Project overview

Haware Intelligentia Sigma South Jvlr Wing A is a MahaRERA Registered Project bearing MahaRERA Registration Number P51900028286. Haware Intelligentia Sigma South Jvlr Wing A is located at Bldg No 18 Ob No 7 And 8 Cts No 352 Pt Tagore Nagar. This is a New being developed by Suresh Kashinath Haware.

Haware Intelligentia Sigma South Jvlr Wing A has Shop Apartments with carpet areas ranging from 108 to 81 Sq.ft. Carpet. The Project has total 140 of which 140 are currently available for sale.

Haware Intelligentia Sigma South Jvlr Wing A is being developed on a total land area of 13364 Sq.ft. Haware Intelligentia Sigma South Jvlr Wing A has 3 Wings / Towers Wing A Floors 1 To 22,Wing A Floors 23 To 27,Wing A Ground Floor

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Haware Intelligentia Sigma South Jvlr Wing A
  • Location:
  • Bldg No 18 Ob No 7 And 8 Cts No 352 Pt Tagore Nagar
  • Const. Stage:
    New
  • Possession:
    30 Jun 2025
Developer Details

  • Developer:
    Suresh Kashinath Haware
  • Phone:
  • Address:
  • Haware Infotech Park
Project RERA Details
MAHA REARA No: P51900028286
Project Type Residential / Group Housing
RERA Project Status New
Architect Space Design
Funding Bank ICICI BANK LIMITED
Proposed Possession 30 Jun 2025
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 18 Feb 2021
Last Retrived 26 Jul 2025
Haware Intelligentia Sigma South Jvlr Wing A QR Code
Haware Intelligentia Sigma South Jvlr Wing A
MahaRERA - P51900028286
Apartment Details & Configuration
TypeArea
AX0134.87 Sq.mts. ( 375 Sq.ft. )
AX0234.9 Sq.mts. ( 376 Sq.ft. )
AX0321.32 Sq.mts. ( 229 Sq.ft. )
AX0429.08 Sq.mts. ( 313 Sq.ft. )
AX0533.65 Sq.mts. ( 362 Sq.ft. )
Shop6.23 Sq.mts. ( 67 Sq.ft. )
Shop7.51 Sq.mts. ( 81 Sq.ft. )
Shop10.02 Sq.mts. ( 108 Sq.ft. )
Shop10.24 Sq.mts. ( 110 Sq.ft. )
Shop11.72 Sq.mts. ( 126 Sq.ft. )
Shop11.79 Sq.mts. ( 127 Sq.ft. )
Shop12.51 Sq.mts. ( 135 Sq.ft. )
Shop12.74 Sq.mts. ( 137 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Haware Intelligentia Sigma South Jvlr Wing Alast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Will Be Provided As Per Requirement
Energy management
Energy Saving Devices Will Be Provided
Fire Protection And Fire Safety Requirements
Will Be Done As Per Cfo Norms
Landscaping & Tree Planting
Will Be Provided
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Na
Solid Waste Management And Disposal
Na
Storm Water Drains
Will Be Provided As Per Norms
Street Lighting
Will Be Provided
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Na
Water Supply
Will Be Provided
Buildings / Wings in Haware Intelligentia Sigma South Jvlr Wing A
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Haware Intelligentia Sigma South Jvlr Wing A by Suresh Kashinath Hawarelast updated on 26 Jul 2025 as per information obtained from MARA RERA.

13364 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

140 apartments in total
Total
140
Booked
0
Available
140

Saleable Area Statistics (Sq. ft.)

44469 Total
Total
44469
Booked
0
Available
44469
Total 140 apartments in project. 0 apartments booked. 0% apartments booked.
Total 44469 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.

Wing A Floors 1 To 22

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing A Floors 1 To 22Dec 202423100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
AX0134.87 Sq.mts. ( 375 Sq.ft. )20
None Booked0% Booked
0% Booked
AX0234.9 Sq.mts. ( 376 Sq.ft. )22
None Booked0% Booked
0% Booked
AX0321.32 Sq.mts. ( 229 Sq.ft. )22
None Booked0% Booked
0% Booked
AX0429.08 Sq.mts. ( 313 Sq.ft. )22
None Booked0% Booked
0% Booked
AX0533.65 Sq.mts. ( 362 Sq.ft. )22
None Booked0% Booked
0% Booked
108 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing A Floors 1 To 22Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing A Floors 23 To 27

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing A Floors 23 To 27Dec 202428100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
AX0134.87 Sq.mts. ( 375 Sq.ft. )4
None Booked0% Booked
0% Booked
AX0234.9 Sq.mts. ( 376 Sq.ft. )5
None Booked0% Booked
0% Booked
AX0321.32 Sq.mts. ( 229 Sq.ft. )5
None Booked0% Booked
0% Booked
AX0429.08 Sq.mts. ( 313 Sq.ft. )5
None Booked0% Booked
0% Booked
AX0533.65 Sq.mts. ( 362 Sq.ft. )5
None Booked0% Booked
0% Booked
24 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing A Floors 23 To 27Completion
Basement (if any)
work-in-progress50% done
50% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
work-in-progress50% done
50% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Wing A Ground Floor

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing A Ground FloorDec 202323100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Shop6.23 Sq.mts. ( 67 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop7.51 Sq.mts. ( 81 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop10.02 Sq.mts. ( 108 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop10.24 Sq.mts. ( 110 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop11.72 Sq.mts. ( 126 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop11.79 Sq.mts. ( 127 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop12.51 Sq.mts. ( 135 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop12.74 Sq.mts. ( 137 Sq.ft. )1
None Booked0% Booked
0% Booked
8 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing A Ground FloorCompletion
Basement (if any)
work-in-progress75% done
75% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
work-in-progress75% done
75% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Channel Partners
Channel Partners Registered by Developer
Suresh Kashinath Haware
for Project
Haware Intelligentia Sigma South Jvlr Wing A
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation