Project overview
Jai Guruji Tower is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700012793. Jai Guruji Tower is located at Survey No 55 Hissa No 1 B. This is a Ongoing being developed by Om Sai Construction And Developers.
Jai Guruji Tower has 1 BHK, 1 RK & 2 BHK Apartments with carpet areas ranging from 222 to 560 Sq.ft. Carpet. The Project has total 56 of which 25 are currently available for sale.
Jai Guruji Tower is being developed on a total land area of 22389 Sq.ft. Jai Guruji Tower has 1 Wings / Towers Jai Guruji Tower
| Project | Developer | Location | Possession |
| Woodside Meadows | Om Shree Sai Developers | S No 52 / 4 And S No 52 /11/1 | 31-05-2018 00:00:00 |
| Urbanville | Sai Krupa Builders | S No25-9 No25-10 No25-1Pt No11 No10 No2 No3 No24-4 | 31-12-2019 00:00:00 |
| Tharwani Rosalie Lx, Type - E, Aster - Wing | Sai Homes | Survey No 5, Hissa No 3 | 30-09-2018 00:00:00 |
| Amrut Pearl Building No 2 | Amrut Builders | Sn 52 Hn 7-1 | 30-12-2022 00:00:00 |
| Sundar Residency G Wing | Navaditya Developers | 13/1, 13/2 | 31-12-2019 00:00:00 |
| Tharwani Miracle | Anil Hardasmal Tharwani | Survey No 4Hissa No 2 P | 31-12-2018 00:00:00 |
| Amrut Pearl Building No. 5 And 6 | Amrut Builders | Sn 52 Hn 7-1 | 31-12-2018 00:00:00 |
| MAHA REARA No: |
P51700012793 |
| Project Type |
Residential / Group Housing |
| RERA Project Status |
Ongoing |
| Architect |
Varghese John |
| Funding Bank |
AXIS BANK |
| Proposed Possession |
30 Dec 2022 |
| Revised Possession |
30 Dec 2022 |
| Extended Possession |
30 Jun 2023 |
| Litigations |
No Litigations |
| Last Modified |
27 Mar 2023 |
| Last Retrived |
26 Jul 2025 |
Jai Guruji Tower QR Code
Jai Guruji Tower
MahaRERA - P51700012793
| Type | Area |
| 1 BHK | 31.74 Sq.mts. ( 342 Sq.ft. ) |
| 1 BHK | 32.43 Sq.mts. ( 349 Sq.ft. ) |
| 1 BHK | 32.59 Sq.mts. ( 351 Sq.ft. ) |
| 1 BHK | 32.89 Sq.mts. ( 354 Sq.ft. ) |
| 1 BHK | 33.25 Sq.mts. ( 358 Sq.ft. ) |
| 1 BHK | 33.49 Sq.mts. ( 360 Sq.ft. ) |
| 1 BHK | 36.35 Sq.mts. ( 391 Sq.ft. ) |
| 1 BHK | 36.46 Sq.mts. ( 392 Sq.ft. ) |
| 1 BHK | 36.48 Sq.mts. ( 393 Sq.ft. ) |
| 1 BHK | 36.57 Sq.mts. ( 394 Sq.ft. ) |
| 1 BHK | 36.68 Sq.mts. ( 395 Sq.ft. ) |
| 1 BHK | 36.8 Sq.mts. ( 396 Sq.ft. ) |
| 1 BHK | 36.89 Sq.mts. ( 397 Sq.ft. ) |
| 1 RK | 20.66 Sq.mts. ( 222 Sq.ft. ) |
| 2 BHK | 51.99 Sq.mts. ( 560 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Jai Guruji Towerlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space75% completed
|
|
Work In Progress |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station85% completed
|
|
Work In Progress |
|
|
|
Solar Panels As Per Kdmc Norms |
Fire Protection And Fire Safety
Requirements90% completed
|
|
As Per Kdmc Norms |
Landscaping & Tree Planting75% completed
|
|
Only Trees Plantation As Per Kdmc Norms |
|
|
|
Work In Progress |
Sewerage (Chamber, Lines, Septic Tank , STP)90% completed
|
|
As Per Kdmc Norms |
Solid Waste Management And Disposal
|
|
Na |
Storm Water Drains80% completed
|
|
As Per Kdmc Norms |
|
|
|
Na |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting100% completed
|
|
As Per Kdmc Norms |
|
|
|
Kdmc Will Provide After Completion |
Buildings / Wings in Jai Guruji Tower
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Jai Guruji Tower by Om Sai Construction And Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
56
apartments in total
Saleable Area Statistics (Sq. ft.)
20924
Total
Total 56 apartments in project. 31 apartments booked. 55% apartments booked.
Total 20924 Sq.ft. saleable area. 11764 saleable area booked.
56% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Jai Guruji Tower | Sep 2021 | 8 | 1 | 0 | 7 | 0 | 11 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 31.74 Sq.mts. ( 342 Sq.ft. ) | 6 | |
| 1 BHK | 32.43 Sq.mts. ( 349 Sq.ft. ) | 7 | |
| 1 BHK | 32.59 Sq.mts. ( 351 Sq.ft. ) | 1 | |
| 1 BHK | 32.89 Sq.mts. ( 354 Sq.ft. ) | 1 | |
| 1 BHK | 33.25 Sq.mts. ( 358 Sq.ft. ) | 6 | |
| 1 BHK | 33.49 Sq.mts. ( 360 Sq.ft. ) | 6 | |
| 1 BHK | 36.35 Sq.mts. ( 391 Sq.ft. ) | 6 | |
| 1 BHK | 36.46 Sq.mts. ( 392 Sq.ft. ) | 6 | |
| 1 BHK | 36.48 Sq.mts. ( 393 Sq.ft. ) | 1 | |
| 1 BHK | 36.57 Sq.mts. ( 394 Sq.ft. ) | 3 | |
| 1 BHK | 36.68 Sq.mts. ( 395 Sq.ft. ) | 3 | |
| 1 BHK | 36.8 Sq.mts. ( 396 Sq.ft. ) | 4 | |
| 1 BHK | 36.89 Sq.mts. ( 397 Sq.ft. ) | 4 | |
| 1 RK | 20.66 Sq.mts. ( 222 Sq.ft. ) | 1 | |
| 2 BHK | 51.99 Sq.mts. ( 560 Sq.ft. ) | 1 | |
56 total apartments / 31 apartments booked. 55% apartments booked. |
| Work Description in Building Jai Guruji Tower | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Om Sai Construction And Developers
for Project
Jai Guruji Tower
last updated on
26 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |