Project overview

Khatri Sparsh is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700021704. Khatri Sparsh is located at Plot Bearing S No 3. This is a New being developed by Khatri Realty.

Khatri Sparsh has 1 BHK & 1RK Apartments with carpet areas ranging from 254 to 374 Sq.ft. Carpet. The Project has total 364 of which 150 are currently available for sale.

Khatri Sparsh is being developed on a total land area of 75456 Sq.ft. Khatri Sparsh has 4 Wings / Towers Building No 1,Building No 2,Building No 3,Building No 4

ProjectDeveloperLocationPossession
Deep Laxmi HeightDeeplaxmi HeightsBhiwandi30-12-2024 00:00:00
Lodha Bellavista - Wing B1Macrotech Developers LimitedGat No.61/1/1,2,3,4 30-12-2025 00:00:00
Fennelia CommercialAcme Housing India Private LimitedGat No 61/1/1,2,330-12-2025 00:00:00
Project Details
  • Project:
    Khatri Sparsh
  • Location:
  • Plot Bearing S No 3
  • Const. Stage:
    New
  • Possession:
    30 Dec 2027
Developer Details

  • Developer:
    Khatri Realty
  • Phone:
  • Address:
  • Aditya Heights
Project RERA Details
MAHA REARA No: P51700021704
Project Type Residential / Group Housing
RERA Project Status New
Architect Raj Associates
Funding Bank FEDERAL BANK
Proposed Possession 30 Dec 2027
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 14 Feb 2023
Last Retrived 26 Jul 2025
Khatri Sparsh QR Code
Khatri Sparsh
MahaRERA - P51700021704
Apartment Details & Configuration
TypeArea
1 BHK32.11 Sq.mts. ( 346 Sq.ft. )
1 BHK34.29 Sq.mts. ( 369 Sq.ft. )
1 BHK35.18 Sq.mts. ( 379 Sq.ft. )
1 BHK35.95 Sq.mts. ( 387 Sq.ft. )
1 BHK35.96 Sq.mts. ( 387 Sq.ft. )
2 BHK46.45 Sq.mts. ( 500 Sq.ft. )
2 BHK47.5 Sq.mts. ( 511 Sq.ft. )
1 BHK36.44 Sq.mts. ( 392 Sq.ft. )
1 BHK37.29 Sq.mts. ( 401 Sq.ft. )
1 BHK37.86 Sq.mts. ( 408 Sq.ft. )
2 BHK50.4 Sq.mts. ( 543 Sq.ft. )
2 BHK50.83 Sq.mts. ( 547 Sq.ft. )
1 BHK27.61 Sq.mts. ( 297 Sq.ft. )
1 BHK34.75 Sq.mts. ( 374 Sq.ft. )
1 BHK34.77 Sq.mts. ( 374 Sq.ft. )
1 BHK34.81 Sq.mts. ( 375 Sq.ft. )
1RK21.12 Sq.mts. ( 227 Sq.ft. )
1RK24 Sq.mts. ( 258 Sq.ft. )
1 BHK27.14 Sq.mts. ( 292 Sq.ft. )
1 BHK27.97 Sq.mts. ( 301 Sq.ft. )
1 BHK34.05 Sq.mts. ( 367 Sq.ft. )
1RK23.6 Sq.mts. ( 254 Sq.ft. )
1RK24.57 Sq.mts. ( 264 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Khatri Sparshlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
O S Area 831.77 Sq Mtr Work Yet Not Started
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Meter Room Work Yet Not Started
Energy management
Solar Panel Work Yet Not Started
Fire Protection And Fire Safety Requirements
Work Yet Not Started
Landscaping & Tree Planting
Tree Planting Work Yet Not Started
Open Parking
As Per Plan Work Yet Not Started
Sewerage (Chamber, Lines, Septic Tank , STP)
Septic Tank Work Yet Not Started
Solid Waste Management And Disposal
Na
Storm Water Drains
Work Yet Not Started
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Rain Water Harvesting Work Yet Not Started
Water Supply
Mjp Will Provided Water Connection After Oc
Buildings / Wings in Khatri Sparsh
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Khatri Sparsh by Khatri Realtylast updated on 26 Jul 2025 as per information obtained from MARA RERA.

75456 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

364 apartments in total
Total
364
Booked
214
Available
150

Saleable Area Statistics (Sq. ft.)

135405 Total
Total
135405
Booked
75672
Available
59733
Total 364 apartments in project. 214 apartments booked. 58% apartments booked.
Total 135405 Sq.ft. saleable area. 75672 saleable area booked.
56% area booked.

Building No 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 1Dec 202612100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.11 Sq.mts. ( 346 Sq.ft. )36
1 BHK34.29 Sq.mts. ( 369 Sq.ft. )12
1 BHK35.18 Sq.mts. ( 379 Sq.ft. )12
1 BHK35.95 Sq.mts. ( 387 Sq.ft. )23
1 BHK35.96 Sq.mts. ( 387 Sq.ft. )12
3 Booked25% Booked
25% Booked
2 BHK46.45 Sq.mts. ( 500 Sq.ft. )12
2 BHK47.5 Sq.mts. ( 511 Sq.ft. )12
119 total apartments / 17 apartments booked. 14% apartments booked.
Work Description in Building Building No 1Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Building No 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 2Dec 202612100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.11 Sq.mts. ( 346 Sq.ft. )24
14 Booked58% Booked
58% Booked
1 BHK35.96 Sq.mts. ( 387 Sq.ft. )11
8 Booked72% Booked
72% Booked
1 BHK36.44 Sq.mts. ( 392 Sq.ft. )12
3 Booked25% Booked
25% Booked
1 BHK37.29 Sq.mts. ( 401 Sq.ft. )11
8 Booked72% Booked
72% Booked
1 BHK37.86 Sq.mts. ( 408 Sq.ft. )24
5 Booked20% Booked
20% Booked
2 BHK50.4 Sq.mts. ( 543 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK50.83 Sq.mts. ( 547 Sq.ft. )12
8 Booked66% Booked
66% Booked
95 total apartments / 47 apartments booked. 49% apartments booked.
Work Description in Building Building No 2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress60% done
60% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress30% done
30% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress40% done
40% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress80% done
80% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress70% done
70% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress71% done
71% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress60% done
60% Booked
Sanitary Fittings within the flats / premises
work-in-progress70% done
70% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress50% done
50% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 3Dec 20267100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK27.61 Sq.mts. ( 297 Sq.ft. )18
18 Booked100% Booked
100% Booked
1 BHK34.75 Sq.mts. ( 374 Sq.ft. )5
5 Booked100% Booked
100% Booked
1 BHK34.77 Sq.mts. ( 374 Sq.ft. )40
40 Booked100% Booked
100% Booked
1 BHK34.81 Sq.mts. ( 375 Sq.ft. )4
4 Booked100% Booked
100% Booked
1RK21.12 Sq.mts. ( 227 Sq.ft. )2
2 Booked100% Booked
100% Booked
1RK24 Sq.mts. ( 258 Sq.ft. )6
6 Booked100% Booked
100% Booked
75 total apartments / 75 apartments booked. 100% apartments booked.
Work Description in Building Building No 3Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 4

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 4Dec 20217100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK27.14 Sq.mts. ( 292 Sq.ft. )11
11 Booked100% Booked
100% Booked
1 BHK27.61 Sq.mts. ( 297 Sq.ft. )21
21 Booked100% Booked
100% Booked
1 BHK27.97 Sq.mts. ( 301 Sq.ft. )8
8 Booked100% Booked
100% Booked
1 BHK34.05 Sq.mts. ( 367 Sq.ft. )13
13 Booked100% Booked
100% Booked
1 BHK34.77 Sq.mts. ( 374 Sq.ft. )15
15 Booked100% Booked
100% Booked
1RK23.6 Sq.mts. ( 254 Sq.ft. )4
4 Booked100% Booked
100% Booked
1RK24.57 Sq.mts. ( 264 Sq.ft. )3
3 Booked100% Booked
100% Booked
75 total apartments / 75 apartments booked. 100% apartments booked.
Work Description in Building Building No 4Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress89% done
89% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Khatri Realty
for Project
Khatri Sparsh
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation