Project overview

Dev Darshan is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800007029. Dev Darshan is located at Cts No 636, 636 1 To 16 & Cts No 634, 6341 To 26. This is a Ongoing being developed by City Estate Developers Limited.

Dev Darshan has 0 Apartments with carpet areas ranging from 0 to 0 Sq.ft. Carpet. The Project has total 110 of which 2 are currently available for sale.

Dev Darshan is being developed on a total land area of 99875 Sq.ft. out of which 7233 Sq.ft. i.e 7% is reserved for recreational purposes. Dev Darshan has 4 Wings / Towers A Building,B Building,C Building,D Building

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Dev Darshan
  • Location:
  • Cts No 636, 636 1 To 16 & Cts No 634, 6341 To 26
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2022
Developer Details

  • Developer:
    City Estate Developers Limited
  • Phone:
  • Address:
  • Crasto Building, 2Nd Floor
Project RERA Details
MAHA REARA No: P51800007029
Project Type Others
RERA Project Status Ongoing
Architect Hemant Karani
Funding Bank AXIS BANK
Proposed Possession 30 Dec 2022
Revised Possession 30 Dec 2022
Extended Possession
Litigations No Litigations
Last Modified 17 Nov 2017
Last Retrived 26 Jul 2025
Dev Darshan QR Code
Dev Darshan
MahaRERA - P51800007029
Apartment Details & Configuration
TypeArea
2 BHK67.26 Sq.mts. ( 724 Sq.ft. )
2 BHK68.18 Sq.mts. ( 734 Sq.ft. )
3 BHK88.64 Sq.mts. ( 954 Sq.ft. )
3 BHK89.22 Sq.mts. ( 960 Sq.ft. )
Office220.16 Sq.mts. ( 2370 Sq.ft. )
Office336.49 Sq.mts. ( 3622 Sq.ft. )
Office579.76 Sq.mts. ( 6241 Sq.ft. )
Shop37.17 Sq.mts. ( 400 Sq.ft. )
2 BHK53.1 Sq.mts. ( 572 Sq.ft. )
2 BHK55.05 Sq.mts. ( 593 Sq.ft. )
2 BHK67.74 Sq.mts. ( 729 Sq.ft. )
2 BHK69.85 Sq.mts. ( 752 Sq.ft. )
3 BHK87.37 Sq.mts. ( 940 Sq.ft. )
3 BHK88.34 Sq.mts. ( 951 Sq.ft. )
00 Sq.mts. ( 0 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Dev Darshanlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Work Done
Community Buildings100% completed
95% Complete
Completed
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Msedcl
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
As Per Cfo Requirement
Landscaping & Tree Planting100% completed
95% Complete
Tree Planting Only
Mechanical Stack Parking Tower50% completed
50% Complete
-
Open Parking100% completed
95% Complete
Work Done
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Bmc Sewer
Solid Waste Management And Disposal
0
Storm Water Drains100% completed
95% Complete
Internal Strom Water Drain
Street Lighting100% completed
95% Complete
Completed
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Connected To Bmc Drainage
Water Conservation, Rain water Harvesting
Rain Water Harvesting Only
Water Supply100% completed
95% Complete
Bmc Water Supply
Buildings / Wings in Dev Darshan
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Dev Darshan by City Estate Developers Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

99875 Sq. ft.

Project Area

7233 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

110 apartments in total
Total
110
Booked
108
Available
2

Saleable Area Statistics (Sq. ft.)

101791 Total
Total
101791
Booked
100338
Available
1453
Total 110 apartments in project. 108 apartments booked. 98% apartments booked.
Total 101791 Sq.ft. saleable area. 100338 saleable area booked.
99% area booked.

A Building

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A BuildingDec 2021151100230
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK67.26 Sq.mts. ( 724 Sq.ft. )12
11 Booked91% Booked
91% Booked
2 BHK68.18 Sq.mts. ( 734 Sq.ft. )13
13 Booked100% Booked
100% Booked
3 BHK88.64 Sq.mts. ( 954 Sq.ft. )13
13 Booked100% Booked
100% Booked
3 BHK89.22 Sq.mts. ( 960 Sq.ft. )13
13 Booked100% Booked
100% Booked
Office220.16 Sq.mts. ( 2370 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office336.49 Sq.mts. ( 3622 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office579.76 Sq.mts. ( 6241 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop37.17 Sq.mts. ( 400 Sq.ft. )1
1 Booked100% Booked
100% Booked
55 total apartments / 54 apartments booked. 98% apartments booked.
Work Description in Building A BuildingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

B Building

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
B BuildingDec 2021151100230
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK53.1 Sq.mts. ( 572 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK55.05 Sq.mts. ( 593 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK67.74 Sq.mts. ( 729 Sq.ft. )12
11 Booked91% Booked
91% Booked
2 BHK69.85 Sq.mts. ( 752 Sq.ft. )13
13 Booked100% Booked
100% Booked
3 BHK87.37 Sq.mts. ( 940 Sq.ft. )26
26 Booked100% Booked
100% Booked
3 BHK88.34 Sq.mts. ( 951 Sq.ft. )2
2 Booked100% Booked
100% Booked
55 total apartments / 54 apartments booked. 98% apartments booked.
Work Description in Building B BuildingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

C Building

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
C BuildingDec 20210000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
00 Sq.mts. ( 0 Sq.ft. )0
None Booked0% Booked
0% Booked
Work Description in Building C BuildingCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

D Building

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
D BuildingJan 19000000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
00 Sq.mts. ( 0 Sq.ft. )0
None Booked0% Booked
0% Booked
Work Description in Building D BuildingCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
City Estate Developers Limited
for Project
Dev Darshan
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation