Project overview

Hill View Apartments is a MahaRERA Registered Project bearing MahaRERA Registration Number P52000009955. Hill View Apartments is located at 34/1,36/5,120/0. This is a Ongoing being developed by Vaastusiddhi Group Builders And Developers.

Hill View Apartments has 1 BHK Apartments with carpet areas ranging from 346 to 346 Sq.ft. Carpet. The Project has total 126 of which 79 are currently available for sale.

Hill View Apartments is being developed on a total land area of 60063 Sq.ft. out of which 6006 Sq.ft. i.e 10% is reserved for recreational purposes. Hill View Apartments has 11 Wings / Towers Building Number - 1,Building Number - 10,Building Number - 11,Building Number - 2,Building Number - 3,Building Number - 4,Building Number - 5,Building Number - 6,Building Number - 7,Building Number - 8,Building Number -9

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Hill View Apartments
  • Location:
  • 34/1,36/5,120/0
  • Const. Stage:
    Ongoing
  • Possession:
    30 Jun 2018
Developer Details

  • Developer:
    Vaastusiddhi Group Builders And Developers
  • Phone:
  • Address:
  • Bhoomi Landmark
Project RERA Details
MAHA REARA No: P52000009955
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Envirodesigners Pvt Ltd
Funding Bank BANK OF INDIA
Proposed Possession 30 Jun 2018
Revised Possession 30 Jun 2018
Extended Possession 31 Mar 2019
Litigations No Litigations
Last Modified 16 Jul 2018
Last Retrived 28 Jul 2025
Hill View Apartments QR Code
Hill View Apartments
MahaRERA - P52000009955
Apartment Details & Configuration
TypeArea
1 BHK29.65 Sq.mts. ( 319 Sq.ft. )
1 BHK33.14 Sq.mts. ( 357 Sq.ft. )
2 BHK44.06 Sq.mts. ( 474 Sq.ft. )
2 BHK50.07 Sq.mts. ( 539 Sq.ft. )
2 BHK50.55 Sq.mts. ( 544 Sq.ft. )
1 BHK32.18 Sq.mts. ( 346 Sq.ft. )
1 BHK37.24 Sq.mts. ( 401 Sq.ft. )
1 BHK37.61 Sq.mts. ( 405 Sq.ft. )
1 BHK26.27 Sq.mts. ( 283 Sq.ft. )
1 BHK32.19 Sq.mts. ( 346 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Hill View Apartmentslast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Completed
Community Buildings100% completed
95% Complete
Completed
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Completed
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting100% completed
95% Complete
Completed
Open Parking100% completed
95% Complete
Completed
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completed
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
Completed
Street Lighting75% completed
75% Complete
Work In Progress
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Completed
Water Conservation, Rain water Harvesting100% completed
95% Complete
Completed
Water Supply100% completed
95% Complete
Completed
Buildings / Wings in Hill View Apartments
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Hill View Apartments by Vaastusiddhi Group Builders And Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

60063 Sq. ft.

Project Area

6006 Sq. ft.

Recreational Open Space

Total 11

Wings / Towers in Project

Apartments Statistics

126 apartments in total
Total
126
Booked
47
Available
79

Saleable Area Statistics (Sq. ft.)

49826 Total
Total
49826
Booked
19018
Available
30808
Total 126 apartments in project. 47 apartments booked. 37% apartments booked.
Total 49826 Sq.ft. saleable area. 19018 saleable area booked.
38% area booked.

Building Number - 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building Number - 1Jan 19004101004
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.65 Sq.mts. ( 319 Sq.ft. )3
1 Booked33% Booked
33% Booked
1 BHK33.14 Sq.mts. ( 357 Sq.ft. )3
None Booked0% Booked
0% Booked
2 BHK44.06 Sq.mts. ( 474 Sq.ft. )3
3 Booked100% Booked
100% Booked
9 total apartments / 4 apartments booked. 44% apartments booked.
Work Description in Building Building Number - 1Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress75% done
75% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress75% done
75% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress75% done
75% Booked
Stilt Floor
Completed 100% done
100% Booked

Building Number - 10

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building Number - 10Mar 20194101079
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK50.07 Sq.mts. ( 539 Sq.ft. )6
2 Booked33% Booked
33% Booked
2 BHK50.55 Sq.mts. ( 544 Sq.ft. )6
2 Booked33% Booked
33% Booked
12 total apartments / 4 apartments booked. 33% apartments booked.
Work Description in Building Building Number - 10Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Building Number - 11

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building Number - 11Jun 20184101049
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK50.07 Sq.mts. ( 539 Sq.ft. )6
4 Booked66% Booked
66% Booked
2 BHK50.55 Sq.mts. ( 544 Sq.ft. )6
4 Booked66% Booked
66% Booked
12 total apartments / 8 apartments booked. 66% apartments booked.
Work Description in Building Building Number - 11Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress75% done
75% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Building Number - 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building Number - 2Jun 20184101018
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.18 Sq.mts. ( 346 Sq.ft. )12
6 Booked50% Booked
50% Booked
12 total apartments / 6 apartments booked. 50% apartments booked.
Work Description in Building Building Number - 2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress75% done
75% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Building Number - 3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building Number - 3Jun 20184101016
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.18 Sq.mts. ( 346 Sq.ft. )12
6 Booked50% Booked
50% Booked
12 total apartments / 6 apartments booked. 50% apartments booked.
Work Description in Building Building Number - 3Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress75% done
75% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Building Number - 4

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building Number - 4Jun 20184101039
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.18 Sq.mts. ( 346 Sq.ft. )12
12 total apartments / 1 apartments booked. 8% apartments booked.
Work Description in Building Building Number - 4Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress75% done
75% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Building Number - 5

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building Number - 5Jan 190041010411
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK37.24 Sq.mts. ( 401 Sq.ft. )6
None Booked0% Booked
0% Booked
1 BHK37.61 Sq.mts. ( 405 Sq.ft. )6
12 total apartments / 1 apartments booked. 8% apartments booked.
Work Description in Building Building Number - 5Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress75% done
75% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Building Number - 6

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building Number - 6Jan 190041010911
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK37.24 Sq.mts. ( 401 Sq.ft. )6
1 BHK37.61 Sq.mts. ( 405 Sq.ft. )6
2 Booked33% Booked
33% Booked
12 total apartments / 3 apartments booked. 25% apartments booked.
Work Description in Building Building Number - 6Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress75% done
75% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Building Number - 7

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building Number - 7Jan 19004101026
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.27 Sq.mts. ( 283 Sq.ft. )3
3 Booked100% Booked
100% Booked
1 BHK32.19 Sq.mts. ( 346 Sq.ft. )6
2 Booked33% Booked
33% Booked
9 total apartments / 5 apartments booked. 55% apartments booked.
Work Description in Building Building Number - 7Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Building Number - 8

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building Number - 8Jan 190041010110
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.18 Sq.mts. ( 346 Sq.ft. )12
4 Booked33% Booked
33% Booked
12 total apartments / 4 apartments booked. 33% apartments booked.
Work Description in Building Building Number - 8Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Building Number -9

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building Number -9Jan 190041010011
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.18 Sq.mts. ( 346 Sq.ft. )12
5 Booked41% Booked
41% Booked
12 total apartments / 5 apartments booked. 41% apartments booked.
Work Description in Building Building Number -9Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Vaastusiddhi Group Builders And Developers
for Project
Hill View Apartments
last updated on 28 Jul 2025 as per information obtained from MARA RERA.