Project overview

Hayaat Garden is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000006530. Hayaat Garden is located at S. No.28 H. No.13. This is a Ongoing being developed by M M Enterprises.

Hayaat Garden has 1 BHK, 1 RK & 2 BHK Apartments with carpet areas ranging from 256 to 476 Sq.ft. Carpet. The Project has total 12 of which 0 are currently available for sale.

Hayaat Garden is being developed on a total land area of 24542 Sq.ft. out of which 2475 Sq.ft. i.e 10% is reserved for recreational purposes. Hayaat Garden has 2 Wings / Towers B Wing,C Wing

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Hayaat Garden
  • Location:
  • S. No.28 H. No.13
  • Const. Stage:
    Ongoing
  • Possession:
    30 Mar 2018
Developer Details

  • Developer:
    M M Enterprises
  • Phone:
  • Address:
  • Hayaat Residency,
Project RERA Details
MAHA REARA No: P99000006530
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect En Con
Funding Bank FEDERAL BANK
Proposed Possession 30 Mar 2018
Revised Possession 30 Mar 2018
Extended Possession
Litigations No Litigations
Last Modified 14 Aug 2017
Last Retrived 28 Jul 2025
Hayaat Garden QR Code
Hayaat Garden
MahaRERA - P99000006530
Apartment Details & Configuration
TypeArea
1 RK23.74 Sq.mts. ( 256 Sq.ft. )
1 BHK31.58 Sq.mts. ( 340 Sq.ft. )
1 BHK32.26 Sq.mts. ( 347 Sq.ft. )
1 BHK34.08 Sq.mts. ( 367 Sq.ft. )
2 BHK44.22 Sq.mts. ( 476 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Hayaat Gardenlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Completed
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Completed
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting100% completed
95% Complete
Completed
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completed
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
Completed
Street Lighting100% completed
95% Complete
Completed
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
Completed
Water Supply100% completed
95% Complete
Completed
Buildings / Wings in Hayaat Garden
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Hayaat Garden by M M Enterpriseslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

24542 Sq. ft.

Project Area

2475 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

12 apartments in total
Total
12
Booked
12
Available
0

Saleable Area Statistics (Sq. ft.)

4414 Total
Total
4414
Booked
4414
Available
0
Total 12 apartments in project. 12 apartments booked. 100% apartments booked.
Total 4414 Sq.ft. saleable area. 4414 saleable area booked.
100% area booked.

B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
B WingMar 20181100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 RK23.74 Sq.mts. ( 256 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 total apartments / 1 apartments booked. 100% apartments booked.
Work Description in Building B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

C Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
C WingMar 20185101041
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.58 Sq.mts. ( 340 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK32.26 Sq.mts. ( 347 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK34.08 Sq.mts. ( 367 Sq.ft. )3
3 Booked100% Booked
100% Booked
1 RK23.74 Sq.mts. ( 256 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK44.22 Sq.mts. ( 476 Sq.ft. )3
3 Booked100% Booked
100% Booked
11 total apartments / 11 apartments booked. 100% apartments booked.
Work Description in Building C WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
M M Enterprises
for Project
Hayaat Garden
last updated on 28 Jul 2025 as per information obtained from MARA RERA.