Project overview

Jalal Mansion is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700010284. Jalal Mansion is located at 1545,1549. This is a Ongoing being developed by Maryam Enterprises.

Jalal Mansion has COMMERCIAL & RESIDENTIAL Apartments with carpet areas ranging from 1171 to 4474 Sq.ft. Carpet. The Project has total 19 of which 5 are currently available for sale.

Jalal Mansion is being developed on a total land area of 2826 Sq.ft. out of which 2826 Sq.ft. i.e 100% is reserved for recreational purposes. Jalal Mansion has 1 Wings / Towers Jalal Mansion

ProjectDeveloperLocationPossession
Greenworld Developers Pvt. LtdGreenworld Devlopers Pvt. Ltd.2990 Pt A30-06-2021 00:00:00
ShivamGagan Developers & EngineersSurvey No 46 Hissa No.16 P31-03-2019 00:00:00
Kohinoor WavesKohinoor Realties (J.V)12680, 12681, 12682, 1268701-01-2019 00:00:00
GeetanjaliHonest Homes16/11 18/3 19/1531-12-2019 00:00:00
Patel Colossus - Phase IiiPatel Group & CoSurvey No. 42A, H.No. 2 Pt, 3 Pt, 4 Pt, 7 Pt, 8Pt, 9 Pt, 24Pt30-12-2023 00:00:00
Keshar Aagan Cooperative Housing SocietyGagan HomesPlot No 14/6 Survey No 42/A30-09-2026 00:00:00
Balaji AquaBalaji WorldOld Survey No. 39, Hissa No- 3/2/A, 3/2/C, 3/2/D05-11-2029 00:00:00
Patel Colossus Phase 1Patel Group & CoS. No. 42 A, H.N 2 Pt, 3 Pt, 4 Pt, 7 Pt, 8 Pt, 9 Pt, 24 Pt30-12-2022 00:00:00
Bharat Residency Shivsai Builders & DevelopersS No 84 H No 7 /11 B31-05-2018 00:00:00
New Era CM/S. Yogi Developers Corporation22,1/8,1/1,2,3, 24,2Pt,2Pt,2Pt,2Pt,2Pt,2Pt,2Pt,2Pt,2Pt, 25 H No 1,2,3,4Pt,4Pt,530-12-2021 00:00:00
Nirman HeightsNirman HabitatsS No 12,Hissa No 4,Plot No531-08-2018 00:00:00
Ashapura PrasadAshapura Nirman DevelopersCts No. 7380 To 7384 And 7389, Survey No. 4231-12-2018 00:00:00
Geetant AshrayVasudha Construction CompanySurvey No 42/A Hissa No 19B/1631-12-2024 00:00:00
Atharva HeightsJai Shreegurutatvam Engineers And DevelopersSurvey No 130/2A/1 & 20/4A Cts 361531-12-2025 00:00:00
Vaishnavi HeightsVaishnavi ConstructionSurvey No 42A, Hissa No 19/A/3 Cts No. 7273 To 7276, Survey No. 42/A, Hissa No. 19/A/8 Cts No.7277 To 728030-07-2024 00:00:00
Jalal MansionMaryam Enterprises1545,154931-12-2018 00:00:00
Shiv SiddhiKedar ConstructionSurvey No 1 Hissa No 3/A-130-06-2023 00:00:00
Maruti Vihar NxAashray DevelopersThane, 42130131-12-2017 00:00:00
Balaji Exotica-Phase 1Balaji WorldSurvey No-16,H.No-8/2,Plot No-230-12-2022 00:00:00
Disha Co Operative Housing Society LtdGagan Developers And EngineersSurvey No 19 Hissa No 13 Part31-01-2020 00:00:00
Medhekar HeightsSomeshwarnath DevelopersSurvey No. 179, Hissa No. 1, Plot No. 131-03-2026 00:00:00
Shivneri Park Co Op Hsg Soc LtdShree Swastik ConstructionsS No. 14 H. No. 1/331-03-2027 00:00:00
Sai ParkSai Satyam Realty LlpSurvey No. 21 Hiss No. 1/1, 10/1, 10/231-12-2027 00:00:00
Birla Vanya Phase 2Century Textiles & Industries LtdCts No 165331-03-2025 00:00:00
Gayatri NiwasGayatri Builders2991231-12-2025 00:00:00
Bhakti WindsorBhakti Realtors121/3B31-10-2026 00:00:00
Senwin ResidencySenwin Divine VenturesS No 179, H No 431-03-2025 00:00:00
Pancham Co. Operative Hsg SocietyYuvraj Constructions131(P)30-06-2025 00:00:00
Patel MountPatel Group & CoS.No.42A, Hissa No. 2(Pt),3(Pt),(4Pt),7(Pt),8(Pt),9(Pt),24(Pt)30-06-2024 00:00:00
Gayatri AnandGayatri BuildersCts No 2994/A/131-12-2028 00:00:00
Royal PlazaRoyal RealtyCts No 3007 C (P)31-12-2027 00:00:00
Janki DhamRakesh Tapeshwar SinghSurvey No 93 Hissa No 231-12-2027 00:00:00
Jigar Construction VenusPraful Haribhai SenjaliaSurvey No 110 / 1A And 1B31-03-2019 00:00:00
Tycoons Square Avenue Iii Tower CTycoons Avanti Projects Llp421301, Thane31-07-2020 00:00:00
Atmaram Kene ResidencyMega DevelopersSn 82/7 And Sn 87/831-12-2018 00:00:00
Ambre HeightsOm Sai Builders And Developers4878 To 488431-12-2018 00:00:00
Monarch SolitaireMonarch Solitaire LlpSurvey No 169/A/3/1, 169/A/3/230-12-2022 00:00:00
Balaji Arcade Wing AShikhar DevelopersSurvey No.7 Hissa No.10, 13/2/1 , Old Survey No. 10 Part And 13 Part31-12-2019 00:00:00
Shivaay ResidencyRohan Krishnapalsingh ThakurS.No. 42/14/B/C30-06-2019 00:00:00
Athena EnclaveJai Mata Di DevelopersSno 9 Hno 3/1/2/2/A30-12-2023 00:00:00
Millenium HeightsK P DevelopersSurvey No 22/1 Pt30-12-2023 00:00:00
The Chalets AvenueAssets Reality12/130-11-2018 00:00:00
Patel Colossus Phase IiPatel Group & CoSurvey No. 42A, H.N. 2 Pt, 3, Pt, 4 Pt, 7 Pt, 8 Pt, 9Pt30-12-2023 00:00:00
Yash MidtownYash Realty98/4, 99/231-12-2028 00:00:00
Ammu Co-Op Housing Society LtdStonecraftersSurvey No- 42/A, Hissa No- 22/231-03-2027 00:00:00
Satyam Chopra EnclaveSai Satyam Properties LlpSurvey No.130 Hissa No 3/A/1331-03-2027 00:00:00
Om PushpanjaliR B Construction3/4/A,3/4/B,3/4/C31-12-2026 00:00:00
Project Details
  • Project:
    Jalal Mansion
  • Location:
  • 1545,1549
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2018
Developer Details

  • Developer:
    Maryam Enterprises
  • Phone:
  • Address:
  • Kokan Bank Building
Project RERA Details
MAHA REARA No: P51700010284
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Unique Desigh Build Solutions Pvt Ltd
Funding Bank KOTAK MAHINDRA BANK LIMITED
Proposed Possession 31 Dec 2018
Revised Possession 31 Dec 2018
Extended Possession
Litigations No Litigations
Last Modified 24 Aug 2017
Last Retrived 26 Jul 2025
Jalal Mansion QR Code
Jalal Mansion
MahaRERA - P51700010284
Apartment Details & Configuration
TypeArea
COMMERCIAL108.82 Sq.mts. ( 1171 Sq.ft. )
RESIDENTIAL415.68 Sq.mts. ( 4474 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Jalal Mansionlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
No Sub Station And Recieveing Station Proposed
Energy management
Na
Fire Protection And Fire Safety Requirements
As Per Fire Noc
Landscaping & Tree Planting
After Completion
Open Parking50% completed
50% Complete
Completed After Completion
Sewerage (Chamber, Lines, Septic Tank , STP)20% completed
20% Complete
Chambers And Drainage Lines Proposed To Be Connect
Solid Waste Management And Disposal
Na
Storm Water Drains20% completed
20% Complete
In Progress
Street Lighting
After Completion
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Rain Water Harvesting Of Bore Well Proposed
Water Supply
Water Supply Connection To Be Provided By Kdmc
Buildings / Wings in Jalal Mansion
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Jalal Mansion by Maryam Enterpriseslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

2826 Sq. ft.

Project Area

2826 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

19 apartments in total
Total
19
Booked
14
Available
5

Saleable Area Statistics (Sq. ft.)

61892 Total
Total
61892
Booked
39520
Available
22372
Total 19 apartments in project. 14 apartments booked. 73% apartments booked.
Total 61892 Sq.ft. saleable area. 39520 saleable area booked.
64% area booked.

Jalal Mansion

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Jalal MansionJan 19008102042
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
COMMERCIAL108.82 Sq.mts. ( 1171 Sq.ft. )7
7 Booked100% Booked
100% Booked
RESIDENTIAL415.68 Sq.mts. ( 4474 Sq.ft. )12
7 Booked58% Booked
58% Booked
19 total apartments / 14 apartments booked. 73% apartments booked.
Work Description in Building Jalal MansionCompletion
Basement (if any)
work-in-progress70% done
70% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress20% done
20% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress20% done
20% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress42% done
42% Booked
Plinth
work-in-progress70% done
70% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress90% done
90% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress70% done
70% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress70% done
70% Booked
Stilt Floor
work-in-progress70% done
70% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
work-in-progress70% done
70% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress90% done
90% Booked
Channel Partners
Channel Partners Registered by Developer
Maryam Enterprises
for Project
Jalal Mansion
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation