Project overview

GAMI AVENUE is a MahaRERA Registered Project bearing MahaRERA Registration Number P52000013751. GAMI AVENUE is located at Plot No. C-7. This is a New being developed by GAMI INFRA DEVELOPERS.

GAMI AVENUE has FLAT TYPE 1, FLAT TYPE 2, FLAT TYPE 3 & SHOP Apartments with carpet areas ranging from 166 to 260 Sq.ft. Carpet. The Project has total 18 of which 3 are currently available for sale.

GAMI AVENUE is being developed on a total land area of 2691 Sq.ft. GAMI AVENUE has 1 Wings / Towers Gami Avenue

ProjectDeveloperLocationPossession
Project Details
  • Project:
    GAMI AVENUE
  • Location:
  • Plot No. C-7
  • Const. Stage:
    New
  • Possession:
    30 Sep 2019
Developer Details

  • Developer:
    GAMI INFRA DEVELOPERS
  • Phone:
  • Address:
  • Hari Govind Dham Chs
Project RERA Details
MAHA REARA No: P52000013751
Project Type Others
RERA Project Status New
Architect Atul Patel
Funding Bank ABHYUDAYA COOPERATIVE BANK LIMITED
Proposed Possession 30 Sep 2019
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 25 Oct 2017
Last Retrived 14 Feb 2026
GAMI AVENUE QR Code
GAMI AVENUE
MahaRERA - P52000013751
Apartment Details & Configuration
TypeArea
FLAT TYPE 116.737 Sq.mts. ( 180 Sq.ft. )
FLAT TYPE 217.347 Sq.mts. ( 187 Sq.ft. )
FLAT TYPE 324.12 Sq.mts. ( 260 Sq.ft. )
SHOP15.436 Sq.mts. ( 166 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of GAMI AVENUElast updated on 14 Feb 2026 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Electrical Meter Room Will Be Provided
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting100% completed
95% Complete
3 Nos Of Trees
Open Parking100% completed
95% Complete
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Chamber Lines Provided
Solid Waste Management And Disposal
Na
Storm Water Drains
Na
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Na
Water Supply100% completed
95% Complete
Provide Upto Site By Cidco
Buildings / Wings in GAMI AVENUE
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of GAMI AVENUE by GAMI INFRA DEVELOPERSlast updated on 14 Feb 2026 as per information obtained from MARA RERA.

2691 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

18 apartments in total
Total
18
Booked
15
Available
3

Saleable Area Statistics (Sq. ft.)

3705 Total
Total
3705
Booked
3085
Available
620
Total 18 apartments in project. 15 apartments booked. 83% apartments booked.
Total 3705 Sq.ft. saleable area. 3085 saleable area booked.
83% area booked.

Gami Avenue

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Gami AvenueSep 20195101050
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
FLAT TYPE 116.737 Sq.mts. ( 180 Sq.ft. )8
6 Booked75% Booked
75% Booked
FLAT TYPE 217.347 Sq.mts. ( 187 Sq.ft. )2
2 Booked100% Booked
100% Booked
FLAT TYPE 324.12 Sq.mts. ( 260 Sq.ft. )6
5 Booked83% Booked
83% Booked
SHOP15.436 Sq.mts. ( 166 Sq.ft. )2
2 Booked100% Booked
100% Booked
18 total apartments / 15 apartments booked. 83% apartments booked.
Work Description in Building Gami AvenueCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
GAMI INFRA DEVELOPERS
for Project
GAMI AVENUE
last updated on 14 Feb 2026 as per information obtained from MARA RERA.
Name Company Location Mobile Designation