Project overview
GENESIS is a MahaRERA Registered Project bearing MahaRERA Registration Number P52000002114. GENESIS is located at Plot-4, Sector-10B, Ulwe. This is a Ongoing being developed by TODAY PRACHAR REALTY.
GENESIS has 2 BHK Apartments with carpet areas ranging from 405 to 456 Sq.ft. Carpet. The Project has total 54 of which 44 are currently available for sale.
GENESIS is being developed on a total land area of 16658 Sq.ft. GENESIS has 1 Wings / Towers Genesis
| Project | Developer | Location | Possession |
-
Project:
GENESIS
-
Location:
-
Plot-4, Sector-10B, Ulwe
-
Const. Stage:
Ongoing
-
Possession:
31 Mar 2018
-
Developer:
TODAY PRACHAR REALTY
-
Phone:
-
Address:
-
Shelton Cubix,
| MAHA REARA No: |
P52000002114 |
| Project Type |
Residential / Group Housing |
| RERA Project Status |
Ongoing |
| Architect |
Soyuz Talib Architects Pvt Ltd |
| Funding Bank |
INDIAN OVERSEAS BANK |
| Proposed Possession |
31 Mar 2018 |
| Revised Possession |
31 Mar 2018 |
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
31 Jul 2017 |
| Last Retrived |
14 Feb 2026 |
GENESIS QR Code
GENESIS
MahaRERA - P52000002114
| Type | Area |
| 2 BHK | 37.64 Sq.mts. ( 405 Sq.ft. ) |
| 2 BHK | 38.44 Sq.mts. ( 414 Sq.ft. ) |
| 2 BHK | 40.64 Sq.mts. ( 437 Sq.ft. ) |
| 2 BHK | 42.39 Sq.mts. ( 456 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of GENESISlast updated on 14 Feb 2026 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
|
Fitness Center |
Electrical Meter Room, Sub-Station, Receiving Station100% completed
|
|
In Later Scope Of Work |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements100% completed
|
|
In Progress |
Landscaping & Tree Planting
|
|
In Later Scope Of Work |
|
|
|
In Progress |
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
|
|
In Progress |
Solid Waste Management And Disposal
|
|
Na |
Storm Water Drains100% completed
|
|
- |
|
|
|
Na |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting100% completed
|
|
In Progress |
|
|
|
Temporary Water Connection In Place |
Buildings / Wings in GENESIS
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of GENESIS by TODAY PRACHAR REALTYlast updated on 14 Feb 2026 as per information obtained from MARA RERA.
Apartments Statistics
54
apartments in total
Saleable Area Statistics (Sq. ft.)
23740
Total
Total 54 apartments in project. 10 apartments booked. 18% apartments booked.
Total 23740 Sq.ft. saleable area. 4563 saleable area booked.
19% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Genesis | Jan 1900 | 15 | 1 | 0 | 1 | 0 | 7 | 1 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 2 BHK | 37.64 Sq.mts. ( 405 Sq.ft. ) | 2 | |
| 2 BHK | 38.44 Sq.mts. ( 414 Sq.ft. ) | 13 | |
| 2 BHK | 40.64 Sq.mts. ( 437 Sq.ft. ) | 13 | |
| 2 BHK | 42.39 Sq.mts. ( 456 Sq.ft. ) | 26 | |
54 total apartments / 10 apartments booked. 18% apartments booked. |
| Work Description in Building Genesis | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
Channel Partners Registered by Developer
TODAY PRACHAR REALTY
for Project
GENESIS
last updated on
14 Feb 2026 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |