:00 |
| Abhidarshan Homes | Abhidarshan Combines | 162/1/1, 162/1/2 | 30-06-2020 00:00:00 |
| Mamta 1351 | Patil Group Builders And Developers | Cts No 773, 774, 775 | 30-12-2022 00:00:00 |
| Siddheshwar Heights | Shree Jai Malhar Enterprises | S No 26 Hissa No 1 To 6 | 30-03-2023 00:00:00 |
-
Project:
Madhuban F1 F2
-
Location:
-
142 Hissa No 1
-
Const. Stage:
Ongoing
-
Possession:
31 Mar 2019
-
Developer:
Abhilasha Venture
-
Phone:
-
Address:
-
Patil Bhuvan
| MAHA REARA No: |
P51700002614 |
| Project Type |
Residential / Group Housing |
| RERA Project Status |
Ongoing |
| Architect |
Rajeev Tayshete & Associates |
| Funding Bank |
KOTAK MAHINDRA BANK LIMITED |
| Proposed Possession |
31 Mar 2019 |
| Revised Possession |
31 Mar 2019 |
| Extended Possession |
30 Sep 2020 |
| Litigations |
No Litigations |
| Last Modified |
13 Jun 2020 |
| Last Retrived |
26 Jul 2025 |
Madhuban F1 F2 QR Code
Madhuban F1 F2
MahaRERA - P51700002614
| Type | Area |
| 1 BHK | 33.27 Sq.mts. ( 358 Sq.ft. ) |
| 1 BHK | 33.36 Sq.mts. ( 359 Sq.ft. ) |
| 1 BHK | 35.73 Sq.mts. ( 385 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Madhuban F1 F2last updated on 26 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space10% completed
|
|
Promoter |
|
|
|
Promoter |
Community Buildings90% completed
|
|
Promoter |
Electrical Meter Room, Sub-Station, Receiving Station100% completed
|
|
Promoter |
Energy management100% completed
|
|
Promoter |
Fire Protection And Fire Safety
Requirements100% completed
|
|
Promoter |
Landscaping & Tree Planting100% completed
|
|
Promoter |
|
|
|
Promoter |
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
|
|
Promoter |
Solid Waste Management And Disposal
|
|
Na |
Storm Water Drains100% completed
|
|
Promoter |
Street Lighting100% completed
|
|
Promoter |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting100% completed
|
|
Promoter |
|
|
|
Kdmc |
Buildings / Wings in Madhuban F1 F2
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Madhuban F1 F2 by Abhilasha Venturelast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
56
apartments in total
Saleable Area Statistics (Sq. ft.)
20247
Total
Total 56 apartments in project. 30 apartments booked. 53% apartments booked.
Total 20247 Sq.ft. saleable area. 10829 saleable area booked.
53% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| F1 | Mar 2019 | 8 | 1 | 0 | 1 | 0 | 10 | 10 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 33.27 Sq.mts. ( 358 Sq.ft. ) | 14 | |
| 1 BHK | 33.36 Sq.mts. ( 359 Sq.ft. ) | 7 | |
| 1 BHK | 35.73 Sq.mts. ( 385 Sq.ft. ) | 7 | |
28 total apartments / 15 apartments booked. 53% apartments booked. |
| Work Description in Building F1 | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| F2 | Mar 2019 | 8 | 1 | 0 | 1 | 0 | 10 | 10 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 33.27 Sq.mts. ( 358 Sq.ft. ) | 28 | |
28 total apartments / 15 apartments booked. 53% apartments booked. |
| Work Description in Building F2 | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
Channel Partners Registered by Developer
Abhilasha Venture
for Project
Madhuban F1 F2
last updated on
26 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |