Project overview

Dosti Eastern Bay - Phase 1 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51900025142. Dosti Eastern Bay - Phase 1 is located at 2A116 Of Salt Pan Division And 4356 Of Matunga Division. This is a New being developed by Dosti Realty Ltd.

Dosti Eastern Bay - Phase 1 has 1RK & 2 BHK Apartments with carpet areas ranging from 246 to 673 Sq.ft. Carpet. The Project has total 422 of which 6 are currently available for sale.

Dosti Eastern Bay - Phase 1 is being developed on a total land area of 11711 Sq.ft. Dosti Eastern Bay - Phase 1 has 2 Wings / Towers Wing A,Wing B

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Dosti Eastern Bay - Phase 1
  • Location:
  • 2A116 Of Salt Pan Division And 4356 Of Matunga Division
  • Const. Stage:
    New
  • Possession:
    30 Mar 2028
Developer Details

  • Developer:
    Dosti Realty Ltd
  • Phone:
  • Address:
  • Lawrence And Mayo House
Project RERA Details
MAHA REARA No: P51900025142
Project Type Residential / Group Housing
RERA Project Status New
Funding Bank HDFC BANK
Proposed Possession 30 Mar 2028
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 13 May 2024
Last Retrived 26 Jul 2025
Dosti Eastern Bay - Phase 1 QR Code
Dosti Eastern Bay - Phase 1
MahaRERA - P51900025142
Apartment Details & Configuration
TypeArea
1RK36.77 Sq.mts. ( 396 Sq.ft. )
2 BHK61.49 Sq.mts. ( 662 Sq.ft. )
3 BHK87.31 Sq.mts. ( 940 Sq.ft. )
3 BHK88.01 Sq.mts. ( 947 Sq.ft. )
3 BHK94.26 Sq.mts. ( 1015 Sq.ft. )
1RK22.82 Sq.mts. ( 246 Sq.ft. )
2 BHK50.61 Sq.mts. ( 545 Sq.ft. )
2 BHK61.7 Sq.mts. ( 664 Sq.ft. )
2 BHK61.75 Sq.mts. ( 665 Sq.ft. )
2 BHK62.51 Sq.mts. ( 673 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Dosti Eastern Bay - Phase 1last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space80% completed
80% Complete
Provision Made In Layout
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
No Meter Room And No Receiving Station
Energy management
Proposed Solar Panels At Terrace Level
Fire Protection And Fire Safety Requirements100% completed
95% Complete
As Per Cfo Noc
INDOOR SQUASH COURT TABLE TENNIS CAROM CHESS BANQUET HALL WITH OUTDOOR DINNING SPA GYM
Common Amenities To Be Shared Across All Phases
Landscaping & Tree Planting85% completed
85% Complete
Provision Made In Layout
Open Parking
Provision Made In Layout
OUTDOOR BOX CRICKET TENNIS COURT FOOTBALL PITCH
Common Amenities To Be Shared Across All Phases
OUTDOOR CHESS LAWN FITNESS AND AEROBICS DECK LAP POOL WITH DECK CHILDREN POOL WITH DECK
Common Amenities To Be Shared Across All Phases
OUTDOOR CHILDREN PLAY AREA SENIOR CITIZEN AREA JOGGING TRACK MULTIPURPOSE LAWN SUNNING LAWN
Common Amenities To Be Shared Across All Phases
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Provision Made In Layout
Solid Waste Management And Disposal100% completed
95% Complete
Provision Made For Owc
Storm Water Drains98% completed
98% Complete
Provision Made In Layout
Street Lighting
Provision Made In Layout
TODDLERS POOL WITH DECK BBQ GARDEN WITH LOOKOUT DECK OPEN AIR JACUZZI
Common Amenities To Be Shared Across All Phases
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Provision Made For Stp
Water Conservation, Rain water Harvesting97% completed
97% Complete
Provision Made In Layout
Water Supply
From Mcgm
Buildings / Wings in Dosti Eastern Bay - Phase 1
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Dosti Eastern Bay - Phase 1 by Dosti Realty Ltdlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

11711 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

422 apartments in total
Total
422
Booked
416
Available
6

Saleable Area Statistics (Sq. ft.)

310269 Total
Total
310269
Booked
306270
Available
3999
Total 422 apartments in project. 416 apartments booked. 98% apartments booked.
Total 310269 Sq.ft. saleable area. 306270 saleable area booked.
99% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing ASep 202750101417324
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1RK36.77 Sq.mts. ( 396 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK61.49 Sq.mts. ( 662 Sq.ft. )37
37 Booked100% Booked
100% Booked
3 BHK87.31 Sq.mts. ( 940 Sq.ft. )44
42 Booked95% Booked
95% Booked
3 BHK88.01 Sq.mts. ( 947 Sq.ft. )44
44 Booked100% Booked
100% Booked
3 BHK94.26 Sq.mts. ( 1015 Sq.ft. )44
44 Booked100% Booked
100% Booked
170 total apartments / 168 apartments booked. 98% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress99% done
99% Booked
Sanitary Fittings within the flats / premises
work-in-progress99% done
99% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BSep 202750131414268
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1RK22.82 Sq.mts. ( 246 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK50.61 Sq.mts. ( 545 Sq.ft. )81
80 Booked98% Booked
98% Booked
2 BHK61.7 Sq.mts. ( 664 Sq.ft. )38
38 Booked100% Booked
100% Booked
2 BHK61.75 Sq.mts. ( 665 Sq.ft. )88
86 Booked97% Booked
97% Booked
2 BHK62.51 Sq.mts. ( 673 Sq.ft. )44
44 Booked100% Booked
100% Booked
252 total apartments / 248 apartments booked. 98% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress99% done
99% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress90% done
90% Booked
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Dosti Realty Ltd
for Project
Dosti Eastern Bay - Phase 1
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation