Project overview

Gaurav Saffron is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700003472. Gaurav Saffron is located at 417/5, 418/2,3. This is a Ongoing being developed by Ravi Developments.

Gaurav Saffron has 1 BHK, 2 BHK & 3 BHK Apartments with carpet areas ranging from 428 to 711 Sq.ft. Carpet. The Project has total 156 of which 5 are currently available for sale.

Gaurav Saffron is being developed on a total land area of 6486 Sq.ft. Gaurav Saffron has 2 Wings / Towers Saffron A,Saffron B

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Gaurav Saffron
  • Location:
  • 417/5, 418/2,3
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2022
Developer Details

  • Developer:
    Ravi Developments
  • Phone:
  • Address:
  • Laxmi Palace
Project RERA Details
MAHA REARA No: P51700003472
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Anish & Associates
Funding Bank YES BANK
Proposed Possession 30 Dec 2022
Revised Possession 30 Dec 2022
Extended Possession 31 Dec 2024
Litigations No Litigations
Last Modified 06 Mar 2025
Last Retrived 26 Jul 2025
Gaurav Saffron QR Code
Gaurav Saffron
MahaRERA - P51700003472
Apartment Details & Configuration
TypeArea
1 BHK32.72 Sq.mts. ( 352 Sq.ft. )
1 BHK39.76 Sq.mts. ( 428 Sq.ft. )
2 BHK49.42 Sq.mts. ( 532 Sq.ft. )
2 BHK50.7 Sq.mts. ( 546 Sq.ft. )
2 BHK51.23 Sq.mts. ( 551 Sq.ft. )
1 BHK39.74 Sq.mts. ( 428 Sq.ft. )
2 BHK48.49 Sq.mts. ( 522 Sq.ft. )
3 BHK66.06 Sq.mts. ( 711 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Gaurav Saffronlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
0
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
0
Energy management
Na
Fire Protection And Fire Safety Requirements
0
Landscaping & Tree Planting
Na
Open Parking
0
Sewerage (Chamber, Lines, Septic Tank , STP)
0
Solid Waste Management And Disposal
0
Storm Water Drains
0
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
0
Water Supply
Na
Buildings / Wings in Gaurav Saffron
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Gaurav Saffron by Ravi Developmentslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

6486 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

156 apartments in total
Total
156
Booked
151
Available
5

Saleable Area Statistics (Sq. ft.)

82723 Total
Total
82723
Booked
79546
Available
3177
Total 156 apartments in project. 151 apartments booked. 96% apartments booked.
Total 82723 Sq.ft. saleable area. 79546 saleable area booked.
96% area booked.

Saffron A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Saffron ADec 2022171010079
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.72 Sq.mts. ( 352 Sq.ft. )14
14 Booked100% Booked
100% Booked
1 BHK39.76 Sq.mts. ( 428 Sq.ft. )16
16 Booked100% Booked
100% Booked
2 BHK49.42 Sq.mts. ( 532 Sq.ft. )16
16 Booked100% Booked
100% Booked
2 BHK50.7 Sq.mts. ( 546 Sq.ft. )16
16 Booked100% Booked
100% Booked
2 BHK51.23 Sq.mts. ( 551 Sq.ft. )16
16 Booked100% Booked
100% Booked
78 total apartments / 78 apartments booked. 100% apartments booked.
Work Description in Building Saffron ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress73% done
73% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress82% done
82% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress74% done
74% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress67% done
67% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress83% done
83% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress72% done
72% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Saffron B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Saffron BDec 2022171010078
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK39.74 Sq.mts. ( 428 Sq.ft. )16
16 Booked100% Booked
100% Booked
2 BHK48.49 Sq.mts. ( 522 Sq.ft. )32
30 Booked93% Booked
93% Booked
3 BHK66.06 Sq.mts. ( 711 Sq.ft. )30
27 Booked90% Booked
90% Booked
78 total apartments / 73 apartments booked. 93% apartments booked.
Work Description in Building Saffron BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress70% done
70% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress72% done
72% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress42% done
42% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress31% done
31% Booked
Sanitary Fittings within the flats / premises
work-in-progress31% done
31% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress83% done
83% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress99% done
99% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress60% done
60% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Ravi Developments
for Project
Gaurav Saffron
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation