Project overview

Gami Eva is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700031192. Gami Eva is located at Plot No 86. This is a New being developed by Thalia And Gami Enterprises.

Gami Eva has 1 BHK, 2 BHK & Shop Apartments with carpet areas ranging from 109 to 448 Sq.ft. Carpet. The Project has total 32 of which 2 are currently available for sale.

Gami Eva is being developed on a total land area of 4843 Sq.ft. Gami Eva has 1 Wings / Towers Gami Eva

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Gami Eva
  • Location:
  • Plot No 86
  • Const. Stage:
    New
  • Possession:
    30 Jun 2023
Developer Details

  • Developer:
    Thalia And Gami Enterprises
  • Phone:
  • Address:
  • Real Tech Park
Project RERA Details
MAHA REARA No: P51700031192
Project Type Others
RERA Project Status New
Architect Edge Architects
Funding Bank AXIS BANK
Proposed Possession 30 Jun 2023
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 11 Oct 2021
Last Retrived 26 Jul 2025
Gami Eva QR Code
Gami Eva
MahaRERA - P51700031192
Apartment Details & Configuration
TypeArea
1 BHK41.5 Sq.mts. ( 447 Sq.ft. )
1 BHK41.58 Sq.mts. ( 448 Sq.ft. )
1 BHK30.46 Sq.mts. ( 328 Sq.ft. )
1 BHK35.85 Sq.mts. ( 386 Sq.ft. )
1 BHK37.68 Sq.mts. ( 406 Sq.ft. )
1 BHK39.8 Sq.mts. ( 428 Sq.ft. )
2 BHK40.06 Sq.mts. ( 431 Sq.ft. )
Shop10.11 Sq.mts. ( 109 Sq.ft. )
Shop11.38 Sq.mts. ( 122 Sq.ft. )
Shop11.43 Sq.mts. ( 123 Sq.ft. )
Shop20.98 Sq.mts. ( 226 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Gami Evalast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Electric Meter Room Will Be Provide
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting100% completed
95% Complete
As Per Nmmc Norms
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Chamber As Per Nmmc Norms
Solid Waste Management And Disposal
Line Is Provide
Storm Water Drains
Na
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
As Per Nmmc
Water Supply
As Per Nmmc Norms
Buildings / Wings in Gami Eva
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Gami Eva by Thalia And Gami Enterpriseslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

4843 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

32 apartments in total
Total
32
Booked
30
Available
2

Saleable Area Statistics (Sq. ft.)

11942 Total
Total
11942
Booked
11608
Available
335
Total 32 apartments in project. 30 apartments booked. 93% apartments booked.
Total 11942 Sq.ft. saleable area. 11608 saleable area booked.
97% area booked.

Gami Eva

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Gami EvaJun 202281010027
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK41.5 Sq.mts. ( 447 Sq.ft. )5
5 Booked100% Booked
100% Booked
1 BHK41.58 Sq.mts. ( 448 Sq.ft. )5
5 Booked100% Booked
100% Booked
1 BHK30.46 Sq.mts. ( 328 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK35.85 Sq.mts. ( 386 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK37.68 Sq.mts. ( 406 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK39.8 Sq.mts. ( 428 Sq.ft. )2
2 Booked100% Booked
100% Booked
2 BHK40.06 Sq.mts. ( 431 Sq.ft. )5
5 Booked100% Booked
100% Booked
Shop10.11 Sq.mts. ( 109 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop11.38 Sq.mts. ( 122 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop11.43 Sq.mts. ( 123 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop20.98 Sq.mts. ( 226 Sq.ft. )1
None Booked0% Booked
0% Booked
32 total apartments / 30 apartments booked. 93% apartments booked.
Work Description in Building Gami EvaCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Thalia And Gami Enterprises
for Project
Gami Eva
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation