Project overview

Jupiter Complex is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000013313. Jupiter Complex is located at 115,116,118. This is a Ongoing being developed by M/S. Jem Developers.

Jupiter Complex has 1 BHK & 2 BHK Apartments with carpet areas ranging from 335 to 583 Sq.ft. Carpet. The Project has total 174 of which 10 are currently available for sale.

Jupiter Complex is being developed on a total land area of 44160 Sq.ft. out of which 4416 Sq.ft. i.e 10% is reserved for recreational purposes. Jupiter Complex has 2 Wings / Towers Jupiter Complex Bldg No 1,Jupiter Complex Bldg No 2

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Jupiter Complex
  • Location:
  • 115,116,118
  • Const. Stage:
    Ongoing
  • Possession:
    31 May 2019
Developer Details

  • Developer:
    M/S. Jem Developers
  • Phone:
  • Address:
  • Badri Masjid Complex
Project RERA Details
MAHA REARA No: P99000013313
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Ajay Wade & Associates
Funding Bank BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession 31 May 2019
Revised Possession 31 May 2019
Extended Possession 30 Sep 2024
Litigations No Litigations
Last Modified 30 Jan 2025
Last Retrived 28 Jul 2025
Jupiter Complex QR Code
Jupiter Complex
MahaRERA - P99000013313
Apartment Details & Configuration
TypeArea
1 BHK23.25 Sq.mts. ( 250 Sq.ft. )
1 BHK28.17 Sq.mts. ( 303 Sq.ft. )
1 BHK31.15 Sq.mts. ( 335 Sq.ft. )
1 BHK32.33 Sq.mts. ( 348 Sq.ft. )
1 BHK34.4 Sq.mts. ( 370 Sq.ft. )
1 BHK35.32 Sq.mts. ( 380 Sq.ft. )
1 BHK36.33 Sq.mts. ( 391 Sq.ft. )
1 BHK37.34 Sq.mts. ( 402 Sq.ft. )
1 BHK37.51 Sq.mts. ( 404 Sq.ft. )
1 BHK38.25 Sq.mts. ( 412 Sq.ft. )
1 BHK32.47 Sq.mts. ( 350 Sq.ft. )
1 BHK34.84 Sq.mts. ( 375 Sq.ft. )
1 BHK37.78 Sq.mts. ( 407 Sq.ft. )
1 BHK38.26 Sq.mts. ( 412 Sq.ft. )
2 BHK48.73 Sq.mts. ( 525 Sq.ft. )
2 BHK54.15 Sq.mts. ( 583 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Jupiter Complexlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Na
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting20% completed
20% Complete
Na
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Septic Tank
Solid Waste Management And Disposal
Na
Storm Water Drains
Around This Building
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Na
Water Supply100% completed
95% Complete
Oh Tank And Ug Tank
Buildings / Wings in Jupiter Complex
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Jupiter Complex by M/S. Jem Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

44160 Sq. ft.

Project Area

4416 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

174 apartments in total
Total
174
Booked
164
Available
10

Saleable Area Statistics (Sq. ft.)

70612 Total
Total
70612
Booked
66362
Available
4250
Total 174 apartments in project. 164 apartments booked. 94% apartments booked.
Total 70612 Sq.ft. saleable area. 66362 saleable area booked.
94% area booked.

Jupiter Complex Bldg No 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Jupiter Complex Bldg No 1May 20195100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK23.25 Sq.mts. ( 250 Sq.ft. )6
6 Booked100% Booked
100% Booked
1 BHK28.17 Sq.mts. ( 303 Sq.ft. )24
23 Booked95% Booked
95% Booked
1 BHK31.15 Sq.mts. ( 335 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK32.33 Sq.mts. ( 348 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK34.4 Sq.mts. ( 370 Sq.ft. )3
3 Booked100% Booked
100% Booked
1 BHK35.32 Sq.mts. ( 380 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK36.33 Sq.mts. ( 391 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK37.34 Sq.mts. ( 402 Sq.ft. )10
10 Booked100% Booked
100% Booked
1 BHK37.51 Sq.mts. ( 404 Sq.ft. )30
29 Booked96% Booked
96% Booked
1 BHK38.25 Sq.mts. ( 412 Sq.ft. )4
3 Booked75% Booked
75% Booked
90 total apartments / 87 apartments booked. 96% apartments booked.
Work Description in Building Jupiter Complex Bldg No 1Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress80% done
80% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress80% done
80% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress85% done
85% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress85% done
85% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Jupiter Complex Bldg No 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Jupiter Complex Bldg No 2May 202251010018
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.15 Sq.mts. ( 335 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK32.33 Sq.mts. ( 348 Sq.ft. )3
2 Booked66% Booked
66% Booked
1 BHK32.47 Sq.mts. ( 350 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK34.84 Sq.mts. ( 375 Sq.ft. )3
3 Booked100% Booked
100% Booked
1 BHK35.32 Sq.mts. ( 380 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK36.33 Sq.mts. ( 391 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK37.51 Sq.mts. ( 404 Sq.ft. )16
13 Booked81% Booked
81% Booked
1 BHK37.78 Sq.mts. ( 407 Sq.ft. )24
23 Booked95% Booked
95% Booked
1 BHK38.26 Sq.mts. ( 412 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK48.73 Sq.mts. ( 525 Sq.ft. )3
3 Booked100% Booked
100% Booked
2 BHK54.15 Sq.mts. ( 583 Sq.ft. )24
22 Booked91% Booked
91% Booked
84 total apartments / 77 apartments booked. 91% apartments booked.
Work Description in Building Jupiter Complex Bldg No 2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
M/S. Jem Developers
for Project
Jupiter Complex
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation