Project overview

Kuber Samruddhi Phase I is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700009286. Kuber Samruddhi Phase I is located at 421202, Thane. This is a On-Going Project being developed by Creative Infra.

Kuber Samruddhi Phase I has RESIDENTIAL 1BHK & RESIDENTIAL 1RK Apartments with carpet areas ranging from 265 to 285 Sq.ft. Carpet. The Project has total 58 of which 0 are currently available for sale.

Kuber Samruddhi Phase I is being developed on a total land area of 20452 Sq.ft. out of which 4234 Sq.ft. i.e 21% is reserved for recreational purposes. Kuber Samruddhi Phase I has 1 Wings / Towers Kuber Samruddhi B Wing

ProjectDeveloperLocationPossession
Kulswamini PrassannaKulswamini DevelopersOld S No 340 And New S No 86/231-08-2019 00:00:00
Dattusai Complex Building No 2Sairaj EnterprisesS No 358Old/5New, H No 3 4B31-12-2017 00:00:00
Jaya Shantaram HeightsGurudeep ConstructionS No 145 Old 89 New Hn8 Village Gaondevi31-12-2019 00:00:00
Nascon MatoshreeOmkar Developers2105 To 211031-12-2026 00:00:00
Rajas LeelaNakhye's Everest Estate Private LimitedC.T.S. 1616 To 1619, 191431-05-2026 00:00:00
Shreyas ResidencyKashinath Kalu BhoirS No 60 H No 21A & 21B31-03-2026 00:00:00
Bhoir JewelsShankar Namaji BhoirS No. 83 Hissa N. 2/1 4 5 6P 3P 8P Hissa No 32630-12-2022 00:00:00
Yash Enclaves Bldg 3Rachana EnterprisesS No 78, Hissa No 4, Old Servey No 34131-12-2019 00:00:00
Kuber Samruddhi Ph-IiVeer Maruti DevelopersThane, 42120230-07-2020 00:00:00
Project Details
  • Project:
    Kuber Samruddhi Phase I
  • Location:
  • 421202, Thane
  • Const. Stage:
    On-Going Project
  • Possession:
    31 Dec 2018
Developer Details

  • Developer:
    Creative Infra
  • Phone:
  • Address:
  • B 103, Kuber Samruddhi, Subhash Road, Shankeshwar Palm, Kumbharkhan Pada Dombivli-West, 421202
Project RERA Details
MAHA REARA No: P51700009286
Project Type Residential
RERA Project Status On-Going Project
Funding Bank UCO BANK
Proposed Possession 31 Dec 2018
Revised Possession 31 Dec 2019
Extended Possession
Litigations No Litigations
Last Modified 28 Dec 2021
Last Retrived 28 Jul 2025
Kuber Samruddhi Phase I QR Code
Kuber Samruddhi Phase I
MahaRERA - P51700009286
Apartment Details & Configuration
TypeArea
RESIDENTIAL 1BHK26.5 Sq.mts. ( 285 Sq.ft. )
RESIDENTIAL 1RK24.64 Sq.mts. ( 265 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Kuber Samruddhi Phase Ilast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space25% completed
25% Complete
Work In Progress
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station50% completed
50% Complete
Work In Progress
Energy management
Work In Progress
Fire Protection And Fire Safety Requirements50% completed
50% Complete
Work In Progress
Landscaping & Tree Planting
Work In Progress
Open Parking
Work In Progress
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completed
Solid Waste Management And Disposal
Na
Storm Water Drains
Work In Progress
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Work In Progress
Water Conservation, Rain water Harvesting
Work In Progress
Water Supply90% completed
90% Complete
Work In Progress
Buildings / Wings in Kuber Samruddhi Phase I
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Kuber Samruddhi Phase I by Creative Infralast updated on 28 Jul 2025 as per information obtained from MARA RERA.

20452 Sq. ft.

Project Area

4234 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

58 apartments in total
Total
58
Booked
58
Available
0

Saleable Area Statistics (Sq. ft.)

16344 Total
Total
16344
Booked
16344
Available
0
Total 58 apartments in project. 58 apartments booked. 100% apartments booked.
Total 16344 Sq.ft. saleable area. 16344 saleable area booked.
100% area booked.

Kuber Samruddhi B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Kuber Samruddhi B WingJan 1900131010010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL 1BHK26.5 Sq.mts. ( 285 Sq.ft. )48
48 Booked100% Booked
100% Booked
RESIDENTIAL 1RK24.64 Sq.mts. ( 265 Sq.ft. )10
10 Booked100% Booked
100% Booked
58 total apartments / 58 apartments booked. 100% apartments booked.
Work Description in Building Kuber Samruddhi B WingCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress80% done
80% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress86% done
86% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress80% done
80% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Creative Infra
for Project
Kuber Samruddhi Phase I
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation