Project overview

Lucas Residency is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700030052. Lucas Residency is located at Cts No. 596 To 599. This is a New being developed by Sunita Developers.

Lucas Residency has 1 BHK & 2 BHK Apartments with carpet areas ranging from 315 to 464 Sq.ft. Carpet. The Project has total 68 of which 13 are currently available for sale.

Lucas Residency is being developed on a total land area of 17127 Sq.ft. Lucas Residency has 2 Wings / Towers Lucas Residency A-Wing,Lucas Residency B-Wing

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Lucas Residency
  • Location:
  • Cts No. 596 To 599
  • Const. Stage:
    New
  • Possession:
    31 Dec 2023
Developer Details

  • Developer:
    Sunita Developers
  • Phone:
  • Address:
  • Navare Residency
Project RERA Details
MAHA REARA No: P51700030052
Project Type Residential / Group Housing
RERA Project Status New
Architect U K Associates
Funding Bank BANK OF BARODA
Proposed Possession 31 Dec 2023
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 26 Jul 2021
Last Retrived 26 Jul 2025
Lucas Residency QR Code
Lucas Residency
MahaRERA - P51700030052
Apartment Details & Configuration
TypeArea
1 BHK29.24 Sq.mts. ( 315 Sq.ft. )
1 BHK29.64 Sq.mts. ( 319 Sq.ft. )
1 BHK31.56 Sq.mts. ( 340 Sq.ft. )
2 BHK42.26 Sq.mts. ( 455 Sq.ft. )
2 BHK42.36 Sq.mts. ( 456 Sq.ft. )
2 BHK44.99 Sq.mts. ( 484 Sq.ft. )
2 BHK45.42 Sq.mts. ( 489 Sq.ft. )
1 BHK31.21 Sq.mts. ( 336 Sq.ft. )
1 BHK31.76 Sq.mts. ( 342 Sq.ft. )
2 BHK42.51 Sq.mts. ( 458 Sq.ft. )
2 BHK42.62 Sq.mts. ( 459 Sq.ft. )
2 BHK43.15 Sq.mts. ( 464 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Lucas Residencylast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
--
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Na
Open Parking100% completed
95% Complete
--
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
--
Solid Waste Management And Disposal
Na
Storm Water Drains
Na
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
--
Water Supply100% completed
95% Complete
Will Be Provided By Concern Department
Buildings / Wings in Lucas Residency
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Lucas Residency by Sunita Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

17127 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

68 apartments in total
Total
68
Booked
55
Available
13

Saleable Area Statistics (Sq. ft.)

25534 Total
Total
25534
Booked
20678
Available
4856
Total 68 apartments in project. 55 apartments booked. 80% apartments booked.
Total 25534 Sq.ft. saleable area. 20678 saleable area booked.
81% area booked.

Lucas Residency A-Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Lucas Residency A-WingDec 20238101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.24 Sq.mts. ( 315 Sq.ft. )8
6 Booked75% Booked
75% Booked
1 BHK29.64 Sq.mts. ( 319 Sq.ft. )4
3 Booked75% Booked
75% Booked
1 BHK31.56 Sq.mts. ( 340 Sq.ft. )14
13 Booked92% Booked
92% Booked
2 BHK42.26 Sq.mts. ( 455 Sq.ft. )5
4 Booked80% Booked
80% Booked
2 BHK42.36 Sq.mts. ( 456 Sq.ft. )2
2 Booked100% Booked
100% Booked
2 BHK44.99 Sq.mts. ( 484 Sq.ft. )5
5 Booked100% Booked
100% Booked
2 BHK45.42 Sq.mts. ( 489 Sq.ft. )2
2 Booked100% Booked
100% Booked
40 total apartments / 35 apartments booked. 87% apartments booked.
Work Description in Building Lucas Residency A-WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Lucas Residency B-Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Lucas Residency B-WingDec 20238101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.24 Sq.mts. ( 315 Sq.ft. )9
6 Booked66% Booked
66% Booked
1 BHK29.64 Sq.mts. ( 319 Sq.ft. )3
3 Booked100% Booked
100% Booked
1 BHK31.21 Sq.mts. ( 336 Sq.ft. )5
4 Booked80% Booked
80% Booked
1 BHK31.76 Sq.mts. ( 342 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK42.51 Sq.mts. ( 458 Sq.ft. )5
3 Booked60% Booked
60% Booked
2 BHK42.62 Sq.mts. ( 459 Sq.ft. )4
2 Booked50% Booked
50% Booked
2 BHK43.15 Sq.mts. ( 464 Sq.ft. )1
1 Booked100% Booked
100% Booked
28 total apartments / 20 apartments booked. 71% apartments booked.
Work Description in Building Lucas Residency B-WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Sunita Developers
for Project
Lucas Residency
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation