Project overview
Dhanvantari Tower is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000028741. Dhanvantari Tower is located at S No 46 H No 9 And 12. This is a New being developed by Vijay Vitthal Shirishkar.
Dhanvantari Tower has 2 BHK, 3 BHK, NURSING 1ST FLOOR, NURSING 2ND FLOOR, NURSING 3RD FLOOR, NURSING 4\5TH FLOOR & Shop Apartments with carpet areas ranging from 1152 to 869 Sq.ft. Carpet. The Project has total 16 of which 14 are currently available for sale.
Dhanvantari Tower is being developed on a total land area of 7299 Sq.ft. Dhanvantari Tower has 1 Wings / Towers Dhanvantari Tower
| Project | Developer | Location | Possession |
-
Project:
Dhanvantari Tower
-
Location:
-
S No 46 H No 9 And 12
-
Const. Stage:
New
-
Possession:
30 Jun 2024
-
Developer:
Vijay Vitthal Shirishkar
-
Phone:
-
Address:
-
Navjivan Hospital
| MAHA REARA No: |
P99000028741 |
| Project Type |
Others |
| RERA Project Status |
New |
| Architect |
Ajay Wade & Associates |
| Funding Bank |
BASSEIN CATHOLIC COOPERATIVE BANK LIMITED |
| Proposed Possession |
30 Jun 2024 |
| Revised Possession |
|
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
30 Mar 2021 |
| Last Retrived |
28 Jul 2025 |
Dhanvantari Tower QR Code
Dhanvantari Tower
MahaRERA - P99000028741
| Type | Area |
| 2 BHK | 49.92 Sq.mts. ( 537 Sq.ft. ) |
| 2 BHK | 50.3 Sq.mts. ( 541 Sq.ft. ) |
| 2 BHK | 63.01 Sq.mts. ( 678 Sq.ft. ) |
| 3 BHK | 80.59 Sq.mts. ( 867 Sq.ft. ) |
| 3 BHK | 80.7 Sq.mts. ( 869 Sq.ft. ) |
| NURSING 1ST FLOOR | 107.39 Sq.mts. ( 1156 Sq.ft. ) |
| NURSING 2ND FLOOR | 140.62 Sq.mts. ( 1514 Sq.ft. ) |
| NURSING 3RD FLOOR | 172.13 Sq.mts. ( 1853 Sq.ft. ) |
| NURSING 4\5TH FLOOR | 166.8 Sq.mts. ( 1795 Sq.ft. ) |
| Shop | 107.06 Sq.mts. ( 1152 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Dhanvantari Towerlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station
|
|
In Progress |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements
|
|
In Progress |
Landscaping & Tree Planting
|
|
In Progress |
|
|
|
In Progress |
Sewerage (Chamber, Lines, Septic Tank , STP)
|
|
In Progress |
Solid Waste Management And Disposal
|
|
In Progress |
|
|
|
In Progress |
|
|
|
Na |
Treatment And Disposal Of Sewage And Sullage Water
|
|
In Progress |
Water Conservation, Rain water Harvesting
|
|
In Progress |
|
|
|
Facility Will Start Once Vvcmc Water Supply Commen |
Buildings / Wings in Dhanvantari Tower
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Dhanvantari Tower by Vijay Vitthal Shirishkarlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
16
apartments in total
Saleable Area Statistics (Sq. ft.)
16106
Total
Total 16 apartments in project. 2 apartments booked. 12% apartments booked.
Total 16106 Sq.ft. saleable area. 1410 saleable area booked.
9% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Dhanvantari Tower | Dec 2023 | 11 | 1 | 1 | 0 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 2 BHK | 49.92 Sq.mts. ( 537 Sq.ft. ) | 4 | |
| 2 BHK | 50.3 Sq.mts. ( 541 Sq.ft. ) | 1 | |
| 2 BHK | 63.01 Sq.mts. ( 678 Sq.ft. ) | 1 | |
| 3 BHK | 80.59 Sq.mts. ( 867 Sq.ft. ) | 3 | |
| 3 BHK | 80.7 Sq.mts. ( 869 Sq.ft. ) | 1 | |
| NURSING 1ST FLOOR | 107.39 Sq.mts. ( 1156 Sq.ft. ) | 1 | |
| NURSING 2ND FLOOR | 140.62 Sq.mts. ( 1514 Sq.ft. ) | 1 | |
| NURSING 3RD FLOOR | 172.13 Sq.mts. ( 1853 Sq.ft. ) | 1 | |
| NURSING 4\5TH FLOOR | 166.8 Sq.mts. ( 1795 Sq.ft. ) | 2 | |
| Shop | 107.06 Sq.mts. ( 1152 Sq.ft. ) | 1 | |
16 total apartments / 2 apartments booked. 12% apartments booked. |
| Work Description in Building Dhanvantari Tower | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
Channel Partners Registered by Developer
Vijay Vitthal Shirishkar
for Project
Dhanvantari Tower
last updated on
28 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |