Project overview

Dosti Desire-Dosti Joy is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700008886. Dosti Desire-Dosti Joy is located at 87 17C Part. This is a Ongoing being developed by D. D. Associates.

Dosti Desire-Dosti Joy has 1 BHK Apartments with carpet areas ranging from 290 to 290 Sq.ft. Carpet. The Project has total 168 of which 2 are currently available for sale.

Dosti Desire-Dosti Joy is being developed on a total land area of 4962 Sq.ft. Dosti Desire-Dosti Joy has 2 Wings / Towers Dosti Joy A,Dosti Joy B

ProjectDeveloperLocationPossession
EagletonRoma Builders Private Limited99/230-12-2022 00:00:00
HamptonRoma Builders Private Limited99/230-12-2022 00:00:00
BarringtonRoma Builders Private Limited99/2 Pt30-12-2022 00:00:00
CliftonRoma Builders Private Limited99/2 Pt30-12-2022 00:00:00
PrestonRoma Builders Private Limited99/2 Pt30-12-2022 00:00:00
WillowcrestRoma Builders Private Limited99/2 Pt30-12-2022 00:00:00
Vihang Plaza - A CommecialVihang Enterprises91/1/1A,2A,102/1,2B,2C,3B,103/1,2,3A,4,5B/2,104/7B,7C,8B,11/B,109/29B,30B30-12-2026 00:00:00
Sai SapphireDkm Realtors112/1/1,112/2/231-03-2018 00:00:00
One Park Avenue - Avenue 1Purva Oak Private LimitedS No 114/4 115/230-12-2023 00:00:00
Vihang WoodsVihang Enterprises91/1/1A,2A,102/1,2B,2C,3B,103/1,2,3A,4,5B/2,104/7B,7C,8B,11B, 109/29B,30/B30-12-2026 00:00:00
Platinum HeritageDarshan Sagar Developers136/1, 137/6, 137/1131-05-2018 00:00:00
UniqueVs DevelopersSurvey No 110/631-01-2019 00:00:00
FairwayRoma Builders Private Limited99/2 Pt30-12-2022 00:00:00
CloverdaleRoma Builders Private Limited99/2 Pt30-12-2022 00:00:00
D4 IrisNeelkanth Mansions And Infrastructure Pvt. Ltd. 318/1D Pt30-09-2020 00:00:00
DaffodilShree Tirupati Greenfield Developers1/1C, 1/1D, 1/1E, 1/1F, 1/1G30-12-2026 00:00:00
Shiv Shankar ResidencySai Gurukrupa Construction & Developers162/5A 162/5B31-12-2017 00:00:00
Dosti Desire-Dosti PearlD. D. Associates87-17C Part And 96-4C Part28-02-2021 00:00:00
Project Details
  • Project:
    Dosti Desire-Dosti Joy
  • Location:
  • 87 17C Part
  • Const. Stage:
    Ongoing
  • Possession:
    31 Jan 2020
Developer Details

  • Developer:
    D. D. Associates
  • Phone:
  • Address:
  • Lawrence & Mayo Hosue
Project RERA Details
MAHA REARA No: P51700008886
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Archetype Consultants I Pvt Ltd
Funding Bank HDFC BANK
Proposed Possession 31 Jan 2020
Revised Possession 31 Jan 2020
Extended Possession
Litigations No Litigations
Last Modified 19 Aug 2017
Last Retrived 26 Jul 2025
Dosti Desire-Dosti Joy QR Code
Dosti Desire-Dosti Joy
MahaRERA - P51700008886
Apartment Details & Configuration
TypeArea
1 BHK25.92 Sq.mts. ( 279 Sq.ft. )
1 BHK26.62 Sq.mts. ( 287 Sq.ft. )
1 BHK26.97 Sq.mts. ( 290 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Dosti Desire-Dosti Joylast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Layout Amenity
Community Buildings100% completed
95% Complete
Proposed Gymnasium At Stilt Level
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Meter Room Below Bldg Sub Station For Layout
Energy management100% completed
95% Complete
Proposed Solar Panels At Terrace Level
Fire Protection And Fire Safety Requirements100% completed
95% Complete
As Per Cfo Requirements
Landscaping & Tree Planting100% completed
95% Complete
Proposed As Layout Amenity
Open Parking
Will Be Provided
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Proposed As Layout Amenity
Solid Waste Management And Disposal100% completed
95% Complete
Owc Proposed For Layout
Storm Water Drains100% completed
95% Complete
Proposed As Layout Amenity
Street Lighting100% completed
95% Complete
Provision Made In Layout
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Stp Proposed For Layout
Water Conservation, Rain water Harvesting100% completed
95% Complete
Proposed For Layout
Water Supply100% completed
95% Complete
By Thane Municipal Corporation
Buildings / Wings in Dosti Desire-Dosti Joy
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Dosti Desire-Dosti Joy by D. D. Associateslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

4962 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

168 apartments in total
Total
168
Booked
166
Available
2

Saleable Area Statistics (Sq. ft.)

48153 Total
Total
48153
Booked
47588
Available
566
Total 168 apartments in project. 166 apartments booked. 98% apartments booked.
Total 48153 Sq.ft. saleable area. 47588 saleable area booked.
99% area booked.

Dosti Joy A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Dosti Joy AJan 2020181010170
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK25.92 Sq.mts. ( 279 Sq.ft. )49
48 Booked97% Booked
97% Booked
1 BHK26.62 Sq.mts. ( 287 Sq.ft. )17
16 Booked94% Booked
94% Booked
66 total apartments / 64 apartments booked. 96% apartments booked.
Work Description in Building Dosti Joy ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Dosti Joy B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Dosti Joy BJan 2020191010260
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.97 Sq.mts. ( 290 Sq.ft. )102
102 Booked100% Booked
100% Booked
102 total apartments / 102 apartments booked. 100% apartments booked.
Work Description in Building Dosti Joy BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
D. D. Associates
for Project
Dosti Desire-Dosti Joy
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation