Project overview

GHATKOPAR AVENUE AARADHYA ONE EARTH PHASE I is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800024676. GHATKOPAR AVENUE AARADHYA ONE EARTH PHASE I is located at S No 236 A Part And Cts No 194 A. This is a New being developed by MAN REALTORS AND HOLDINGS PRIVATE LIMITED.

GHATKOPAR AVENUE AARADHYA ONE EARTH PHASE I has 1 BHK, 2 BHK & 2 BHK WITH BALCONY Apartments with carpet areas ranging from 488 to 712 Sq.ft. Carpet. The Project has total 632 of which 0 are currently available for sale.

GHATKOPAR AVENUE AARADHYA ONE EARTH PHASE I is being developed on a total land area of 36221 Sq.ft. GHATKOPAR AVENUE AARADHYA ONE EARTH PHASE I has 8 Wings / Towers Rehab Tower 1 - Alpha,Rehab Tower 2 - Breeze,Rehab Tower 3 - Coral,Rehab Tower 4 - Delta,Rehab Tower 5 - Eve,Tower A - Avion,Tower C - Casa,Tower D - Dew

ProjectDeveloperLocationPossession
Project Details
  • Project:
    GHATKOPAR AVENUE AARADHYA ONE EARTH PHASE I
  • Location:
  • S No 236 A Part And Cts No 194 A
  • Const. Stage:
    New
  • Possession:
    30 Mar 2025
Developer Details

  • Developer:
    MAN REALTORS AND HOLDINGS PRIVATE LIMITED
  • Phone:
  • Address:
  • Krushal Commercial Complex
Project RERA Details
MAHA REARA No: P51800024676
Project Type Others
RERA Project Status New
Funding Bank ICICI BANK LIMITED
Proposed Possession 30 Mar 2025
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 19 Oct 2020
Last Retrived 13 Feb 2026
GHATKOPAR AVENUE AARADHYA ONE EARTH PHASE I QR Code
GHATKOPAR AVENUE AARADHYA ONE EARTH PHASE I
MahaRERA - P51800024676
Apartment Details & Configuration
TypeArea
1.5 BHK47.47 Sq.mts. ( 511 Sq.ft. )
2 BHK66.43 Sq.mts. ( 715 Sq.ft. )
2 BHKwithbalcony67.08 Sq.mts. ( 722 Sq.ft. )
3 BHK92.9 Sq.mts. ( 1000 Sq.ft. )
3 BHK101.91 Sq.mts. ( 1097 Sq.ft. )
Shop23 Sq.mts. ( 248 Sq.ft. )
Shop25 Sq.mts. ( 269 Sq.ft. )
Shop40 Sq.mts. ( 431 Sq.ft. )
2 BHK WITH BALCONY75.07 Sq.mts. ( 808 Sq.ft. )
1 BHK45.34 Sq.mts. ( 488 Sq.ft. )
2 BHK61.78 Sq.mts. ( 665 Sq.ft. )
2 BHK WITH BALCONY66.15 Sq.mts. ( 712 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of GHATKOPAR AVENUE AARADHYA ONE EARTH PHASE Ilast updated on 13 Feb 2026 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station80% completed
80% Complete
Wip/No Receiving Station
Energy management
Na
Fire Protection And Fire Safety Requirements80% completed
80% Complete
Wip
Landscaping & Tree Planting70% completed
70% Complete
Wip
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completed
Solid Waste Management And Disposal80% completed
80% Complete
Wip
Storm Water Drains100% completed
95% Complete
Completed
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water80% completed
80% Complete
Wip
Water Conservation, Rain water Harvesting80% completed
80% Complete
Wip
Water Supply100% completed
95% Complete
Completed
Buildings / Wings in GHATKOPAR AVENUE AARADHYA ONE EARTH PHASE I
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of GHATKOPAR AVENUE AARADHYA ONE EARTH PHASE I by MAN REALTORS AND HOLDINGS PRIVATE LIMITEDlast updated on 13 Feb 2026 as per information obtained from MARA RERA.

36221 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 8

Wings / Towers in Project

Apartments Statistics

632 apartments in total
Total
632
Booked
632
Available
0

Saleable Area Statistics (Sq. ft.)

366929 Total
Total
366929
Booked
366929
Available
0
Total 632 apartments in project. 632 apartments booked. 100% apartments booked.
Total 366929 Sq.ft. saleable area. 366929 saleable area booked.
100% area booked.

Rehab Tower 1 - Alpha

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Rehab Tower 1 - AlphaMar 2024181310028
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.5 BHK47.47 Sq.mts. ( 511 Sq.ft. )115
115 Booked100% Booked
100% Booked
115 total apartments / 115 apartments booked. 100% apartments booked.
Work Description in Building Rehab Tower 1 - AlphaCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Rehab Tower 2 - Breeze

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Rehab Tower 2 - BreezeMar 2024181310029
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.5 BHK47.47 Sq.mts. ( 511 Sq.ft. )116
116 Booked100% Booked
100% Booked
116 total apartments / 116 apartments booked. 100% apartments booked.
Work Description in Building Rehab Tower 2 - BreezeCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Rehab Tower 3 - Coral

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Rehab Tower 3 - CoralMar 2024181310017
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.5 BHK47.47 Sq.mts. ( 511 Sq.ft. )66
66 Booked100% Booked
100% Booked
66 total apartments / 66 apartments booked. 100% apartments booked.
Work Description in Building Rehab Tower 3 - CoralCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Rehab Tower 4 - Delta

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Rehab Tower 4 - DeltaMar 2024181310025
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.5 BHK47.47 Sq.mts. ( 511 Sq.ft. )100
100 Booked100% Booked
100% Booked
100 total apartments / 100 apartments booked. 100% apartments booked.
Work Description in Building Rehab Tower 4 - DeltaCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Rehab Tower 5 - Eve

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Rehab Tower 5 - EveMar 2024181310013
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.5 BHK47.47 Sq.mts. ( 511 Sq.ft. )51
51 Booked100% Booked
100% Booked
51 total apartments / 51 apartments booked. 100% apartments booked.
Work Description in Building Rehab Tower 5 - EveCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower A - Avion

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower A - AvionMar 2024171310090
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK66.43 Sq.mts. ( 715 Sq.ft. )44
44 Booked100% Booked
100% Booked
2 BHKwithbalcony66.43 Sq.mts. ( 715 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHKwithbalcony67.08 Sq.mts. ( 722 Sq.ft. )30
30 Booked100% Booked
100% Booked
3 BHK92.9 Sq.mts. ( 1000 Sq.ft. )13
13 Booked100% Booked
100% Booked
3 BHK101.91 Sq.mts. ( 1097 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop23 Sq.mts. ( 248 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop25 Sq.mts. ( 269 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop40 Sq.mts. ( 431 Sq.ft. )1
1 Booked100% Booked
100% Booked
92 total apartments / 92 apartments booked. 100% apartments booked.
Work Description in Building Tower A - AvionCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower C - Casa

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower C - CasaMar 2024171310047
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK66.43 Sq.mts. ( 715 Sq.ft. )31
31 Booked100% Booked
100% Booked
2 BHK WITH BALCONY75.07 Sq.mts. ( 808 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK WITH BALCONY92.9 Sq.mts. ( 1000 Sq.ft. )15
15 Booked100% Booked
100% Booked
47 total apartments / 47 apartments booked. 100% apartments booked.
Work Description in Building Tower C - CasaCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower D - Dew

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower D - DewMar 2024171310045
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK45.34 Sq.mts. ( 488 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK61.78 Sq.mts. ( 665 Sq.ft. )14
14 Booked100% Booked
100% Booked
2 BHK WITH BALCONY66.15 Sq.mts. ( 712 Sq.ft. )30
30 Booked100% Booked
100% Booked
45 total apartments / 45 apartments booked. 100% apartments booked.
Work Description in Building Tower D - DewCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
MAN REALTORS AND HOLDINGS PRIVATE LIMITED
for Project
GHATKOPAR AVENUE AARADHYA ONE EARTH PHASE I
last updated on 13 Feb 2026 as per information obtained from MARA RERA.