Project overview

Eternal Avenue is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700006365. Eternal Avenue is located at S No 90 Hissa No 2 And 3. This is a Ongoing being developed by Magnum Life Spaces.

Eternal Avenue has 1 BHK & 1 RK Apartments with carpet areas ranging from 242 to 349 Sq.ft. Carpet. The Project has total 47 of which 31 are currently available for sale.

Eternal Avenue is being developed on a total land area of 18145 Sq.ft. Eternal Avenue has 1 Wings / Towers Eternal Avenue Wing C

ProjectDeveloperLocationPossession
Riddhi SiddhiShreeji & Innovative DevelopersPlot No 6 And 9, Survey No 105 - A, Hissa No 131-12-2018 00:00:00
Harishree Residency-1Harishree CreationsPlot No. 1 Survey No 129/2 P30-12-2021 00:00:00
Harishree Residency-2Harishree CreationsPlot No2 Survey No 129 Hissa No 2 P30-12-2021 00:00:00
Shubh NisargVardhaman And Vastu AssociatesS No 9 H No 5 6 720-12-2021 00:00:00
Vastu ShilpVastu HomesS No 105A Hissa No 4231-03-2018 00:00:00
Siddharth ApartmentRohan Gruh NirmanS No 40 And H No 331-03-2018 00:00:00
Sairaj Avenue Wing BVirendra Atmaram SalunkheS No 97B, Hissa No 5/3, Plot No 4431-05-2024 00:00:00
Shreeji MilestoneDeep Laxmi AssociatesSurvey No. 48, Plot No. 0130-06-2029 00:00:00
Pinnacle AdarshPinnacle EnterprisesSurvey No 5 Hiss No 4 Plot No 930-06-2025 00:00:00
Sai Raj ResidencyShriram Developers19 H .No.47, P No.731-12-2018 00:00:00
Aditya RoyalPrashant Aditya Shukla1408B30-06-2018 00:00:00
Nandraj Nagari Type ESwaraj DevelopersS No 58 Hissa No 2P S No 60Pplot 16 And 1431-05-2018 00:00:00
Om Shrinivas ApartmentShriniwas DevelopersSurvey No 9 Hissa No 4A Plot No 531-03-2018 00:00:00
Maruti AsthaMaruti HomesSurvey No 97B,Hissa No. 7, Plot No. 531-12-2017 00:00:00
Saurabh ArcadeM/S Krishna Builders & DevelopersS No 7A H No 4A Plot No 1 230-12-2021 00:00:00
Maruti MeadowsVasani EnterprisesNa, Thane, 42150330-12-2020 00:00:00
Vedant EnclaveSara EnterprisesS.No.51 H.No.2A/7 Plot No 1730-11-2020 00:00:00
Om Shiv Vatika A WingsOm Shiv DevelopersSr No 137 Hiss No B28-11-2021 00:00:00
Shivam Complex Wing D And EUmiya EnterprisesS No 105A H No 22P30-09-2018 00:00:00
Pranjee Garden City Phase -IiPranjee Properties Pvt. LtdPlot No 330-11-2018 00:00:00
Tharwani Ariana Phase IiAnil Hardasmal TharwaniSurvey No 133/1 Part And Survey 133/1A30-04-2018 00:00:00
Deep EnclaveDattaguru EnterprisesSurvey No. 42, Plot No. C-11 And C-11A30-06-2019 00:00:00
Sanveg Residency - Phase IOm Vastu HomesSurvey No 180 Hissa No 230-06-2021 00:00:00
Kohinoor CastlesKohinoor Castles140 4A/130-03-2021 00:00:00
Tulsi SignatureTulsi BuildconNear Cyndrella School31-12-2019 00:00:00
Manohar Vikas Shreeji Paraiso Phase - 2Deeplaxmi DevelopersS. No. 60, H.No.5 Pt,6 Pt, S. No.61,H. No.1 Part,S. No. 9130-03-2029 00:00:00
DhavalShreeji And Innovative DevelopersPlot No 10/ Survey No 105A /Hissa No 1Pt30-12-2022 00:00:00
Chintamani HeightsYash EnterprisesPlot No 4 Plot No 731-12-2019 00:00:00
Aawas DeepShree Krishna BuildconSurvey No. 16630-12-2022 00:00:00
Sai Kishan ApartmentSai Kishan ConstructionsSurvey No.17, Hissa No.14, Plot No. 231-07-2019 00:00:00
Eternal AvenueMagnum Life SpacesS No 90 Hissa No 2 And 331-03-2018 00:00:00
Tharwani Ariana Phase IiiAnil Hardasmal TharwaniSurvey No 133/1 Part And Survey 133/1A30-04-2023 00:00:00
Precious HarmonyM/S Soham ConstructionSurvey No 51 Hissa No 2 New Belavali Badlapur 42150331-03-2018 00:00:00
Shreeji HeightsShubh BuildconSurvey No 83 1 84 1 2 3 630-06-2022 00:00:00
Metro ImperialMetro Balaji DevelopersS No 2030-06-2021 00:00:00
Rathadia Co-Operative Housing Society LtdJ Square InfraSurvey No 90 H No 331-03-2019 00:00:00
Navjeevan Co-Op. Housing Society LtdAvishkar GroupSurvey No. 4231-12-2019 00:00:00
Hira Panna ResidencyHaro Om Sai Builders And Developers10A/5/431-12-2019 00:00:00
Shree PalacePushlata Subhash GhuleSurvey No 273 Hissa No 130-12-2021 00:00:00
Precious Harmony Phase IiM/S Soham ConstructionS No 50 H No 2, 4, 530-12-2022 00:00:00
Royal Wood ParkPrabhavati ConstructionsS.No.23, H.No.1 Pt30-06-2021 00:00:00
Alok GalaxyJuhi Developers30 Mtr Road13-10-2021 00:00:00
Omkar ApartmentsPinnacle LifespacesS No 1,H No 17 E, 5A30-03-2022 00:00:00
Krishna C And D WingNina BuildersGut.No.90/1, 91/1A30-12-2021 00:00:00
Sai Krupa ResidencySairaj DevelopersS.No.78 Plot No.1 H.No.2 P31-12-2019 00:00:00
Shubh Nirman Phase IGuru DevelopersBelavali, Thane, 42150330-12-2022 00:00:00
Badlapur ArcadeMahalaxmi Builders & DevelopersSurvey No 44 1 A 130-12-2023 00:00:00
Mansvi ApartmentRuhi EnterprisesS No 45 H No 17 Plot No 7 Belavali West Badlapur30-03-2023 00:00:00
Manohar Vikas Shreeji Paraiso Phase 1Deeplaxmi DevelopersS No 60/5, 60/6, 61/130-05-2022 00:00:00
Mahalaxmi ParadiseShree Mahalaxmi Builders And Developers133, Hissa No. 1A131-07-2019 00:00:00
Rattan GalaxyRattan Properties And Projects Private LimitedSurvey No 97/B Hissa No 6 And 7 Plot No 1 Belavali Badlapur30-04-2018 00:00:00
Amber ArcadeMaitri DevelopersSurvey No 51 Hissa No 3P31-12-2018 00:00:00
Datar HeightsSaleem Abdul ShaikhS.No 7A31-10-2019 00:00:00
Ravi DarshanRavi DevelopersS.N0-105A25-05-2018 00:00:00
Sara HeightsShete's ConstructionG No 47, Hissa No. 19 And 2030-12-2022 00:00:00
Radha ResidencyAkshay DevelopersSurvey No 20 Plot No 230-06-2019 00:00:00
Shrushti PrarambhShrushti DevelopersSurvey No.5 Hissa No.3/330-12-2022 00:00:00
Paradise Park - Phase 1M/S Vakratund Enterprises421503, Thane, Belavli30-03-2024 00:00:00
SundaramM/S. Purab AssociatesPart Portion Of S No 45 H No 2Pt Plot No 1 2 3 And Part Portion Of S No 45 H No 2 Pt Plot No 431-01-2020 00:00:00
Swaraswati HeightsShree Samarth EnterprisesSurvey No 79, Hissa No. 1,2 & 330-09-2028 00:00:00
Tharwanis Meghna Montana Phase - 3Tharwani Constructions Pvt LtdS.No 135/3A, 138/1D, 138/2, 134/231-12-2028 00:00:00
Vighnaharta Co. Op. Housing Society LtdShree Krushna AssociatesSurvey No. 89, Hissa No. 231-12-2029 00:00:00
Shiv SarovarMahesh Bharat Divnale95 /1/ V01-05-2025 00:00:00
Krishna KutirShubh Krishna Realtors42150330-06-2025 00:00:00
Badlapur LandmarkRavindra PatilBadlapur West, Thane31-12-2026 00:00:00
Project Details
  • Project:
    Eternal Avenue
  • Location:
  • S No 90 Hissa No 2 And 3
  • Const. Stage:
    Ongoing
  • Possession:
    31 Mar 2018
Developer Details

