Project overview

DATTANI VERTEX WING CD PHASE III is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000005990. DATTANI VERTEX WING CD PHASE III is located at Survey No.284. This is a Ongoing being developed by BRIJESH SATISH DATTANI.

DATTANI VERTEX WING CD PHASE III has 1 BHK Apartments with carpet areas ranging from 11884 to 11884 Sq.ft. Carpet. The Project has total 56 of which 9 are currently available for sale.

DATTANI VERTEX WING CD PHASE III is being developed on a total land area of 13808 Sq.ft. out of which 88128 Sq.ft. i.e 638% is reserved for recreational purposes. DATTANI VERTEX WING CD PHASE III has 2 Wings / Towers Dattani Vertex Wing C,Dattani Vertex Wing D

ProjectDeveloperLocationPossession
Project Details
  • Project:
    DATTANI VERTEX WING CD PHASE III
  • Location:
  • Survey No.284
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2023
Developer Details

  • Developer:
    BRIJESH SATISH DATTANI
  • Phone:
  • Address:
  • Laxmi Shopping Center
Project RERA Details
MAHA REARA No: P99000005990
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Encon
Funding Bank BANK OF INDIA
Proposed Possession 30 Dec 2023
Revised Possession 30 Dec 2023
Extended Possession
Litigations No Litigations
Last Modified 14 Aug 2017
Last Retrived 14 Feb 2026
DATTANI VERTEX WING CD PHASE III QR Code
DATTANI VERTEX WING CD PHASE III
MahaRERA - P99000005990
Apartment Details & Configuration
TypeArea
1 BHK1104.04 Sq.mts. ( 11884 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of DATTANI VERTEX WING CD PHASE IIIlast updated on 14 Feb 2026 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space90% completed
90% Complete
Work In Progress
Community Buildings
Yet To Start
Electrical Meter Room, Sub-Station, Receiving Station
Yet To Start
Energy management
Yet To Start
Fire Protection And Fire Safety Requirements
Yet To Start
Landscaping & Tree Planting
Yet To Start
Open Parking
Yet To Start
Sewerage (Chamber, Lines, Septic Tank , STP)
Yet To Start
Solid Waste Management And Disposal
Yet To Start
Storm Water Drains
Yet To Start
Street Lighting
Yet To Start
Treatment And Disposal Of Sewage And Sullage Water
Yet To Start
Water Conservation, Rain water Harvesting
Yet To Start
Water Supply
Yet To Start
Buildings / Wings in DATTANI VERTEX WING CD PHASE III
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of DATTANI VERTEX WING CD PHASE III by BRIJESH SATISH DATTANIlast updated on 14 Feb 2026 as per information obtained from MARA RERA.

13808 Sq. ft.

Project Area

88128 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

56 apartments in total
Total
56
Booked
47
Available
9

Saleable Area Statistics (Sq. ft.)

665498 Total
Total
665498
Booked
558543
Available
106955
Total 56 apartments in project. 47 apartments booked. 83% apartments booked.
Total 665498 Sq.ft. saleable area. 558543 saleable area booked.
84% area booked.

Dattani Vertex Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Dattani Vertex Wing CJan 1900810101316
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK1104.04 Sq.mts. ( 11884 Sq.ft. )28
24 Booked85% Booked
85% Booked
28 total apartments / 24 apartments booked. 85% apartments booked.
Work Description in Building Dattani Vertex Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress95% done
95% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Dattani Vertex Wing D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Dattani Vertex Wing DJan 1900810101315
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK1104.04 Sq.mts. ( 11884 Sq.ft. )28
23 Booked82% Booked
82% Booked
28 total apartments / 23 apartments booked. 82% apartments booked.
Work Description in Building Dattani Vertex Wing DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress95% done
95% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
BRIJESH SATISH DATTANI
for Project
DATTANI VERTEX WING CD PHASE III
last updated on 14 Feb 2026 as per information obtained from MARA RERA.
Name Company Location Mobile Designation