Project overview

Esquire is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800005229. Esquire is located at Xr7iteovzx9ocidlnzg8vhr0nf4hz+Gsflazpff2lkhzit20akwojy9lhbucyxzr. This is a Ongoing being developed by Oberoi Realty Limited.

Esquire has 3 BHK Superior Zone 1, 3 BHK Superior Zone 2, 3 BHK Supreme Zone 1 & 3 BHK Supreme Zone 2 Apartments with carpet areas ranging from 1367 to 1496 Sq.ft. Carpet. The Project has total 882 of which 273 are currently available for sale.

Esquire is being developed on a total land area of 35594 Sq.ft. Esquire has 3 Wings / Towers Tower A,Tower B,Tower C

ProjectDeveloperLocationPossession
Garnet PaladiumGarnet Construction Limited0A++Bme+8Ulurzz45gg20q==31-12-2018 00:00:00
GulmoharUdyam Enterprises400063, Mumbai Suburban30-06-2022 00:00:00
Borivli Vasundhara Chs Ltd.Shree Sai Shraddha DevelopersE/Dq4ez6stsoqjmmcambra==04-01-2020 00:00:00
Om TrimurtiJe And Vee InfrastructureEiqo/Lgxhnbzsbm+Xlpeua==30-12-2023 00:00:00
Satellite EleganceNewone Constructions Private LimitedS0mshos6slqclmxjliwasyir/Wa5khi+Vlzhmmtm3k807ishz2qcccjtniccrblh30-12-2024 00:00:00
Chaurang Sunshine Chaurang BuildersWc2rdd6uh0qtrexq/Gfe/A==31-05-2018 00:00:00
Prayag HeightsJenvee Infrastructure Pvt LtdMh9rolkf/Rxshqmbcwrnjq==30-12-2023 00:00:00
Leela SterlingVora Estate Developers400063, Mumbai Suburban31-12-2020 00:00:00
Bhawani ConstructionBhawani ConstructionsD3j57s8emlfpnxpl6keqrnunpz5hs1wdsq9h7unk9gbwlbwanimsl+Wondoehcqz30-12-2023 00:00:00
Sheth Blue IvySheth Developers Private LimitedInvlzvihfuigmcs/Qr+Nphytihkrvvqcaov30rzvlztrmicm5l0smjzmi56ys6ypjeqyvimurkk9omcvczwk2q==30-06-2023 00:00:00
Jyoti SukritiJyoti Builders9Oxykhzdhavn8om+M15jirvv9iz2xz3/0Wffowm4vce/Febi80z3pgjrb19s3gqxczlwgao+8Cxaieypjhr0pzioizprxj1vxt7c9b8cwn0=30-06-2021 00:00:00
Western WoodsKarmvir Mumbai Housing Private LimitedLrj+F2kjayvoaqgk4a7/Xw==31-12-2018 00:00:00
Origin ClaremontMpire Reality Limited2Kttcjg7rzdehrgcydedm64twrjxtnhf0pi9rtpn3sgra07a3eboinfgzpvikldr31-12-2030 00:00:00
Sejal SquareAlchemi Developers Private LimitedCujkzgeqluw76mybcfzlhcosrbjns0pmy13iiphy0od8ryzzjclsyzh+Jjqagqjsi6v1k5mzdfx2/Mdjwlvxwu/Q67pil7jisaob21efbbekja+Gloovlfzxmje2mq7gt3o2mvaul5exm1fyoocvzg==31-12-2029 00:00:00
Sayba Signature SpacesStar SapphireB4aovs5ewee7d35b1rxgjw==30-06-2027 00:00:00
Crescent Western Trade Center - GoregaonBp Infra Realtors LlpC7dpvxe7zbeire4fqzruxw==31-12-2027 00:00:00
Serenity DecksEternity And Aakar RealtyQygcgt9q80yf9nilxherla==31-07-2028 00:00:00
MeluhaSaptrishi Urban Space Private LimitedDgckct/O2140srqn667agw==31-12-2030 00:00:00
Kabra Tiara - Redevelopment Of Dindoshi Darshan ChslKabra And Associates3N+Pdxdczojy5ypaz61qskt2dsedxjjxtknzd/Xnfh8=31-12-2027 00:00:00
HorizonJaycee Homes Private Limited400063, Mumbai Suburban31-03-2018 00:00:00
Hiramani EnclaveDamji Hirji & CompanyTsb0zzug7emsgsgclxu8hnpcm88ebafockwoqahqs/O=01-06-2019 00:00:00
Conwood Astoria Tower AConwood Realty Private Limited7Xqfqpf9hicsv1vcbmtlr5ujuchqpo8dad2ltu5i9gqrjedzk3n1b+Yxexllpdq3hsxfpwmotzqnxqetd1vvvw==31-12-2018 00:00:00
Rashi TowerRashi DevelopersOpr3v3yvfo0dqx38xnlkm40u9ft2shpydnprtuxk1xu=30-12-2023 00:00:00
Redevelopment Of Lamplight ChslShree Mahavir Estates0Jtqcl24amcoeiaqtcnziczewcecssjzd3eei3pjr6xqdhv3gg4cvyjrqpdihwtw31-12-2019 00:00:00
EsquireOberoi Realty LimitedXr7iteovzx9ocidlnzg8vhr0nf4hz+Gsflazpff2lkhzit20akwojy9lhbucyxzr30-06-2018 00:00:00
Astoria Tower BConwood Realty Private LimitedAdlqipmx0ipn+2Mmjmytad9tg+Xoahc/Vpeucriicvfgb218j3hppo0wr7t4zonk31-12-2020 00:00:00
Atlanta Estate ExtensionAtul Raj Builders Pvt Ltd400063, Mumbai City30-06-2011 00:00:00
Happy Home EnclaveJd & Fc Ventures LlpT8+7Okzlniyrbmz/Oazlog==31-12-2026 00:00:00
Elysian Tower C, D, EOberoi Realty LimitedXeb34arhi8ffb/Hyxjpybh5cje5z898w0gqljvkz7lfz4nzcx+Xee/Pisxkaau5ocixnwigvpvz9huqv8txq5wkkschg7nuycclbtm8opngz3yashrxchhf/Jvvsoz+Mjbrf5kr+K7blvzy1glaadidvxmij+V6lp05xgr3jypofump1ofn2wmint6j4vawn3mvjieejyynneku16j0wynfsazizfon0bh7jg5iivxtcg7mtcon3msosgxvkypiiwosd/V9+B/3Snmysjs4zjwjcoaxdo1/K5afymnv8j6kfvjayizdxlly2v5lucqun31-10-2031 00:00:00
Goregaon Manorath Chs LtdK Anand Infra1Imropker7/Eyktfi96pkblowwftueyho9g06n+Cgdwg//Hwywog4hrc2wtpquaj31-03-2026 00:00:00
Jp DecksJ. P. Infra (Mumbai) Private LimitedOo69at23d+1W5dhnkpuaoj1vy4+Tjdilpylezuzpwh/Wq6splaqj5cq8wedkfkkvqlztluufuhql/Zczhpytnwhfgh6obk58emat5pjtbcffofmoiqpeh+Zvh1cckkc8nuh/1Bf32ckk2cse74pa4g==31-12-2019 00:00:00
Saan SymphonySantosh Raosaheb NavleSx2hvy0/Wwlshh6+Ntgkew==31-05-2027 00:00:00
Sheth Cnergy MaladSheth Developers Private LimitedVnipze/Xs59vjm6k7azlm8w5bgzwcfqbo3e1xwihuiwcustxvokk8fo10of+Zxir30-06-2023 00:00:00
Elysian Tower AOberoi Realty LimitedKg0yyudtbi343j0uuvgadivcddrmuzslv2o5abkmnhm=30-06-2027 00:00:00
Elysian Tower BOberoi Realty LimitedKg0yyudtbi343j0uuvgadivcddrmuzslv2o5abkmnhm=30-06-2027 00:00:00
Project Details
  • Project:
    Esquire
  • Location:
  • Xr7iteovzx9ocidlnzg8vhr0nf4hz+Gsflazpff2lkhzit20akwojy9lhbucyxzr
  • Const. Stage:
    Ongoing
  • Possession:
    30 Jun 2018
Developer Details

  • Developer:
    Oberoi Realty Limited
  • Phone:
  • Address:
  • Commerz
Project RERA Details
MAHA REARA No: P51800005229
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Architect Shashank Kokil
Funding Bank AXIS BANK
Proposed Possession 30 Jun 2018
Revised Possession 30 Jun 2018
Extended Possession
Litigations No Litigations
Last Modified 11 Aug 2017
Last Retrived 13 Feb 2026
Esquire QR Code
Esquire
MahaRERA - P51800005229
Apartment Details & Configuration
TypeArea
3 BHK Superior Zone 1127.01 Sq.mts. ( 1367 Sq.ft. )
3 BHK Superior Zone 2138.57 Sq.mts. ( 1492 Sq.ft. )
4 BHK Royale Zone 1190.77 Sq.mts. ( 2053 Sq.ft. )
4 BHK Royale Zone 2192.11 Sq.mts. ( 2068 Sq.ft. )
3 BHK Supreme Zone 1127.43 Sq.mts. ( 1372 Sq.ft. )
3 BHK Supreme Zone 2138.99 Sq.mts. ( 1496 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Esquirelast updated on 13 Feb 2026 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
To Be Provided As Per Provisions Of Dcr
Community Buildings100% completed
95% Complete
Clubhouse Proposed To Be Provided
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Will Be Provided As Necessary
Energy management100% completed
95% Complete
Will Be Provided
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Will Be Provided
Landscaping & Tree Planting100% completed
95% Complete
Will Be Provided
Open Parking
Na
Prop Public Parking to be handed over to MCGM at any location in LargerProperty incl under RE Proj
To Be Handed Over To Mcgm
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Will Be Provided
Solid Waste Management And Disposal100% completed
95% Complete
Will Be Provided
Storm Water Drains100% completed
95% Complete
Will Be Provided
Street Lighting100% completed
95% Complete
Will Be Provided
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Will Be Provided
Water Conservation, Rain water Harvesting100% completed
95% Complete
Will Be Provided
Water Supply100% completed
95% Complete
Will Be Provided
Buildings / Wings in Esquire
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Esquire by Oberoi Realty Limitedlast updated on 13 Feb 2026 as per information obtained from MARA RERA.

35594 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

882 apartments in total
Total
882
Booked
609
Available
273

Saleable Area Statistics (Sq. ft.)

1304906 Total
Total
1304906
Booked
907047
Available
397859
Total 882 apartments in project. 609 apartments booked. 69% apartments booked.
Total 1304906 Sq.ft. saleable area. 907047 saleable area booked.
70% area booked.

Tower A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower AJun 20185913350925
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK Superior Zone 1127.01 Sq.mts. ( 1367 Sq.ft. )210
171 Booked81% Booked
81% Booked
3 BHK Superior Zone 2138.57 Sq.mts. ( 1492 Sq.ft. )86
296 total apartments / 188 apartments booked. 63% apartments booked.
Work Description in Building Tower ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower BJun 20185913260919
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK Superior Zone 1127.01 Sq.mts. ( 1367 Sq.ft. )136
106 Booked77% Booked
77% Booked
3 BHK Superior Zone 2138.57 Sq.mts. ( 1492 Sq.ft. )56
4 BHK Royale Zone 1190.77 Sq.mts. ( 2053 Sq.ft. )82
79 Booked96% Booked
96% Booked
4 BHK Royale Zone 2192.11 Sq.mts. ( 2068 Sq.ft. )20
20 Booked100% Booked
100% Booked
294 total apartments / 209 apartments booked. 71% apartments booked.
Work Description in Building Tower BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tower C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower CJun 20185913160912
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK Superior Zone 1127.01 Sq.mts. ( 1367 Sq.ft. )139
119 Booked85% Booked
85% Booked
3 BHK Superior Zone 2138.57 Sq.mts. ( 1492 Sq.ft. )58
3 BHK Supreme Zone 1127.43 Sq.mts. ( 1372 Sq.ft. )67
67 Booked100% Booked
100% Booked
3 BHK Supreme Zone 2138.99 Sq.mts. ( 1496 Sq.ft. )28
17 Booked60% Booked
60% Booked
292 total apartments / 212 apartments booked. 72% apartments booked.
Work Description in Building Tower CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Oberoi Realty Limited
for Project
Esquire
last updated on 13 Feb 2026 as per information obtained from MARA RERA.
Name Company Location Mobile Designation