Project overview

Godrej Urban Park is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800028364. Godrej Urban Park is located at 24. This is a New being developed by Godrej Properties Limited.

Godrej Urban Park has 1 BHK, 2 BHK, Shop & Studio Apartments with carpet areas ranging from 1528 to 836 Sq.ft. Carpet. The Project has total 579 of which 80 are currently available for sale.

Godrej Urban Park is being developed on a total land area of 118232 Sq.ft. out of which 31384 Sq.ft. i.e 27% is reserved for recreational purposes. Godrej Urban Park has 9 Wings / Towers Tower 1,Tower 2,Tower 3,Tower 4,Tower 5,Tower 6,Tower 7,Tower 8,Tower 9

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Godrej Urban Park
  • Location:
  • 24
  • Const. Stage:
    New
  • Possession:
    30 Sep 2026
Developer Details

  • Developer:
    Godrej Properties Limited
  • Phone:
  • Address:
  • Godrej One
Project RERA Details
MAHA REARA No: P51800028364
Project Type Residential / Group Housing
RERA Project Status New
Funding Bank AXIS BANK
Proposed Possession 30 Sep 2026
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 22 Feb 2021
Last Retrived 26 Jul 2025
Godrej Urban Park QR Code
Godrej Urban Park
MahaRERA - P51800028364
Apartment Details & Configuration
TypeArea
3 BHK83.91 Sq.mts. ( 903 Sq.ft. )
3 BHK84.13 Sq.mts. ( 906 Sq.ft. )
3 BHK85.97 Sq.mts. ( 925 Sq.ft. )
Shop94.61 Sq.mts. ( 1018 Sq.ft. )
Shop141.31 Sq.mts. ( 1521 Sq.ft. )
Shop22.53 Sq.mts. ( 243 Sq.ft. )
Shop26.05 Sq.mts. ( 280 Sq.ft. )
3 BHK86.07 Sq.mts. ( 926 Sq.ft. )
3 BHK86.62 Sq.mts. ( 932 Sq.ft. )
3 BHK86.65 Sq.mts. ( 933 Sq.ft. )
3 BHK86.9 Sq.mts. ( 935 Sq.ft. )
3 BHK87.22 Sq.mts. ( 939 Sq.ft. )
Shop20.11 Sq.mts. ( 216 Sq.ft. )
Shop21.87 Sq.mts. ( 235 Sq.ft. )
Shop25.82 Sq.mts. ( 278 Sq.ft. )
Shop26.28 Sq.mts. ( 283 Sq.ft. )
Shop28.36 Sq.mts. ( 305 Sq.ft. )
Shop32.98 Sq.mts. ( 355 Sq.ft. )
Shop40.98 Sq.mts. ( 441 Sq.ft. )
1 BHK40.47 Sq.mts. ( 436 Sq.ft. )
2 BHK55.51 Sq.mts. ( 598 Sq.ft. )
2 BHK55.67 Sq.mts. ( 599 Sq.ft. )
2 BHK55.76 Sq.mts. ( 600 Sq.ft. )
2 BHK56.33 Sq.mts. ( 606 Sq.ft. )
2 BHK56.41 Sq.mts. ( 607 Sq.ft. )
Shop108.3 Sq.mts. ( 1166 Sq.ft. )
Shop123.02 Sq.mts. ( 1324 Sq.ft. )
Shop9.45 Sq.mts. ( 102 Sq.ft. )
Shop11.32 Sq.mts. ( 122 Sq.ft. )
Shop17.53 Sq.mts. ( 189 Sq.ft. )
Shop17.54 Sq.mts. ( 189 Sq.ft. )
Shop21.32 Sq.mts. ( 229 Sq.ft. )
Shop21.6 Sq.mts. ( 233 Sq.ft. )
Shop21.73 Sq.mts. ( 234 Sq.ft. )
Shop23.02 Sq.mts. ( 248 Sq.ft. )
Shop25.84 Sq.mts. ( 278 Sq.ft. )
Shop29.01 Sq.mts. ( 312 Sq.ft. )
Shop31.6 Sq.mts. ( 340 Sq.ft. )
1 BHK40.48 Sq.mts. ( 436 Sq.ft. )
2 BHK55.48 Sq.mts. ( 597 Sq.ft. )
2 BHK58.78 Sq.mts. ( 633 Sq.ft. )
2 BHK58.96 Sq.mts. ( 635 Sq.ft. )
Shop9.93 Sq.mts. ( 107 Sq.ft. )
Shop12.3 Sq.mts. ( 132 Sq.ft. )
Shop15.32 Sq.mts. ( 165 Sq.ft. )
Shop15.34 Sq.mts. ( 165 Sq.ft. )
Shop22.02 Sq.mts. ( 237 Sq.ft. )
Shop27.86 Sq.mts. ( 300 Sq.ft. )
Shop29.39 Sq.mts. ( 316 Sq.ft. )
Shop38.45 Sq.mts. ( 414 Sq.ft. )
Shop38.99 Sq.mts. ( 420 Sq.ft. )
Studio31.16 Sq.mts. ( 335 Sq.ft. )
Shop61.72 Sq.mts. ( 664 Sq.ft. )
Shop62.04 Sq.mts. ( 668 Sq.ft. )
Shop12.45 Sq.mts. ( 134 Sq.ft. )
Shop15.53 Sq.mts. ( 167 Sq.ft. )
Shop16.18 Sq.mts. ( 174 Sq.ft. )
Shop17.98 Sq.mts. ( 194 Sq.ft. )
Shop18.12 Sq.mts. ( 195 Sq.ft. )
Shop19.4 Sq.mts. ( 209 Sq.ft. )
Shop20.59 Sq.mts. ( 222 Sq.ft. )
Shop20.89 Sq.mts. ( 225 Sq.ft. )
1 BHK40.17 Sq.mts. ( 432 Sq.ft. )
1 BHK40.33 Sq.mts. ( 434 Sq.ft. )
1 BHK41.51 Sq.mts. ( 447 Sq.ft. )
1 BHK41.66 Sq.mts. ( 448 Sq.ft. )
2 BHK55.52 Sq.mts. ( 598 Sq.ft. )
2 BHK57.16 Sq.mts. ( 615 Sq.ft. )
Shop94.92 Sq.mts. ( 1022 Sq.ft. )
Shop111.3 Sq.mts. ( 1198 Sq.ft. )
Shop9.11 Sq.mts. ( 98 Sq.ft. )
Shop12.18 Sq.mts. ( 131 Sq.ft. )
Shop13.26 Sq.mts. ( 143 Sq.ft. )
Shop13.55 Sq.mts. ( 146 Sq.ft. )
Shop14.49 Sq.mts. ( 156 Sq.ft. )
Shop14.69 Sq.mts. ( 158 Sq.ft. )
Shop16.36 Sq.mts. ( 176 Sq.ft. )
Shop17.11 Sq.mts. ( 184 Sq.ft. )
Shop17.94 Sq.mts. ( 193 Sq.ft. )
Shop18 Sq.mts. ( 194 Sq.ft. )
Shop20.52 Sq.mts. ( 221 Sq.ft. )
Shop20.94 Sq.mts. ( 225 Sq.ft. )
Shop32.88 Sq.mts. ( 354 Sq.ft. )
Shop36.34 Sq.mts. ( 391 Sq.ft. )
2 BHK58.81 Sq.mts. ( 633 Sq.ft. )
3 BHK82.84 Sq.mts. ( 892 Sq.ft. )
3 BHK83.36 Sq.mts. ( 897 Sq.ft. )
3 BHK87.19 Sq.mts. ( 939 Sq.ft. )
3 BHK87.71 Sq.mts. ( 944 Sq.ft. )
Shop20.95 Sq.mts. ( 226 Sq.ft. )
Shop21.77 Sq.mts. ( 234 Sq.ft. )
Shop23.41 Sq.mts. ( 252 Sq.ft. )
Shop23.69 Sq.mts. ( 255 Sq.ft. )
Shop26.58 Sq.mts. ( 286 Sq.ft. )
Shop28.45 Sq.mts. ( 306 Sq.ft. )
Shop30.54 Sq.mts. ( 329 Sq.ft. )
Shop32.15 Sq.mts. ( 346 Sq.ft. )
Shop32.77 Sq.mts. ( 353 Sq.ft. )
Shop37.05 Sq.mts. ( 399 Sq.ft. )
3 BHK83.89 Sq.mts. ( 903 Sq.ft. )
3 BHK84.41 Sq.mts. ( 909 Sq.ft. )
3 BHK86.52 Sq.mts. ( 931 Sq.ft. )
3 BHK87.04 Sq.mts. ( 937 Sq.ft. )
3 BHK87.66 Sq.mts. ( 944 Sq.ft. )
Shop18.02 Sq.mts. ( 194 Sq.ft. )
Shop18.71 Sq.mts. ( 201 Sq.ft. )
Shop20.99 Sq.mts. ( 226 Sq.ft. )
Shop21.58 Sq.mts. ( 232 Sq.ft. )
Shop24.65 Sq.mts. ( 265 Sq.ft. )
Shop26.62 Sq.mts. ( 287 Sq.ft. )
Shop26.94 Sq.mts. ( 290 Sq.ft. )
Shop28.81 Sq.mts. ( 310 Sq.ft. )
Shop29.83 Sq.mts. ( 321 Sq.ft. )
Shop31.75 Sq.mts. ( 342 Sq.ft. )
1 BHK36.83 Sq.mts. ( 396 Sq.ft. )
1 BHK37.55 Sq.mts. ( 404 Sq.ft. )
1 BHK38.95 Sq.mts. ( 419 Sq.ft. )
1 BHK39.82 Sq.mts. ( 429 Sq.ft. )
2 BHK58.84 Sq.mts. ( 633 Sq.ft. )
2 BHK61.16 Sq.mts. ( 658 Sq.ft. )
2 BHK61.75 Sq.mts. ( 665 Sq.ft. )
Shop77.66 Sq.mts. ( 836 Sq.ft. )
Shop142 Sq.mts. ( 1528 Sq.ft. )
Shop23.32 Sq.mts. ( 251 Sq.ft. )
Shop25.04 Sq.mts. ( 270 Sq.ft. )
Studio25.75 Sq.mts. ( 277 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Godrej Urban Parklast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space90% completed
90% Complete
As Per Approved Plans
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station90% completed
90% Complete
As Per Approved Plans
Energy management75% completed
75% Complete
As Per Approved Plans
Fire Protection And Fire Safety Requirements85% completed
85% Complete
As Per Approved Plans
Landscaping & Tree Planting85% completed
85% Complete
As Per Approved Plans
Open Parking70% completed
70% Complete
As Per Approved Plans
Sewerage (Chamber, Lines, Septic Tank , STP)95% completed
95% Complete
As Per Design
Solid Waste Management And Disposal70% completed
70% Complete
As Per Design
Storm Water Drains80% completed
80% Complete
As Per Approved Plans
Street Lighting50% completed
50% Complete
As Per Design
Treatment And Disposal Of Sewage And Sullage Water80% completed
80% Complete
Stp Provided
Water Conservation, Rain water Harvesting85% completed
85% Complete
As Per Approved Plans
Water Supply80% completed
80% Complete
By Bmc
Buildings / Wings in Godrej Urban Park
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Godrej Urban Park by Godrej Properties Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

118232 Sq. ft.

Project Area

31384 Sq. ft.

Recreational Open Space

Total 9

Wings / Towers in Project

Apartments Statistics

579 apartments in total
Total
579
Booked
499
Available
80

Saleable Area Statistics (Sq. ft.)

351507 Total
Total
351507
Booked
307138
Available
44369
Total 579 apartments in project. 499 apartments booked. 86% apartments booked.
Total 351507 Sq.ft. saleable area. 307138 saleable area booked.
87% area booked.

Tower 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower 1Mar 2026151310081
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK83.91 Sq.mts. ( 903 Sq.ft. )13
13 Booked100% Booked
100% Booked
3 BHK84.13 Sq.mts. ( 906 Sq.ft. )15
15 Booked100% Booked
100% Booked
3 BHK85.97 Sq.mts. ( 925 Sq.ft. )14
11 Booked78% Booked
78% Booked
Shop94.61 Sq.mts. ( 1018 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop141.31 Sq.mts. ( 1521 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop22.53 Sq.mts. ( 243 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop26.05 Sq.mts. ( 280 Sq.ft. )1
1 Booked100% Booked
100% Booked
46 total apartments / 43 apartments booked. 93% apartments booked.
Work Description in Building Tower 1Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower 2Mar 2026151310176
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK86.07 Sq.mts. ( 926 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK86.62 Sq.mts. ( 932 Sq.ft. )12
11 Booked91% Booked
91% Booked
3 BHK86.65 Sq.mts. ( 933 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK86.9 Sq.mts. ( 935 Sq.ft. )14
13 Booked92% Booked
92% Booked
3 BHK87.22 Sq.mts. ( 939 Sq.ft. )12
12 Booked100% Booked
100% Booked
Shop20.11 Sq.mts. ( 216 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop21.87 Sq.mts. ( 235 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop25.82 Sq.mts. ( 278 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop26.28 Sq.mts. ( 283 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop28.36 Sq.mts. ( 305 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop32.98 Sq.mts. ( 355 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop40.98 Sq.mts. ( 441 Sq.ft. )1
1 Booked100% Booked
100% Booked
47 total apartments / 45 apartments booked. 95% apartments booked.
Work Description in Building Tower 2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress95% done
95% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower 3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower 3Mar 2026151310078
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK40.47 Sq.mts. ( 436 Sq.ft. )15
15 Booked100% Booked
100% Booked
2 BHK55.51 Sq.mts. ( 598 Sq.ft. )12
12 Booked100% Booked
100% Booked
2 BHK55.67 Sq.mts. ( 599 Sq.ft. )12
12 Booked100% Booked
100% Booked
2 BHK55.76 Sq.mts. ( 600 Sq.ft. )12
12 Booked100% Booked
100% Booked
2 BHK56.33 Sq.mts. ( 606 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK56.41 Sq.mts. ( 607 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop108.3 Sq.mts. ( 1166 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop123.02 Sq.mts. ( 1324 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop9.45 Sq.mts. ( 102 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop11.32 Sq.mts. ( 122 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop17.53 Sq.mts. ( 189 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop17.54 Sq.mts. ( 189 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop21.32 Sq.mts. ( 229 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop21.6 Sq.mts. ( 233 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop21.73 Sq.mts. ( 234 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop23.02 Sq.mts. ( 248 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop25.84 Sq.mts. ( 278 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop29.01 Sq.mts. ( 312 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop31.6 Sq.mts. ( 340 Sq.ft. )1
1 Booked100% Booked
100% Booked
66 total apartments / 66 apartments booked. 100% apartments booked.
Work Description in Building Tower 3Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress90% done
90% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress79% done
79% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress90% done
90% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower 4

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower 4Mar 2026151310075
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK40.48 Sq.mts. ( 436 Sq.ft. )14
14 Booked100% Booked
100% Booked
2 BHK55.48 Sq.mts. ( 597 Sq.ft. )14
8 Booked57% Booked
57% Booked
2 BHK58.78 Sq.mts. ( 633 Sq.ft. )13
13 Booked100% Booked
100% Booked
2 BHK58.96 Sq.mts. ( 635 Sq.ft. )13
13 Booked100% Booked
100% Booked
Shop9.93 Sq.mts. ( 107 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop12.3 Sq.mts. ( 132 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop15.32 Sq.mts. ( 165 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop15.34 Sq.mts. ( 165 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop22.02 Sq.mts. ( 237 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop27.86 Sq.mts. ( 300 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop29.39 Sq.mts. ( 316 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop38.45 Sq.mts. ( 414 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop38.99 Sq.mts. ( 420 Sq.ft. )1
1 Booked100% Booked
100% Booked
Studio31.16 Sq.mts. ( 335 Sq.ft. )1
1 Booked100% Booked
100% Booked
65 total apartments / 59 apartments booked. 90% apartments booked.
Work Description in Building Tower 4Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress70% done
70% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress70% done
70% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress70% done
70% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress50% done
50% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress59% done
59% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress70% done
70% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower 5

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower 5Mar 2026151310076
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK40.48 Sq.mts. ( 436 Sq.ft. )14
13 Booked92% Booked
92% Booked
2 BHK55.48 Sq.mts. ( 597 Sq.ft. )14
11 Booked78% Booked
78% Booked
2 BHK58.78 Sq.mts. ( 633 Sq.ft. )13
13 Booked100% Booked
100% Booked
2 BHK58.96 Sq.mts. ( 635 Sq.ft. )13
13 Booked100% Booked
100% Booked
Shop61.72 Sq.mts. ( 664 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop62.04 Sq.mts. ( 668 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop12.45 Sq.mts. ( 134 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop15.53 Sq.mts. ( 167 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop16.18 Sq.mts. ( 174 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop17.98 Sq.mts. ( 194 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop18.12 Sq.mts. ( 195 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop19.4 Sq.mts. ( 209 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop20.59 Sq.mts. ( 222 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop20.89 Sq.mts. ( 225 Sq.ft. )1
1 Booked100% Booked
100% Booked
Studio31.16 Sq.mts. ( 335 Sq.ft. )1
1 Booked100% Booked
100% Booked
65 total apartments / 61 apartments booked. 93% apartments booked.
Work Description in Building Tower 5Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress70% done
70% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress70% done
70% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress70% done
70% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress50% done
50% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress59% done
59% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress70% done
70% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower 6

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower 6Mar 20261513100112
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK40.17 Sq.mts. ( 432 Sq.ft. )14
11 Booked78% Booked
78% Booked
1 BHK40.33 Sq.mts. ( 434 Sq.ft. )12
12 Booked100% Booked
100% Booked
1 BHK40.47 Sq.mts. ( 436 Sq.ft. )12
12 Booked100% Booked
100% Booked
1 BHK40.48 Sq.mts. ( 436 Sq.ft. )13
13 Booked100% Booked
100% Booked
1 BHK41.51 Sq.mts. ( 447 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK41.66 Sq.mts. ( 448 Sq.ft. )2
1 Booked50% Booked
50% Booked
2 BHK55.52 Sq.mts. ( 598 Sq.ft. )25
24 Booked96% Booked
96% Booked
2 BHK57.16 Sq.mts. ( 615 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop94.92 Sq.mts. ( 1022 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop111.3 Sq.mts. ( 1198 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop9.11 Sq.mts. ( 98 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop12.18 Sq.mts. ( 131 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop13.26 Sq.mts. ( 143 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop13.55 Sq.mts. ( 146 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop14.49 Sq.mts. ( 156 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop14.69 Sq.mts. ( 158 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop16.36 Sq.mts. ( 176 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop17.11 Sq.mts. ( 184 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop17.94 Sq.mts. ( 193 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop17.98 Sq.mts. ( 194 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop18 Sq.mts. ( 194 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop20.52 Sq.mts. ( 221 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop20.94 Sq.mts. ( 225 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop32.88 Sq.mts. ( 354 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop36.34 Sq.mts. ( 391 Sq.ft. )1
1 Booked100% Booked
100% Booked
97 total apartments / 91 apartments booked. 93% apartments booked.
Work Description in Building Tower 6Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress65% done
65% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress70% done
70% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress70% done
70% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress80% done
80% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress90% done
90% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress90% done
90% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress65% done
65% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower 7

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower 7Mar 2026151310089
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK58.81 Sq.mts. ( 633 Sq.ft. )28
25 Booked89% Booked
89% Booked
3 BHK82.84 Sq.mts. ( 892 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK83.36 Sq.mts. ( 897 Sq.ft. )12
12 Booked100% Booked
100% Booked
3 BHK87.19 Sq.mts. ( 939 Sq.ft. )1
None Booked0% Booked
0% Booked
3 BHK87.71 Sq.mts. ( 944 Sq.ft. )12
11 Booked91% Booked
91% Booked
Shop20.95 Sq.mts. ( 226 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop21.77 Sq.mts. ( 234 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop23.41 Sq.mts. ( 252 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop23.69 Sq.mts. ( 255 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop26.58 Sq.mts. ( 286 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop28.45 Sq.mts. ( 306 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop30.54 Sq.mts. ( 329 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop32.15 Sq.mts. ( 346 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop32.77 Sq.mts. ( 353 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop37.05 Sq.mts. ( 399 Sq.ft. )1
1 Booked100% Booked
100% Booked
65 total apartments / 60 apartments booked. 92% apartments booked.
Work Description in Building Tower 7Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress40% done
40% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress40% done
40% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress40% done
40% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress40% done
40% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress45% done
45% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress45% done
45% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower 8

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower 8Mar 2026151310079
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK83.89 Sq.mts. ( 903 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK84.41 Sq.mts. ( 909 Sq.ft. )12
12 Booked100% Booked
100% Booked
3 BHK86.52 Sq.mts. ( 931 Sq.ft. )1
None Booked0% Booked
0% Booked
3 BHK87.04 Sq.mts. ( 937 Sq.ft. )12
11 Booked91% Booked
91% Booked
3 BHK87.66 Sq.mts. ( 944 Sq.ft. )14
13 Booked92% Booked
92% Booked
Shop18.02 Sq.mts. ( 194 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop18.71 Sq.mts. ( 201 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop20.99 Sq.mts. ( 226 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop21.58 Sq.mts. ( 232 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop24.65 Sq.mts. ( 265 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop26.62 Sq.mts. ( 287 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop26.94 Sq.mts. ( 290 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop28.45 Sq.mts. ( 306 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop28.81 Sq.mts. ( 310 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop29.39 Sq.mts. ( 316 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop29.83 Sq.mts. ( 321 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop31.75 Sq.mts. ( 342 Sq.ft. )1
1 Booked100% Booked
100% Booked
52 total apartments / 49 apartments booked. 94% apartments booked.
Work Description in Building Tower 8Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress30% done
30% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress30% done
30% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress30% done
30% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress30% done
30% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress41% done
41% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress40% done
40% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress40% done
40% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower 9

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower 9Mar 2026111310095
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36.83 Sq.mts. ( 396 Sq.ft. )13
1 BHK37.55 Sq.mts. ( 404 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK38.95 Sq.mts. ( 419 Sq.ft. )15
5 Booked33% Booked
33% Booked
1 BHK39.82 Sq.mts. ( 429 Sq.ft. )15
2 BHK58.84 Sq.mts. ( 633 Sq.ft. )13
6 Booked46% Booked
46% Booked
2 BHK61.16 Sq.mts. ( 658 Sq.ft. )13
5 Booked38% Booked
38% Booked
2 BHK61.75 Sq.mts. ( 665 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop77.66 Sq.mts. ( 836 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop142 Sq.mts. ( 1528 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop23.32 Sq.mts. ( 251 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop25.04 Sq.mts. ( 270 Sq.ft. )1
1 Booked100% Booked
100% Booked
Studio25.75 Sq.mts. ( 277 Sq.ft. )1
None Booked0% Booked
0% Booked
76 total apartments / 25 apartments booked. 32% apartments booked.
Work Description in Building Tower 9Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress56% done
56% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress20% done
20% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress20% done
20% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress56% done
56% Booked
Channel Partners
Channel Partners Registered by Developer
Godrej Properties Limited
for Project
Godrej Urban Park
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation