Project overview

Jhelum is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800010836. Jhelum is located at 32 A/1/2A Part, 32 A/1/2B. This is a Ongoing being developed by Satre Infrastructure Private Limited.

Jhelum has 1 BHK Apartments with carpet areas ranging from 269 to 269 Sq.ft. Carpet. The Project has total 192 of which 49 are currently available for sale.

Jhelum is being developed on a total land area of 47315 Sq.ft. out of which 4589 Sq.ft. i.e 10% is reserved for recreational purposes. Jhelum has 2 Wings / Towers Jhelum,Sra-Ranveer Chsl

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Jhelum
  • Location:
  • 32 A/1/2A Part, 32 A/1/2B
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2021
Developer Details

  • Developer:
    Satre Infrastructure Private Limited
  • Phone:
  • Address:
  • D1, Vedant Complex
Project RERA Details
MAHA REARA No: P51800010836
Project Type Others
RERA Project Status Ongoing
Architect Samar Raut
Funding Bank STATE BANK OF INDIA
Proposed Possession 30 Dec 2021
Revised Possession 30 Dec 2021
Extended Possession
Litigations No Litigations
Last Modified 06 Apr 2018
Last Retrived 26 Jul 2025
Jhelum QR Code
Jhelum
MahaRERA - P51800010836
Apartment Details & Configuration
TypeArea
1 Bedroom Type 136 Sq.mts. ( 388 Sq.ft. )
1 Bedroom Type 232 Sq.mts. ( 344 Sq.ft. )
1 Bedroom Type 326 Sq.mts. ( 280 Sq.ft. )
1 Room Kitchen21 Sq.mts. ( 226 Sq.ft. )
1 BHK25 Sq.mts. ( 269 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Jhelumlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Ph Reservation Units
Electrical Meter Room, Sub-Station, Receiving Station
Na
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Na
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Na
Solid Waste Management And Disposal
Na
Storm Water Drains
Na
Street Lighting
Internal 6.00 M Wide Access
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Na
Water Supply
Na
Buildings / Wings in Jhelum
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Jhelum by Satre Infrastructure Private Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

47315 Sq. ft.

Project Area

4589 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

192 apartments in total
Total
192
Booked
143
Available
49

Saleable Area Statistics (Sq. ft.)

55704 Total
Total
55704
Booked
40677
Available
15027
Total 192 apartments in project. 143 apartments booked. 74% apartments booked.
Total 55704 Sq.ft. saleable area. 40677 saleable area booked.
73% area booked.

Jhelum

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
JhelumDec 202014101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 Bedroom Type 136 Sq.mts. ( 388 Sq.ft. )24
17 Booked70% Booked
70% Booked
1 Bedroom Type 232 Sq.mts. ( 344 Sq.ft. )27
10 Booked37% Booked
37% Booked
1 Bedroom Type 326 Sq.mts. ( 280 Sq.ft. )18
1 Room Kitchen21 Sq.mts. ( 226 Sq.ft. )24
14 Booked58% Booked
58% Booked
93 total apartments / 44 apartments booked. 47% apartments booked.
Work Description in Building JhelumCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress78% done
78% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress80% done
80% Booked
Sanitary Fittings within the flats / premises
work-in-progress80% done
80% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Sra-Ranveer Chsl

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Sra-Ranveer ChslMay 201810101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK25 Sq.mts. ( 269 Sq.ft. )99
99 Booked100% Booked
100% Booked
99 total apartments / 99 apartments booked. 100% apartments booked.
Work Description in Building Sra-Ranveer ChslCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Satre Infrastructure Private Limited
for Project
Jhelum
last updated on 26 Jul 2025 as per information obtained from MARA RERA.