Project overview

Durahomes Builders And Developers Pvt Ltd is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700012518. Durahomes Builders And Developers Pvt Ltd is located at 19,20,21,22,23,81/2,81/5,82/3. This is a Ongoing being developed by Arshad Ahmed Siddiqui.

Durahomes Builders And Developers Pvt Ltd has Industrial Unit Apartments with carpet areas ranging from 598608 to 598608 Sq.ft. Carpet. The Project has total 43 of which 43 are currently available for sale.

Durahomes Builders And Developers Pvt Ltd is being developed on a total land area of 1363452 Sq.ft. out of which 144657 Sq.ft. i.e 11% is reserved for recreational purposes. Durahomes Builders And Developers Pvt Ltd has 5 Wings / Towers Building E,Building F,Building G,Building Kl 1,Building Km 1

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Durahomes Builders And Developers Pvt Ltd
  • Location:
  • 19,20,21,22,23,81/2,81/5,82/3
  • Const. Stage:
    Ongoing
  • Possession:
    31 Jul 2028
Developer Details

  • Developer:
    Arshad Ahmed Siddiqui
  • Phone:
  • Address:
  • Embassey Centre
Project RERA Details
MAHA REARA No: P51700012518
Project Type Industrial
RERA Project Status Ongoing
Architect Kailash B Marathe
Funding Bank SOUTH INDIAN BANK
Proposed Possession 31 Jul 2028
Revised Possession 31 Jul 2028
Extended Possession
Litigations No Litigations
Last Modified 01 Sep 2017
Last Retrived 26 Jul 2025
Durahomes Builders And Developers Pvt Ltd QR Code
Durahomes Builders And Developers Pvt Ltd
MahaRERA - P51700012518
Apartment Details & Configuration
TypeArea
Industrial unit6689.75 Sq.mts. ( 72008 Sq.ft. )
Industrial unit26685.84 Sq.mts. ( 287246 Sq.ft. )
Industrial unit2207.51 Sq.mts. ( 23762 Sq.ft. )
Industrial Unit55612 Sq.mts. ( 598608 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Durahomes Builders And Developers Pvt Ltdlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Pending
Community Buildings
Pending
Electrical Meter Room, Sub-Station, Receiving Station
Na
Energy management
Na
Fire Protection And Fire Safety Requirements
Pending
Landscaping & Tree Planting
Pending
Open Parking
Pending
Sewerage (Chamber, Lines, Septic Tank , STP)
Pending
Solid Waste Management And Disposal
Na
Storm Water Drains
Pending
Street Lighting
Pending
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Pending
Water Supply
Pending
Buildings / Wings in Durahomes Builders And Developers Pvt Ltd
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Durahomes Builders And Developers Pvt Ltd by Arshad Ahmed Siddiquilast updated on 26 Jul 2025 as per information obtained from MARA RERA.

1363453 Sq. ft.

Project Area

144657 Sq. ft.

Recreational Open Space

Total 5

Wings / Towers in Project

Apartments Statistics

43 apartments in total
Total
43
Booked
0
Available
43

Saleable Area Statistics (Sq. ft.)

13813430 Total
Total
13813430
Booked
0
Available
13813430
Total 43 apartments in project. 0 apartments booked. 0% apartments booked.
Total 13813430 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.

Building E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building EJan 19000000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Industrial unit6689.75 Sq.mts. ( 72008 Sq.ft. )3
None Booked0% Booked
0% Booked
3 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building ECompletion
Basement (if any)
Excavation
work-in-progress80% done
80% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress60% done
60% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
work-in-progress60% done
60% Booked

Building F

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building FJan 190021000800
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Industrial unit26685.84 Sq.mts. ( 287246 Sq.ft. )12
None Booked0% Booked
0% Booked
12 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building FCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress70% done
70% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress60% done
60% Booked
Stilt Floor

Building G

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building GJan 190021000800
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Industrial unit26685.84 Sq.mts. ( 287246 Sq.ft. )12
None Booked0% Booked
0% Booked
12 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building GCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress70% done
70% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress90% done
90% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress50% done
50% Booked
Stilt Floor

Building Kl 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building Kl 1Jan 190021000200
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Industrial unit2207.51 Sq.mts. ( 23762 Sq.ft. )5
None Booked0% Booked
0% Booked
5 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building Kl 1Completion
Basement (if any)
work-in-progress90% done
90% Booked
Excavation
work-in-progress90% done
90% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress50% done
50% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress90% done
90% Booked
Plinth
work-in-progress90% done
90% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress50% done
50% Booked
Slabs of Super Structure
work-in-progress90% done
90% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress99% done
99% Booked
Stilt Floor

Building Km 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building Km 1Jan 190021000400
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Industrial Unit55612 Sq.mts. ( 598608 Sq.ft. )11
None Booked0% Booked
0% Booked
11 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building Km 1Completion
Basement (if any)
work-in-progress80% done
80% Booked
Excavation
work-in-progress80% done
80% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress80% done
80% Booked
Plinth
work-in-progress80% done
80% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Channel Partners
Channel Partners Registered by Developer
Arshad Ahmed Siddiqui
for Project
Durahomes Builders And Developers Pvt Ltd
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation