Project overview

Highstreet Vasai is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000026489. Highstreet Vasai is located at Railway Land. This is a New being developed by Ganadhar Infra Developers Pvt. Ltd.

Highstreet Vasai has Shop Apartments with carpet areas ranging from 10693 to 10693 Sq.ft. Carpet. The Project has total 190 of which 137 are currently available for sale.

Highstreet Vasai is being developed on a total land area of 21345 Sq.ft. out of which 21345 Sq.ft. i.e 100% is reserved for recreational purposes. Highstreet Vasai has 2 Wings / Towers Highstreet Vasai Phase 1,Highstreet Vasai Phase 2

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Highstreet Vasai
  • Location:
  • Railway Land
  • Const. Stage:
    New
  • Possession:
    30 Jun 2023
Developer Details

  • Developer:
    Ganadhar Infra Developers Pvt. Ltd
  • Phone:
  • Address:
  • Highstreet Vasai
Project RERA Details
MAHA REARA No: P99000026489
Project Type Commercial
RERA Project Status New
Architect An Archment
Funding Bank THE COSMOS CO OPERATIVE BANK LIMITED
Proposed Possession 30 Jun 2023
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 20 Sep 2023
Last Retrived 28 Jul 2025
Highstreet Vasai QR Code
Highstreet Vasai
MahaRERA - P99000026489
Apartment Details & Configuration
TypeArea
Shop1235.12 Sq.mts. ( 13295 Sq.ft. )
Shop993.37 Sq.mts. ( 10693 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Highstreet Vasailast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station15% completed
15% Complete
Will Be N Progress
Energy management
Na
Fire Protection And Fire Safety Requirements10% completed
10% Complete
Will Be In Progress
Landscaping & Tree Planting10% completed
10% Complete
Will Be In Progress
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)40% completed
40% Complete
Will Be In Progress
Solid Waste Management And Disposal15% completed
15% Complete
Will Be In Progress
Storm Water Drains60% completed
60% Complete
Will Be In Progress
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting45% completed
45% Complete
In Progress
Water Supply45% completed
45% Complete
Will Be N Progress
Buildings / Wings in Highstreet Vasai
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Highstreet Vasai by Ganadhar Infra Developers Pvt. Ltdlast updated on 28 Jul 2025 as per information obtained from MARA RERA.

21345 Sq. ft.

Project Area

21345 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

190 apartments in total
Total
190
Booked
53
Available
137

Saleable Area Statistics (Sq. ft.)

2320444 Total
Total
2320444
Booked
629162
Available
1691282
Total 190 apartments in project. 53 apartments booked. 27% apartments booked.
Total 2320444 Sq.ft. saleable area. 629162 saleable area booked.
27% area booked.

Highstreet Vasai Phase 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Highstreet Vasai Phase 1Dec 202240200027
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Shop1235.12 Sq.mts. ( 13295 Sq.ft. )111
24 Booked21% Booked
21% Booked
111 total apartments / 24 apartments booked. 21% apartments booked.
Work Description in Building Highstreet Vasai Phase 1Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress70% done
70% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress40% done
40% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress40% done
40% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress85% done
85% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress85% done
85% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress70% done
70% Booked
Sanitary Fittings within the flats / premises
work-in-progress70% done
70% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress70% done
70% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Highstreet Vasai Phase 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Highstreet Vasai Phase 2Dec 202240200027
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Shop993.37 Sq.mts. ( 10693 Sq.ft. )79
29 Booked36% Booked
36% Booked
79 total apartments / 29 apartments booked. 36% apartments booked.
Work Description in Building Highstreet Vasai Phase 2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress70% done
70% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress40% done
40% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress40% done
40% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress85% done
85% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress85% done
85% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress70% done
70% Booked
Sanitary Fittings within the flats / premises
work-in-progress70% done
70% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress70% done
70% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Ganadhar Infra Developers Pvt. Ltd
for Project
Highstreet Vasai
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation