Dharmavihar C Wing is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700019748. Dharmavihar C Wing is located at 421302, Bhiwandi, Thane. This is a New Project being developed by Mky Infrastructure.
Dharmavihar C Wing has 1 BHK & 2 BHK Apartments with carpet areas ranging from 468 to 655 Sq.ft. Carpet. The Project has total 134 of which 105 are currently available for sale.
Dharmavihar C Wing is being developed on a total land area of 86193 Sq.ft. out of which 16774 Sq.ft. i.e 19% is reserved for recreational purposes. Dharmavihar C Wing has 1 Wings / Towers Dharma Vihar C Wing
| Project | Developer | Location | Possession |
-
Project:
Dharmavihar C Wing
-
Location:
-
421302, Bhiwandi, Thane
-
Const. Stage:
New Project
-
Possession:
30 Dec 2025
-
Developer:
Mky Infrastructure
-
Phone:
-
Address:
-
Survey No 108/4, Mky Infrastructure, Kamatghar, Kamatghar, Bhiwandhi, 421302
| MAHA REARA No: |
P51700019748 |
| Project Type |
Residential |
| RERA Project Status |
New Project |
| Funding Bank |
KOTAK MAHINDRA BANK |
| Proposed Possession |
30 Dec 2025 |
| Revised Possession |
|
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
09 Dec 2022 |
| Last Retrived |
28 Jul 2025 |
Dharmavihar C Wing QR Code
Dharmavihar C Wing
MahaRERA - P51700019748
| Type | Area |
| 1 BHK | 43.48 Sq.mts. ( 468 Sq.ft. ) |
| 1 BHK | 44.41 Sq.mts. ( 478 Sq.ft. ) |
| 1 BHK | 45.06 Sq.mts. ( 485 Sq.ft. ) |
| 2 BHK | 58.06 Sq.mts. ( 625 Sq.ft. ) |
| 2 BHK | 58.81 Sq.mts. ( 633 Sq.ft. ) |
| 2 BHK | 60.85 Sq.mts. ( 655 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Dharmavihar C Winglast updated on 28 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space50% completed
|
|
1558.32 Sq Mtrs |
Community Buildings90% completed
|
|
Work In Progress |
Electrical Meter Room, Sub-Station, Receiving Station
|
|
Work Not Started |
|
|
|
Work Not Started |
Fire Protection And Fire Safety
Requirements
|
|
Work Not Started |
Landscaping & Tree Planting20% completed
|
|
Work In Progress |
|
|
|
Work Not Started |
Sewerage (Chamber, Lines, Septic Tank , STP)80% completed
|
|
Septic Tank Complete |
Solid Waste Management And Disposal
|
|
Work Not Started |
|
|
|
Work Not Started |
|
|
|
Work Not Started |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Include In Sewerage |
Water Conservation, Rain water Harvesting
|
|
Work Not Started |
|
|
|
The Water Supply Provided By Bnmc After Oc |
Buildings / Wings in Dharmavihar C Wing
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Dharmavihar C Wing by Mky Infrastructurelast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
134
apartments in total
Saleable Area Statistics (Sq. ft.)
74631
Total
Total 134 apartments in project. 29 apartments booked. 21% apartments booked.
Total 74631 Sq.ft. saleable area. 15697 saleable area booked.
21% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Dharma Vihar C Wing | Dec 2024 | 18 | 1 | 0 | 1 | 0 | 18 | 1 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 43.48 Sq.mts. ( 468 Sq.ft. ) | 32 | |
| 1 BHK | 44.41 Sq.mts. ( 478 Sq.ft. ) | 17 | |
| 1 BHK | 45.06 Sq.mts. ( 485 Sq.ft. ) | 17 | |
| 2 BHK | 58.06 Sq.mts. ( 625 Sq.ft. ) | 17 | |
| 2 BHK | 58.81 Sq.mts. ( 633 Sq.ft. ) | 34 | |
| 2 BHK | 60.85 Sq.mts. ( 655 Sq.ft. ) | 17 | |
134 total apartments / 29 apartments booked. 21% apartments booked. |
| Work Description in Building Dharma Vihar C Wing | Completion |
Channel Partners Registered by Developer
Mky Infrastructure
for Project
Dharmavihar C Wing
last updated on
28 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |