Project overview

Goldcrest Business Park is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800001671. Goldcrest Business Park is located at 4064A Pt, 4066 Pt, 4063. This is a Ongoing being developed by Swastik Associates.

Goldcrest Business Park has IT OFFICE Apartments with carpet areas ranging from 1580 to 856 Sq.ft. Carpet. The Project has total 204 of which 116 are currently available for sale.

Goldcrest Business Park is being developed on a total land area of 26664 Sq.ft. Goldcrest Business Park has 1 Wings / Towers Goldcrest Business Park

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Goldcrest Business Park
  • Location:
  • 4064A Pt, 4066 Pt, 4063
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2018
Developer Details

  • Developer:
    Swastik Associates
  • Phone:
  • Address:
  • Swastik Disa Corporate Park
Project RERA Details
MAHA REARA No: P51800001671
Project Type Commercial
RERA Project Status Ongoing
Architect Enclosurre
Funding Bank KOTAK MAHINDRA BANK LIMITED
Proposed Possession 31 Dec 2018
Revised Possession 31 Dec 2018
Extended Possession
Litigations No Litigations
Last Modified 29 Jul 2017
Last Retrived 26 Jul 2025
Goldcrest Business Park QR Code
Goldcrest Business Park
MahaRERA - P51800001671
Apartment Details & Configuration
TypeArea
IT OFFICE34.3 Sq.mts. ( 369 Sq.ft. )
IT OFFICE35.47 Sq.mts. ( 382 Sq.ft. )
IT OFFICE35.48 Sq.mts. ( 382 Sq.ft. )
IT OFFICE37.43 Sq.mts. ( 403 Sq.ft. )
IT OFFICE38.11 Sq.mts. ( 410 Sq.ft. )
IT OFFICE39.18 Sq.mts. ( 422 Sq.ft. )
IT OFFICE39.48 Sq.mts. ( 425 Sq.ft. )
IT OFFICE42.87 Sq.mts. ( 461 Sq.ft. )
IT OFFICE44.09 Sq.mts. ( 475 Sq.ft. )
IT OFFICE53.17 Sq.mts. ( 572 Sq.ft. )
IT OFFICE54.31 Sq.mts. ( 585 Sq.ft. )
IT OFFICE79.49 Sq.mts. ( 856 Sq.ft. )
IT OFFICE146.76 Sq.mts. ( 1580 Sq.ft. )
IT OFFICE243.77 Sq.mts. ( 2624 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Goldcrest Business Parklast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Completed
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Completed
Landscaping & Tree Planting100% completed
95% Complete
Only Tree Planting
Open Parking100% completed
95% Complete
Completed
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Only Chamber Lines
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
Completed
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
Only Rain Water Harvesting
Water Supply100% completed
95% Complete
Completed
Buildings / Wings in Goldcrest Business Park
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Goldcrest Business Park by Swastik Associateslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

26664 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

204 apartments in total
Total
204
Booked
88
Available
116

Saleable Area Statistics (Sq. ft.)

86836 Total
Total
86836
Booked
40843
Available
45992
Total 204 apartments in project. 88 apartments booked. 43% apartments booked.
Total 86836 Sq.ft. saleable area. 40843 saleable area booked.
47% area booked.

Goldcrest Business Park

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Goldcrest Business ParkJan 19001012002141
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
IT OFFICE34.3 Sq.mts. ( 369 Sq.ft. )120
48 Booked40% Booked
40% Booked
IT OFFICE35.47 Sq.mts. ( 382 Sq.ft. )10
3 Booked30% Booked
30% Booked
IT OFFICE35.48 Sq.mts. ( 382 Sq.ft. )10
3 Booked30% Booked
30% Booked
IT OFFICE37.43 Sq.mts. ( 403 Sq.ft. )1
None Booked0% Booked
0% Booked
IT OFFICE38.11 Sq.mts. ( 410 Sq.ft. )9
5 Booked55% Booked
55% Booked
IT OFFICE39.18 Sq.mts. ( 422 Sq.ft. )16
7 Booked43% Booked
43% Booked
IT OFFICE39.48 Sq.mts. ( 425 Sq.ft. )15
10 Booked66% Booked
66% Booked
IT OFFICE42.87 Sq.mts. ( 461 Sq.ft. )1
None Booked0% Booked
0% Booked
IT OFFICE44.09 Sq.mts. ( 475 Sq.ft. )8
7 Booked87% Booked
87% Booked
IT OFFICE53.17 Sq.mts. ( 572 Sq.ft. )9
IT OFFICE54.31 Sq.mts. ( 585 Sq.ft. )1
None Booked0% Booked
0% Booked
IT OFFICE79.49 Sq.mts. ( 856 Sq.ft. )1
1 Booked100% Booked
100% Booked
IT OFFICE146.76 Sq.mts. ( 1580 Sq.ft. )1
1 Booked100% Booked
100% Booked
IT OFFICE243.77 Sq.mts. ( 2624 Sq.ft. )2
2 Booked100% Booked
100% Booked
204 total apartments / 88 apartments booked. 43% apartments booked.
Work Description in Building Goldcrest Business ParkCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Swastik Associates
for Project
Goldcrest Business Park
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation