Project overview

Ghatkopar Avenue Aaradhya One Earth Phase I is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800024676. Ghatkopar Avenue Aaradhya One Earth Phase I is located at S No 236 A Part And Cts No 194 A. This is a New being developed by Man Realtors And Holdings Private Limited.

Ghatkopar Avenue Aaradhya One Earth Phase I has 1 BHK, 2 BHK & 2 BHK WITH BALCONY Apartments with carpet areas ranging from 488 to 712 Sq.ft. Carpet. The Project has total 632 of which 0 are currently available for sale.

Ghatkopar Avenue Aaradhya One Earth Phase I is being developed on a total land area of 36221 Sq.ft. Ghatkopar Avenue Aaradhya One Earth Phase I has 8 Wings / Towers Rehab Tower 1 - Alpha,Rehab Tower 2 - Breeze,Rehab Tower 3 - Coral,Rehab Tower 4 - Delta,Rehab Tower 5 - Eve,Tower A - Avion,Tower C - Casa,Tower D - Dew

ProjectDeveloperLocationPossession
Deeplaxmi HeightDeep Laxmi DevelopersS No 159, H No 11 Part31-12-2020 00:00:00
Sini EnterprisesVinod Balnath PatilSurvey No. 1330-12-2023 00:00:00
Vivanta S BlissJai Bhawani Orchid Infra Llp53/5 53/6 310/2 310/3 310/430-06-2022 00:00:00
Vivanta Bliss Phase IiJai Bhawani Orchid Infra LlpS No 53/5, 53/6, 310/2, 310/3 & 310/4, 51/4, 51/2, 51/10 And 51/3B31-12-2028 00:00:00
Ashar Maple BirchMs Ashar RealtorsCts No.18 B Of Village Mulund30-12-2025 00:00:00
Pushpanjali ResidencyShree Dham Developers352 Pt30-12-2023 00:00:00
Sheetal Standard BatteriesSheetal Developers97A 2630-12-2023 00:00:00
Kadri ResidencyKadri Construction122A/1 To 7, 122A30-12-2024 00:00:00
HorizonCrescent SheltersCts No 13330-12-2023 00:00:00
Shivdarshan Phase ISpace Developer575, 35130-10-2020 00:00:00
Ghatkopar Avenue Aaradhya One Earth Phase IMan Realtors And Holdings Private LimitedS No 236 A Part And Cts No 194 A30-03-2025 00:00:00
Saptarshi ClassicRockford Ventures Llp1130-12-2025 00:00:00
FairmontTrident Ozone Llp112, 112 /1 To 1630-12-2026 00:00:00
Eksar Gurukripa Chs LtdWestin Homes Llp2247-B30-06-2023 00:00:00
Durgamata HouseZulfiqar Haider Safdar Sayyed529-530-53130-12-2021 00:00:00
Swastik PearlSuvasya Builders And Developers Llp352 Pt30-12-2024 00:00:00
Gayatri Chsl 8Th 9Th FloorKhushi Associates268/B30-12-2021 00:00:00
Ghatkopar Avenue Aaradhya One Earth Phase IiMan Realtors And Holdings Private LimitedS No 236 A Part And Cts No 194 A30-03-2028 00:00:00
Pratap PalaceJpv Realtors Private LimitedCts No 15/1 To 15/8, Cts No 1530-03-2025 00:00:00
Redevelopment Of Malad Amber ChslPranav Constructions Limited647/1 To 10, Village Malad North, Cts No. 64730-10-2023 00:00:00
The Sanctuary - Tower 4Runwal Construction Private Limited544 And 544/130-06-2026 00:00:00
Arkade SereneArkade Developers Private Limited33/1430-06-2024 00:00:00
Kush SymphonyKush Buildcon LlpCts No 784 Of Village Mulund West31-12-2023 00:00:00
Arihant EnclaveM/S Arihant EnterpriseCts No 127A And 127B Of Village Mogra31-12-2023 00:00:00
Om Residency 1132-A30-06-2023 00:00:00
19 NorthDimple Realtors Private LimitedCts No 692, 721, 719, 711C. Land Area Of This Project Is Inclusive Of Ptc Building And Recreational Open Space, 710, 711B30-06-2025 00:00:00
Urban WaterfrontHarekrushna Developers LlpB906 B/1 Pt, B-1152 Pt30-06-2026 00:00:00
Urban WavesHarekrushna Developers LlpB-906 B/1 Pt, B-1152 Pt30-06-2025 00:00:00
Shraddha ChhayaShraddha Chhaya Developers Llp441-44230-03-2023 00:00:00
66 PalazzioParsh Realty36A/ 164/ 164/1 /164/715-06-2025 00:00:00
Saraswati SadanLakshmi Builders And Developers739 1 To 4, 73901-07-2024 00:00:00
Taxmen Coop Hsg Society LtdRaj BuildersPlot No 11/Cts No 308/6 Of Valnai Village02-04-2024 00:00:00
Jyotika HeightsIcon DevelopersOpp. Mcgm Office, Kandivali - West, M. G. Cross Road No - 02, Mumbai.29-02-2024 00:00:00
Redevelopment Of Borivali Shivdarshan ChslPranav Constructions LimitedNew Final Plot No 719/1130-03-2024 00:00:00
Sheetal Ganga GobindSheetala Developers638701-05-2024 00:00:00
Varshkrushna HeightsKrishna Thale &Amp; Kailash ThaleMumbai Suburban01-06-2024 00:00:00
Shradha ResidencyKonark Shradha RealtorsCts 72, 72/1 To 1030-06-2023 00:00:00
Tulsi Chamber Phase IiSurana Construction (Chembur )38530-06-2024 00:00:00
Pallavi ChhayaAtharva DevelopersBuilding No 5, Chembur Village, Cts No 58 Pt, Mumbai Suburban: 40007130-06-2025 00:00:00
Pant Nagar Saraswati ChslKyraa Infra Projects574030-06-2026 00:00:00
Hari Prasad BuildingNirmitee DevelopersC.T.S. Nos. 2117, 2117 1 To 530-11-2022 00:00:00
Ghatkopar Avenue Aaradhya One Earth E Phase IiMan Realtors And Holdings Private LimitedS No 236 A Part And Cts No 194 A30-09-2025 00:00:00
Ghatkopar Avenue Aaradhya One Earth B Phase IiiMan Realtors And Holdings Private LimitedS No 236A Part And Cts No 194A30-03-2025 00:00:00
Ghatkopar Avenue Aaradhya One Earth F Phase IvMan Realtors And Holdings Pvt LtdS. No 236A Part And Cts No 194A30-09-2025 00:00:00
Ghatkopar Avenue Aaradhya One Earth I Phase VMan Realtors And Holdings Private LimitedS No 236A Part And Cts No 194A30-06-2026 00:00:00
Shreenaths LegacyMehul Kirit Mehta23731-07-2024 00:00:00
Raheja AscencioK Raheja Corp Real Estate Private LimitedMumbai, Taluka Kurla, 119D/1A/1 Of Village Tungwa30-05-2025 00:00:00
Auris Ilaria Tower ATranscon-Sheth Creators Private Limited40006430-10-2027 00:00:00
RajkamalKhushi Associates2114/B/130-06-2025 00:00:00
Pratap GrandeurM/S Jpv RealtorsCts No 34630-06-2025 00:00:00
Goregaon Sukhniwas Co-Operative Housing Society LimitedDilip Doshi349 Part 3491 To 430-06-2024 00:00:00
Tower 28 - C And FShiv Shakti Builders And Developers19/1 To 67, 20 And 20/1 To 121, 1930-06-2025 00:00:00
Jayant VillaYog Life Spaces Llp5179 To 518711-01-2025 00:00:00
Kush SolitaireKush Buildcon LlpCts No 769 Of Village Malad East30-12-2023 00:00:00
Auris Ilaria Tower C Phase I Commercial ShopTranscon-Sheth Creators Private Limited40006430-04-2027 00:00:00
Pranay ApsaraPranay Real Estate Developers2728H-275531-12-2024 00:00:00
Panom Park Wing E Sale Building No.3Panom Developers Llp354Pt28-02-2023 00:00:00
Rishabraj SurajH Rishabraj RealtyPlot No 2231-05-2024 00:00:00
Ghatkopar Avenue Aaradhya One Earth G Phase ViMan Realtors And Holdings Private LimitedS No 236A Part And Cts No 194A30-06-2025 00:00:00
Redevelopment Of Popular Terrace ChslPranav Constructions LimitedFinal Plot No 62030-09-2024 00:00:00
Olivia BlissJai Bhawani Orchid Infra LlpS No 54, H No 631-12-2026 00:00:00
Laxminarayan Sra Chs LtdShree S S Developers Private Limited226 Part 226/1 And 226/20 Part30-12-2025 00:00:00
AnantyaShree Krishna Homes Pvt. Ltd.566230-09-2022 00:00:00
Ganesh ResidencyShree Venkateshwara Developers2725-07-2023 00:00:00
Priya Co-Operative Housing Society Ltd.Arjunsingh Bhoorsingh Rathore521/230-06-2023 00:00:00
Kukreja Gardens Wing BTolaram And CoCts No 465/A 465 A/1 To 20 And 465/B Of Village Bhandup Taluka Kurla S Ward, Mumbai Suburban District Lbs Marg Bhandup West30-04-2026 00:00:00
The Sanctuary - Tower 5Runwal Construction Private Limited544 And 544/131-03-2026 00:00:00
KavitaManisha Elite Realty Private Limited568 A/230-05-2024 00:00:00
Borivali Nirmala Sadan Chs LtdShreenath Realty Llp246D30-06-2023 00:00:00
The Sagar Co-Op. Housing Society Ltd.J.K.Construction Co.Mumbai Suburban31-07-2023 00:00:00
La PrendaD M Lifespaces262, 2661 To 8, 26630-12-2024 00:00:00
IconRaghu Leela Realtors Private Limited37 1 To 85 Of Village Kandivali, 32 Pt, 3731-12-2027 00:00:00
Neelkanth Jyot Chs Ltd.SchemaaticsCts No. 195126, Plot No. 16830-12-2024 00:00:00
Arkade Earth - HazelArkade Developers Private Limited101930-12-2023 00:00:00
Sheetal GrandeurD.G. Land Developers Private Limited7262 6951 Pt Old And 7262 6951 A New01-10-2023 00:00:00
Hs OzoneHs Chetana Enterprises Nx Llp5662 Part30-06-2024 00:00:00
ShrishtiDhruva Mahendra RathodPlot No 358/A Cts No 370E25-12-2024 00:00:00
Lashkaria PearlLashkaria Housing & Infrastructure Private LimitedCts No 325 325/1 32601-11-2025 00:00:00
Arihant City Phase-Ii - K BuildingArihant Enterprises49/1P,49/2,49/3P,50/1P,52/1P,52/1P,53/1P,53/1P,53/1P,53/2P,55P,55P,55P,56P30-06-2026 00:00:00
Ncp Commercial Tower - SupremusMacrotech Developers LimitedWtt, C.S. No.8 Pt. Salt Pan Division, Block C30-03-2024 00:00:00
Project Details
  • Project:
    Ghatkopar Avenue Aaradhya One Earth Phase I
  • Location:
  • S No 236 A Part And Cts No 194 A
  • Const. Stage:
    New
  • Possession:
    30 Mar 2025
Developer Details

  • Developer:
    Man Realtors And Holdings Private Limited
  • Phone:
  • Address:
  • Krushal Commercial Complex
Project RERA Details
MAHA REARA No: P51800024676
Project Type Others
RERA Project Status New
Funding Bank ICICI BANK LIMITED
Proposed Possession 30 Mar 2025
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 19 Oct 2020
Last Retrived 26 Jul 2025
Ghatkopar Avenue Aaradhya One Earth Phase I QR Code
Ghatkopar Avenue Aaradhya One Earth Phase I
MahaRERA - P51800024676
Apartment Details & Configuration
TypeArea
1.5 BHK47.47 Sq.mts. ( 511 Sq.ft. )
2 BHK66.43 Sq.mts. ( 715 Sq.ft. )
2 BHKwithbalcony67.08 Sq.mts. ( 722 Sq.ft. )
3 BHK92.9 Sq.mts. ( 1000 Sq.ft. )
3 BHK101.91 Sq.mts. ( 1097 Sq.ft. )
Shop23 Sq.mts. ( 248 Sq.ft. )
Shop25 Sq.mts. ( 269 Sq.ft. )
Shop40 Sq.mts. ( 431 Sq.ft. )
2 BHK WITH BALCONY75.07 Sq.mts. ( 808 Sq.ft. )
1 BHK45.34 Sq.mts. ( 488 Sq.ft. )
2 BHK61.78 Sq.mts. ( 665 Sq.ft. )
2 BHK WITH BALCONY66.15 Sq.mts. ( 712 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Ghatkopar Avenue Aaradhya One Earth Phase Ilast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station80% completed
80% Complete
Wip/No Receiving Station
Energy management
Na
Fire Protection And Fire Safety Requirements80% completed
80% Complete
Wip
Landscaping & Tree Planting70% completed
70% Complete
Wip
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completed
Solid Waste Management And Disposal80% completed
80% Complete
Wip
Storm Water Drains100% completed
95% Complete
Completed
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water80% completed
80% Complete
Wip
Water Conservation, Rain water Harvesting80% completed
80% Complete
Wip
Water Supply100% completed
95% Complete
Completed
Buildings / Wings in Ghatkopar Avenue Aaradhya One Earth Phase I
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Ghatkopar Avenue Aaradhya One Earth Phase I by Man Realtors And Holdings Private Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

36221 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 8

Wings / Towers in Project

Apartments Statistics

632 apartments in total
Total
632
Booked
632
Available
0

Saleable Area Statistics (Sq. ft.)

366929 Total
Total
366929
Booked
366929
Available
0
Total 632 apartments in project. 632 apartments booked. 100% apartments booked.
Total 366929 Sq.ft. saleable area. 366929 saleable area booked.
100% area booked.

Rehab Tower 1 - Alpha

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Rehab Tower 1 - AlphaMar 2024181310028
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.5 BHK47.47 Sq.mts. ( 511 Sq.ft. )115
115 Booked100% Booked
100% Booked
115 total apartments / 115 apartments booked. 100% apartments booked.
Work Description in Building Rehab Tower 1 - AlphaCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Rehab Tower 2 - Breeze

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Rehab Tower 2 - BreezeMar 2024181310029
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.5 BHK47.47 Sq.mts. ( 511 Sq.ft. )116
116 Booked100% Booked
100% Booked
116 total apartments / 116 apartments booked. 100% apartments booked.
Work Description in Building Rehab Tower 2 - BreezeCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Rehab Tower 3 - Coral

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Rehab Tower 3 - CoralMar 2024181310017
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.5 BHK47.47 Sq.mts. ( 511 Sq.ft. )66
66 Booked100% Booked
100% Booked
66 total apartments / 66 apartments booked. 100% apartments booked.
Work Description in Building Rehab Tower 3 - CoralCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Rehab Tower 4 - Delta

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Rehab Tower 4 - DeltaMar 2024181310025
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.5 BHK47.47 Sq.mts. ( 511 Sq.ft. )100
100 Booked100% Booked
100% Booked
100 total apartments / 100 apartments booked. 100% apartments booked.
Work Description in Building Rehab Tower 4 - DeltaCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Rehab Tower 5 - Eve

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Rehab Tower 5 - EveMar 2024181310013
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.5 BHK47.47 Sq.mts. ( 511 Sq.ft. )51
51 Booked100% Booked
100% Booked
51 total apartments / 51 apartments booked. 100% apartments booked.
Work Description in Building Rehab Tower 5 - EveCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower A - Avion

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower A - AvionMar 2024171310090
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK66.43 Sq.mts. ( 715 Sq.ft. )44
44 Booked100% Booked
100% Booked
2 BHKwithbalcony66.43 Sq.mts. ( 715 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHKwithbalcony67.08 Sq.mts. ( 722 Sq.ft. )30
30 Booked100% Booked
100% Booked
3 BHK92.9 Sq.mts. ( 1000 Sq.ft. )13
13 Booked100% Booked
100% Booked
3 BHK101.91 Sq.mts. ( 1097 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop23 Sq.mts. ( 248 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop25 Sq.mts. ( 269 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop40 Sq.mts. ( 431 Sq.ft. )1
1 Booked100% Booked
100% Booked
92 total apartments / 92 apartments booked. 100% apartments booked.
Work Description in Building Tower A - AvionCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower C - Casa

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower C - CasaMar 2024171310047
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK66.43 Sq.mts. ( 715 Sq.ft. )31
31 Booked100% Booked
100% Booked
2 BHK WITH BALCONY75.07 Sq.mts. ( 808 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK WITH BALCONY92.9 Sq.mts. ( 1000 Sq.ft. )15
15 Booked100% Booked
100% Booked
47 total apartments / 47 apartments booked. 100% apartments booked.
Work Description in Building Tower C - CasaCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower D - Dew

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower D - DewMar 2024171310045
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK45.34 Sq.mts. ( 488 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK61.78 Sq.mts. ( 665 Sq.ft. )14
14 Booked100% Booked
100% Booked
2 BHK WITH BALCONY66.15 Sq.mts. ( 712 Sq.ft. )30
30 Booked100% Booked
100% Booked
45 total apartments / 45 apartments booked. 100% apartments booked.
Work Description in Building Tower D - DewCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Man Realtors And Holdings Private Limited
for Project
Ghatkopar Avenue Aaradhya One Earth Phase I
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation