Project overview

Highland Haven Building 3C Coral-B Phase 3 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700007196. Highland Haven Building 3C Coral-B Phase 3 is located at S. N. 82. This is a Ongoing being developed by Siddhi Krish Developers.

Highland Haven Building 3C Coral-B Phase 3 has 2 BHK & 3 BHK Apartments with carpet areas ranging from 589 to 828 Sq.ft. Carpet. The Project has total 88 of which 21 are currently available for sale.

Highland Haven Building 3C Coral-B Phase 3 is being developed on a total land area of 38330 Sq.ft. out of which 11445 Sq.ft. i.e 30% is reserved for recreational purposes. Highland Haven Building 3C Coral-B Phase 3 has 1 Wings / Towers Building 3C- Coral B

ProjectDeveloperLocationPossession
Shree Siddhivinayak EnterprisesShree Siddhivinayak Enterprises309,311 To 317, 321,32401-12-2018 00:00:00
Kaveri KrishnaShree Shakti Developers235 236/131-12-2017 00:00:00
Highland Haven Building 6F Mist-B Phase 5Siddhi Krish DevelopersS. N. 75/5, 75/630-12-2024 00:00:00
Paramount FKalpataru Homes Private LimitedSno 115/4/2 Pt 115/5 Pt 115/6 Pt 115/7/2 Pt 115/8/2 Pt 115/10/2 Pt Of Village Majiwade30-09-2024 00:00:00
Rustomjee La Vie Wing AKapstone Constructions Private LimitedPlot No 8A Survey No 329/3 Pt Of Village Majiwade31-12-2028 00:00:00
Paramount CKalpataru Homes Private LimitedSno 115/5Pt 115/9Pt 115/12Pt,115/13Pt Of Village Majiwade 212/1Pt Of Village Balkum30-06-2025 00:00:00
Rustomjee La Familia - Wing BKapstone Constructions Private LimitedSub Plot 8 Survey No 30 2, 30 3,And 329 2Pt31-12-2026 00:00:00
Runwal Garden City - DahliaRunwal Developers Private LimitedSurvey Nos As Documented30-06-2018 00:00:00
Casa Royale - GrandeLodha Buildcon Private Ltd (Lodha Develoopers Pvt Ltd)161/1A/3P31-01-2018 00:00:00
Highland Haven Building 2B Dew-A Phase 2Siddhi Krish DevelopersS. N. 83/1/3 Part, 83/1/331-03-2019 00:00:00
Viraj TowerShree Viraj Enterprises192/1 P30-12-2021 00:00:00
Dosti West County - Dosti OakDosti EnterprisesNew Survey No 17/1, 17/2, 17/3Pt, 19/23, 19/29, 19/30Pt30-06-2022 00:00:00
Highland Haven Building 4D Coral-A Phase 4Siddhi Krish DevelopersS. N. 8231-03-2019 00:00:00
Highland Haven Building 1A Dew-B Phase 1Siddhi Krish DevelopersS. N. 83/3 Part, 83/1/3 Part31-03-2019 00:00:00
Highland Haven Building 3C Coral-B Phase 3Siddhi Krish DevelopersS. N. 8231-03-2019 00:00:00
Residential Buildings Of Lig Mig Hig At Balkum Thane Under Lum Sum TurnkeyKonkan Housing And Area Development BoardThane, 40060804-02-2017 00:00:00
Windson HeightsOvla Builders & Developers Pvt. Ltd.199/1A, 199/1B, 224/1, 224/2, 224/3A, 224/3B, 224/4A/1, 224/4A/2, 224/4B/1, 224/4B/2, 224/5A, 224/5B30-12-2023 00:00:00
Vardhman Garden Phase 1Diwali Construction Company22831-12-2018 00:00:00
Hari Om ArcadeIdeal EnterprisesOld S No 236/1, 236/228-02-2021 00:00:00
Sonu Aai ComplexArvind Gopal Patil Aop192/1, 192/230-12-2022 00:00:00
Dosti Westcounty- Phase 2- Dosti CedarDosti EnterprisesSr No 17/6P, 19/43P, 25/13A,49/1P, 17/3P, 17/5P, 17/9P, 17/14P, 17/10P30-12-2023 00:00:00
Dosti Westcounty-Phase 3-Dosti WestwoodDosti EnterprisesSurvey Nos. 49/7A P30-12-2026 00:00:00
Project Details
  • Project:
    Highland Haven Building 3C Coral-B Phase 3
  • Location:
  • S. N. 82
  • Const. Stage:
    Ongoing
  • Possession:
    31 Mar 2019
Developer Details

  • Developer:
    Siddhi Krish Developers
  • Phone:
  • Address:
  • Lake City Mall
Project RERA Details
MAHA REARA No: P51700007196
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Jitesh P Pawar And Associates
Funding Bank HDFC BANK
Proposed Possession 31 Mar 2019
Revised Possession 31 Mar 2019
Extended Possession
Litigations No Litigations
Last Modified 17 Aug 2017
Last Retrived 26 Jul 2025
Highland Haven Building 3C Coral-B Phase 3 QR Code
Highland Haven Building 3C Coral-B Phase 3
MahaRERA - P51700007196
Apartment Details & Configuration
TypeArea
2 BHK54.75 Sq.mts. ( 589 Sq.ft. )
3 BHK76.96 Sq.mts. ( 828 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Highland Haven Building 3C Coral-B Phase 3last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space60% completed
60% Complete
As Per Layout
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station50% completed
50% Complete
As Per Layout
Energy management80% completed
80% Complete
As Per Layout
Fire Protection And Fire Safety Requirements70% completed
70% Complete
As Per Layout
Landscaping & Tree Planting30% completed
30% Complete
As Per Layout
Open Parking60% completed
60% Complete
As Per Layout
Sewerage (Chamber, Lines, Septic Tank , STP)60% completed
60% Complete
As Per Layout
Solid Waste Management And Disposal15% completed
15% Complete
As Per Layout
Storm Water Drains55% completed
55% Complete
As Per Layout
Street Lighting30% completed
30% Complete
As Per Layout
Treatment And Disposal Of Sewage And Sullage Water70% completed
70% Complete
As Per Layout
Water Conservation, Rain water Harvesting80% completed
80% Complete
As Per Layout
Water Supply60% completed
60% Complete
As Per Layout
Buildings / Wings in Highland Haven Building 3C Coral-B Phase 3
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Highland Haven Building 3C Coral-B Phase 3 by Siddhi Krish Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

38330 Sq. ft.

Project Area

11445 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

88 apartments in total
Total
88
Booked
67
Available
21

Saleable Area Statistics (Sq. ft.)

62858 Total
Total
62858
Booked
47135
Available
15723
Total 88 apartments in project. 67 apartments booked. 76% apartments booked.
Total 62858 Sq.ft. saleable area. 47135 saleable area booked.
75% area booked.

Building 3C- Coral B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building 3C- Coral BMar 20192410111480
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK54.75 Sq.mts. ( 589 Sq.ft. )42
35 Booked83% Booked
83% Booked
3 BHK76.96 Sq.mts. ( 828 Sq.ft. )46
32 Booked69% Booked
69% Booked
88 total apartments / 67 apartments booked. 76% apartments booked.
Work Description in Building Building 3C- Coral BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress80% done
80% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress70% done
70% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress70% done
70% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress90% done
90% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress75% done
75% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress75% done
75% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress80% done
80% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Siddhi Krish Developers
for Project
Highland Haven Building 3C Coral-B Phase 3
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation