Project overview

Highland Springs B4- C Wing is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700006307. Highland Springs B4- C Wing is located at 74/5A 59/1A 59/1B 46/18. This is a Ongoing being developed by Siddhi Real Estate Developers.

Highland Springs B4- C Wing has 1 BHK, 2 BHK & Shop Apartments with carpet areas ranging from 134 to 542 Sq.ft. Carpet. The Project has total 202 of which 98 are currently available for sale.

Highland Springs B4- C Wing is being developed on a total land area of 6690 Sq.ft. Highland Springs B4- C Wing has 1 Wings / Towers Highland Springs - C Wing

ProjectDeveloperLocationPossession
The EmpressUnique Shanti Developers LlpOld S.No.479/230-03-2023 00:00:00
Lotus ParkReal Enterprise842-A, Plot No. 02,0330-12-2022 00:00:00
Marigold B WingShree Tirupati Greenfield Developers1/1C, 1/1D, 1/1E, 1/1F, 1/1G30-12-2022 00:00:00
Paramount BKalpataru Homes Private LimitedS.No. 114/8-Part,114/4-Part30-06-2025 00:00:00
Raviraj ApartmentRajendra GhorpadeS.No 85,H. No 11, Plot No 930-12-2022 00:00:00
Krupa SindhuAshish Waman GoleS No 48 H No 8/428-11-2021 00:00:00
Arvind GalaxySanchit EnterprisesTika No 16 Cts No 7830-12-2023 00:00:00
Shree Sai Pooja ApartmentOm Sai RealtyS No 29/A H No 19 Plot No 8730-09-2019 00:00:00
Mauli MadhusudhanRameshwar Patil42160530-03-2023 00:00:00
Salangpur NirmanSalangpur Nirman252 6,7 Part30-12-2022 00:00:00
Payal PrideMit Enterprises10430-03-2022 00:00:00
Panvelkar Estate - GreenfordPanvelkar Infrastructures Private LimitedSurvey No. 42 Hissa No 2 And 330-12-2022 00:00:00
Plot 1 Sector 10 GhansoliCidco Of Maharashtra Ltd.Plot No 130-06-2021 00:00:00
Golden Hills B- 3Vihang Enterprises921,923,9241,9243,928130-12-2024 00:00:00
Classic ResidencyClassic ConstructionThane30-06-2021 00:00:00
Sarvodaya ClassicEkta BuildersSurvey No. 28 H.No 530-03-2026 00:00:00
NandigramYogesh Kishor MahajanTikka No 5, 62A/131-03-2025 00:00:00
Windermere Building No 1 To 6A G Superstructures Pvt LtdNew S. No./Old S. No./ H.No. 221/564/1,3,4A,4B,8. New S. No/Old S. No/ H.No/220/565/1,4,6,7,8,9,10. New S. No/Old S. No/H.No/267/567/1,2/1. New S. No/Old S. No/245/579/1A,1B,2,3A,3B,3C,4,5,6,731-12-2027 00:00:00
Cosmos Horizon Phase IiConcorde Developers192/2A30-03-2024 00:00:00
Simone ResidencyM R M DevelopersDaighar Village30-12-2022 00:00:00
Delta WoodsDelta Venture1883Pt30-09-2023 00:00:00
Bharat Ecovistas Phase IiBharat Realty Venture Private Limited67/2/P, 67/3A, Sub Plot B30-12-2023 00:00:00
Panvelkar Estate - Stanford - Phase 1Panvelkar Infrastructures Private LimitedGut No 42/131-12-2018 00:00:00
Sunrise CAgile Real Estate Pvt. Ltd.S. No. 104/16-Part Of Village Balkum30-12-2023 00:00:00
Sunrise AAgile Real Estate Pvt. Ltd.S. No. 97/5-Part,97/6C-Part Of Village Balkum30-12-2023 00:00:00
Sunrise DAgile Real Estate Pvt. Ltd.S. No. 104/16-Part,97/1-Part, 95/26C-Part Of Village Balkum30-12-2023 00:00:00
Ten X Era Raymond Realty Tower CRaymond Limited121 Pt 83/3 83/130-01-2029 00:00:00
Guru Ganesh ChsVadnere Builder & DevelopersSurvey No 13 Hissa No 6(A) Plot No 2631-12-2025 00:00:00
Mangeshi NeptuneMangesh GaikarThane31-12-2027 00:00:00
Shreeji LandmarkVinayak DevelopersSurvey No 46 Hissa No 5-130-12-2029 00:00:00
Hyde Park Residency F6 Building PhaseNexus Builders And Developers Pvt Ltd47/1/2, 47/1/3, 47/1/4, 47/1/5, 47/1/7, 47/1/8, 47/1/9, 47/1/1030-12-2021 00:00:00
Hyde Park Residency F4 Building PhaseNexus Builders And Developers Pvt Ltd47/1/2, 47/1/3, 47/1/4, 47/1/5, 47/1/7, 47/1/9, 47/1/1030-12-2021 00:00:00
The Icon Phase 1Leading Frontier Private LimitedSurvey No 60/18,60/19,Survey No 61/2A To 61/2F, 61/3,62/3,62/5E,62/6,62/7,62/9C30-12-2022 00:00:00
Kashi Darshan B WingVarad Raj Construction98/1920-12-2023 00:00:00
Saroj Sadan Chs LtdShrusti DevelopersThane19-01-2026 00:00:00
Narang Privado - BNarang Realty Private Limited146/5/B And 146/6/B/131-03-2028 00:00:00
Saptashree HeightsSaptashree Reality Private LimitedGut No 25 Hissa No 2 , 331-05-2018 00:00:00
Jai MatadeeAaradhana Developers37531-03-2018 00:00:00
Sunrise BAgile Real Estate Pvt. Ltd.S. No. 104/16-Part Of Village Balkum30-12-2023 00:00:00
Keyur Co-Operative Housing Society LtdDhanashree DevelopersKansai31-12-2025 00:00:00
Suyog ApartmentTelange Builders & Developers Private Limited4693 To 469930-03-2025 00:00:00
Prabhat DarshanYashomalhar Construction7015A/1A30-06-2023 00:00:00
Rental Building A-1 R2Sonam Spark Infra Private Limited30/11,14,15,21,22,24,29/1,23/2,22/1,2,330-09-2020 00:00:00
Raj Tattva Wing A B And EKothari Autoparts Manufacturers Private Limited1411, 2, 3, 144, 1451, 2, 4, 1462, 3, 4, 1481, 1421, 1483130-12-2023 00:00:00
Sunrise EAgile Real Estate Pvt. Ltd.S. No.97/1-Part,97/2-Part30-12-2023 00:00:00
Lodha Amara - Tower 26, 27, 28, 30, 34, 35Macrotech Developers Limited64/3,64/7,65/2,65/3,65/4,65/5, 68/3,68/4,68/5,69/2,69/6,70/1,70/2,70/3,70/430-12-2021 00:00:00
Vardhman Garden Phase IiDiwali Construction CompanyThane31-12-2022 00:00:00
Vardhman VatikaDiwali DevelopersSurvey No 21 Part And 22 Part31-12-2019 00:00:00
Shivsai ParadiseBharat Agri Fert & Realty Realty Ltd112/2A,3,4,5/1,5/2,5/330-12-2028 00:00:00
RubaShreyas Enterprises112/5/430-09-2020 00:00:00
OrchidMehta RealtorsS No 378/131-03-2019 00:00:00
Saket ImperialNirmaan Realty9570,957107-08-2025 00:00:00
Maruti Square Building No 7Maruti Dwellers Private LimitedNew Survey Nos 63 66 And 69 Pt31-12-2027 00:00:00
Paramount FKalpataru Homes Private LimitedSno 115/4/2 Pt 115/5 Pt 115/6 Pt 115/7/2 Pt 115/8/2 Pt 115/10/2 Pt Of Village Majiwade30-09-2024 00:00:00
Krishna - B WingNeelkanth Palm Realty149/4/1 Pt, 412/2 Pt30-05-2022 00:00:00
Runwal PearlRunwal Construction Private LimitedGut No 21/B1 Gut No 21/B231-05-2019 00:00:00
Mayfair HeliosRaj Laxmi DevelopersNew Survey No 104/17 Of Village Balkum Thane31-12-2022 00:00:00
Paramount EKalpataru Homes Private LimitedS.No. 115/10/2-Part And 115/8/2-Part Of Village Majiwada30-06-2025 00:00:00
Madhu VillaShree Krishna EnterprisesSurvey No. 18 / House No. 2230-12-2022 00:00:00
Hyde Park Residency F5 Building PhaseNexus Builders And Developers Pvt LtdGut No 47/1/2, 47/1/3, 47/1/5, 47/1/7, 47/1/8, 47/1/9, 47/1/1030-09-2023 00:00:00
Teri KudratVishnu Jethanand BadlaniPlot No 433, Sheet No 48, Cts No 2578331-10-2024 00:00:00
Kanha ResidencyKulkarnii Builder105A/4/2/3/4/5/4114-05-2025 00:00:00
Trinity MokshRattanraj LifespacesS No 64 1 And 64 231-03-2025 00:00:00
Panvelkar Estate - Oxford - Phase 1Panvelkar Infrastructures Private LimitedGut No.45/2,46/2,47,49/4,49/9,49/11,49/1230-12-2023 00:00:00
Highland Springs B4- E WingSiddhi Real Estate Developers46/18Pt, 47/13Pt31-10-2019 00:00:00
Krishna Vihar Co-Operative Housing Society LimitedBal Ganapati Laabh DevelopersCts Nos 20/7 And 33A T No 1630-12-2021 00:00:00
Nirman SignatureShree Sha DevelopersSuevey No.180 Hissa No.3/231-03-2026 00:00:00
Hcs HorizonHcs Realtors LlpOld Survey No 271 New Survey No 82 Hissa No 1131-12-2026 00:00:00
Maplewoods Phase 1M/S Bks Galaxy Realtors Llp51(2) 56 And 57(2)31-12-2028 00:00:00
Arihant City Phase-Ii - N BuildingArihant Enterprises49/1P,49/2,49/3P,50/1P,52/1P,52/1P,53/1P,53/1P,53/1P,53/2P,55P,55P,55P,56P30-06-2026 00:00:00
Arihant City Phase-Ii - M BuildingArihant Enterprises49/1P,49/2,49/3,50/1P,52/1P,52/1P,53/1P,53/1P,53/1P,53/2P,55P,55P,55P,56P30-06-2026 00:00:00
Sarthi ElanzaSarthi DevelopersS No-264/58 Plot No-5531-10-2023 00:00:00
Bsc It ParkBansal Steel CorporationA21601-06-2024 00:00:00
Runwal Lands EndRunwal Construction Private Limited20/3 Part30-06-2029 00:00:00
Terraform ArcadeMoney Magnum Constructions37/10, 38/1, 146/1, 146/2P31-07-2022 00:00:00
Indraprasth Wing CSonam Spark Infra Private Limited30/11,14,15,21,22,24,29/1,23/2,22/1,2,330-09-2020 00:00:00
Arihant City Phase-Ii - L BuildingArihant Enterprises49/1P,49/2,49/3P,50/1P,52/1P,52/1P,53/1P,53/1P,53/1P,53/2P,55P,55P,55P,56P30-06-2026 00:00:00
The Icon Phase 2Leading Frontier Private Limited61/2B30-06-2026 00:00:00
Newa Bhakti Park B WingNewa Technocity (I) Private LimitedIt 631-12-2027 00:00:00
Skyrise ResidencyNishith Subandhu LuharPlot No 6/Cts No 7469/S No 38/B/630-07-2025 00:00:00
Priyanka ParadisePriyanka Regency LlpPlot 16A Sector 24 Sanpada Navi Mumbai31-12-2024 00:00:00
Yashanand Chsl Ojass ConstructionsOjass ConstructionsCts No. 4030-03-2022 00:00:00
Royal EmpireSai Pooja ConstructionsS No 184 H No 2A30-12-2024 00:00:00
Guru SakshatSadguru EnterprisesPlot No 3 Gut No 46/3 H No 4 And 530-12-2025 00:00:00
Highland Springs B4- A WingSiddhi Real Estate Developers74/5Apart30-06-2023 00:00:00
Highland Park Building 2- K25 Wing A Phase 2Siddhi Gaurav EnterprisesS. N. 87/2 And 82/630-12-2024 00:00:00
Falco CheshireAanya RealtorsThane, 42110231-10-2016 00:00:00
Ganesh BhuvanMagnum Homes66830-09-2024 00:00:00
Audumber Flower ValleyAudumber SuperstructuresS No 5/4/D 5/4/B 5/23/B30-06-2025 00:00:00
Spm Dream City Phase 1D K BuildconS No 52 H No 4/531-12-2028 00:00:00
Poddar Wondercity Phase - ViPoddar Housing And Development Limited42150330-06-2024 00:00:00
Poddar Wondercity Phase - IiPoddar Housing And Development Limited42150330-06-2022 00:00:00
Thanekar Palacio Phase IiThanekar Construction LlpSurvey No. 82/2/1 Survey No 83/3/6 Survey No 83/3/7 Survey No 83/4A Plot No 3 5 6 & 731-12-2026 00:00:00
Veer GalaxyYash InfraSector 2 , 108/4C , 108/4D31-07-2025 00:00:00
Priyanka AvenuePriyanka Regency LlpPlot No 29 Sector 1531-03-2028 00:00:00
Poddar Wondercity Phase - IPoddar Housing And Development LimitedS No 29 H No 230-09-2023 00:00:00
Poddar Wondercity Phase - IiiPoddar Housing And Development Limited42150330-09-2024 00:00:00
Poddar Wondercity Phase - IvPoddar Housing And Development LimitedJoveli Village31-07-2023 00:00:00
Paramount CKalpataru Homes Private LimitedSno 115/5Pt 115/9Pt 115/12Pt,115/13Pt Of Village Majiwade 212/1Pt Of Village Balkum30-06-2025 00:00:00
My City Phase Ii Cluster 5 Part IiHorizon Projects Pvt Ltd108/1 And 93 Part31-12-2027 00:00:00
Highland Springs B4- C WingSiddhi Real Estate Developers74/5A 59/1A 59/1B 46/1830-12-2023 00:00:00
Ashar Metro TowersShree Saibaba Grihanirimiti Private LimitedS.No 229 Pt H.No 1,S.No 207 Pt And 208 Pt H No 7 Pt30-12-2024 00:00:00
Poddar Wondercity Phase - VPoddar Housing And Development Limited42150330-06-2024 00:00:00
Lodha Amara - Wing 40 And 41Macrotech Developers Limited64 By 2 And 64 By 329-11-2024 00:00:00
Project Details
  • Project:
    Highland Springs B4- C Wing
  • Location:
  • 74/5A 59/1A 59/1B 46/18
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2023
Developer Details

  • Developer:
    Siddhi Real Estate Developers
  • Phone:
  • Address:
  • Highland Gardens
Project RERA Details
MAHA REARA No: P51700006307
Project Type Others
RERA Project Status Ongoing
Architect Design Consortium Architects I Pvt Ltd
Funding Bank HDFC BANK
Proposed Possession 30 Dec 2023
Revised Possession 30 Dec 2023
Extended Possession 30 Nov 2024
Litigations No Litigations
Last Modified 03 Jan 2024
Last Retrived 26 Jul 2025
Highland Springs B4- C Wing QR Code
Highland Springs B4- C Wing
MahaRERA - P51700006307
Apartment Details & Configuration
TypeArea
1 BHK33.92 Sq.mts. ( 365 Sq.ft. )
1 BHK34.01 Sq.mts. ( 366 Sq.ft. )
1 BHK34.23 Sq.mts. ( 368 Sq.ft. )
1 BHK34.36 Sq.mts. ( 370 Sq.ft. )
1 BHK37.55 Sq.mts. ( 404 Sq.ft. )
1 BHK37.77 Sq.mts. ( 407 Sq.ft. )
2 BHK45.74 Sq.mts. ( 492 Sq.ft. )
2 BHK48.13 Sq.mts. ( 518 Sq.ft. )
2 BHK50.31 Sq.mts. ( 542 Sq.ft. )
Shop12.43 Sq.mts. ( 134 Sq.ft. )
Shop12.63 Sq.mts. ( 136 Sq.ft. )
Shop15.47 Sq.mts. ( 167 Sq.ft. )
Shop18.02 Sq.mts. ( 194 Sq.ft. )
Shop18.2 Sq.mts. ( 196 Sq.ft. )
Shop18.21 Sq.mts. ( 196 Sq.ft. )
Shop18.22 Sq.mts. ( 196 Sq.ft. )
Shop26.99 Sq.mts. ( 291 Sq.ft. )
Shop27.92 Sq.mts. ( 301 Sq.ft. )
Shop27.94 Sq.mts. ( 301 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Highland Springs B4- C Winglast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
R.G.Area Proposed As Per Approved Plan
Community Buildings50% completed
50% Complete
Common Clubhouse Proposed For All Phases
Electrical Meter Room, Sub-Station, Receiving Station90% completed
90% Complete
Electric Meter Room Proposed In The Stilt
Energy management50% completed
50% Complete
Solar Panels To Be Provided
Fire Protection And Fire Safety Requirements50% completed
50% Complete
As Per Cfo Noc
Landscaping & Tree Planting5% completed
5% Complete
R.G.Area Proposed As Per Approved Plan
Open Parking25% completed
25% Complete
As Per Approved Plan
Sewerage (Chamber, Lines, Septic Tank , STP)70% completed
70% Complete
Common Stp Proposed For All Phases In Basement
Solid Waste Management And Disposal100% completed
95% Complete
Provision For Owc As Per Ec
Storm Water Drains60% completed
60% Complete
As Per Tmc Noc
Street Lighting5% completed
5% Complete
Only For Internal Roads &Amp; Footpaths
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Common Stp Proposed For All Phases In Basement
Water Conservation, Rain water Harvesting50% completed
50% Complete
Rain Water Harvestg Tanks Is Proposed In Basement
Water Supply70% completed
70% Complete
Water Provided By Tmc
Buildings / Wings in Highland Springs B4- C Wing
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Highland Springs B4- C Wing by Siddhi Real Estate Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

6690 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

202 apartments in total
Total
202
Booked
104
Available
98

Saleable Area Statistics (Sq. ft.)

81704 Total
Total
81704
Booked
40321
Available
41384
Total 202 apartments in project. 104 apartments booked. 51% apartments booked.
Total 81704 Sq.ft. saleable area. 40321 saleable area booked.
49% area booked.

Highland Springs - C Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Highland Springs - C WingDec 2022251110997
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK33.92 Sq.mts. ( 365 Sq.ft. )32
28 Booked87% Booked
87% Booked
1 BHK34.01 Sq.mts. ( 366 Sq.ft. )32
10 Booked31% Booked
31% Booked
1 BHK34.23 Sq.mts. ( 368 Sq.ft. )17
5 Booked29% Booked
29% Booked
1 BHK34.36 Sq.mts. ( 370 Sq.ft. )17
14 Booked82% Booked
82% Booked
1 BHK37.55 Sq.mts. ( 404 Sq.ft. )36
12 Booked33% Booked
33% Booked
1 BHK37.77 Sq.mts. ( 407 Sq.ft. )8
3 Booked37% Booked
37% Booked
2 BHK45.74 Sq.mts. ( 492 Sq.ft. )17
9 Booked52% Booked
52% Booked
2 BHK48.13 Sq.mts. ( 518 Sq.ft. )17
10 Booked58% Booked
58% Booked
2 BHK50.31 Sq.mts. ( 542 Sq.ft. )16
Shop12.43 Sq.mts. ( 134 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop12.63 Sq.mts. ( 136 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop15.47 Sq.mts. ( 167 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop18.02 Sq.mts. ( 194 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop18.2 Sq.mts. ( 196 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop18.21 Sq.mts. ( 196 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop18.22 Sq.mts. ( 196 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop26.99 Sq.mts. ( 291 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop27.92 Sq.mts. ( 301 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop27.94 Sq.mts. ( 301 Sq.ft. )1
1 Booked100% Booked
100% Booked
202 total apartments / 104 apartments booked. 51% apartments booked.
Work Description in Building Highland Springs - C WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress87% done
87% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress36% done
36% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress36% done
36% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress87% done
87% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress87% done
87% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress25% done
25% Booked
Sanitary Fittings within the flats / premises
work-in-progress25% done
25% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress87% done
87% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Siddhi Real Estate Developers
for Project
Highland Springs B4- C Wing
last updated on 26 Jul 2025 as per information obtained from MARA RERA.