  • Developer:
    Magnum Life Spaces
  • Phone:
  • Address:
  • Laxmi Chs
Project RERA Details
MAHA REARA No: P51700006365
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Raj Associates Architect & Enginners
Funding Bank DOMBIVLI NAGARI SAHAKARI BANK LIMITED
Proposed Possession 31 Mar 2018
Revised Possession 31 Mar 2018
Extended Possession
Litigations No Litigations
Last Modified 14 Aug 2017
Last Retrived 26 Jul 2025
Eternal Avenue QR Code
Eternal Avenue
MahaRERA - P51700006365
Apartment Details & Configuration
TypeArea
1 BHK26.88 Sq.mts. ( 289 Sq.ft. )
1 BHK28.56 Sq.mts. ( 307 Sq.ft. )
1 BHK28.69 Sq.mts. ( 309 Sq.ft. )
1 BHK29.06 Sq.mts. ( 313 Sq.ft. )
1 BHK29.69 Sq.mts. ( 320 Sq.ft. )
1 BHK29.72 Sq.mts. ( 320 Sq.ft. )
1 BHK32.44 Sq.mts. ( 349 Sq.ft. )
1 RK22.52 Sq.mts. ( 242 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Eternal Avenuelast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Os Area 309.26 Sq. Mtr Work Yet Not Started
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Meter Room Work Yet Not Started
Energy management
Solar Panel Of Wing C Work Yet Not Started
Fire Protection And Fire Safety Requirements70% completed
70% Complete
Partly Work Remaining
Landscaping & Tree Planting100% completed
95% Complete
Tree Planting Work Has Been Completed
Open Parking50% completed
50% Complete
As Per Plan Partly Work Completed
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Drainage Lines Has Beenconnected To Munci.Sew.Line
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
Work Has Been Completed
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting70% completed
70% Complete
Rain Water Harvesting Partly Work Has Been Complet
Water Supply
Mjp Will Provided Water Connection After Oc
Buildings / Wings in Eternal Avenue
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Eternal Avenue by Magnum Life Spaceslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

18145 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

47 apartments in total
Total
47
Booked
16
Available
31

Saleable Area Statistics (Sq. ft.)

14784 Total
Total
14784
Booked
4907
Available
9877
Total 47 apartments in project. 16 apartments booked. 34% apartments booked.
Total 14784 Sq.ft. saleable area. 4907 saleable area booked.
33% area booked.

Eternal Avenue Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Eternal Avenue Wing CMar 201881020102
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.88 Sq.mts. ( 289 Sq.ft. )5
1 Booked20% Booked
20% Booked
1 BHK28.56 Sq.mts. ( 307 Sq.ft. )15
8 Booked53% Booked
53% Booked
1 BHK28.69 Sq.mts. ( 309 Sq.ft. )4
1 Booked25% Booked
25% Booked
1 BHK29.06 Sq.mts. ( 313 Sq.ft. )3
3 Booked100% Booked
100% Booked
1 BHK29.69 Sq.mts. ( 320 Sq.ft. )8
1 BHK29.72 Sq.mts. ( 320 Sq.ft. )3
None Booked0% Booked
0% Booked
1 BHK32.44 Sq.mts. ( 349 Sq.ft. )8
1 RK22.52 Sq.mts. ( 242 Sq.ft. )1
1 Booked100% Booked
100% Booked
47 total apartments / 16 apartments booked. 34% apartments booked.
Work Description in Building Eternal Avenue Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress89% done
89% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Magnum Life Spaces
for Project
Eternal Avenue
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation