Project overview

Daji Residency is a MahaRERA Registered Project bearing MahaRERA Registration Number P52000015560. Daji Residency is located at 75/1/2/B/3. This is a New being developed by Vw Realty.

Daji Residency has 1 BHK Apartments with carpet areas ranging from 312 to 388 Sq.ft. Carpet. The Project has total 116 of which 66 are currently available for sale.

Daji Residency is being developed on a total land area of 39827 Sq.ft. out of which 3042 Sq.ft. i.e 8% is reserved for recreational purposes. Daji Residency has 3 Wings / Towers Wing A,Wing B,Wing C

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Daji Residency
  • Location:
  • 75/1/2/B/3
  • Const. Stage:
    New
  • Possession:
    30 Dec 2023
Developer Details

  • Developer:
    Vw Realty
  • Phone:
  • Address:
  • Rahul Apartment
Project RERA Details
MAHA REARA No: P52000015560
Project Type Residential / Group Housing
RERA Project Status New
Architect Chetan Dilip Wajekar
Funding Bank AXIS BANK
Proposed Possession 30 Dec 2023
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 08 Mar 2018
Last Retrived 28 Jul 2025
Daji Residency QR Code
Daji Residency
MahaRERA - P52000015560
Apartment Details & Configuration
TypeArea
1 BHK28.98 Sq.mts. ( 312 Sq.ft. )
1 BHK35.48 Sq.mts. ( 382 Sq.ft. )
2 BHK36 Sq.mts. ( 388 Sq.ft. )
1 BHK29.12 Sq.mts. ( 313 Sq.ft. )
1 BHK30.35 Sq.mts. ( 327 Sq.ft. )
2 BHK37.5 Sq.mts. ( 404 Sq.ft. )
SHOP10.95 Sq.mts. ( 118 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Daji Residencylast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
To Be Provided
Community Buildings100% completed
95% Complete
Gymnasia To Be Provided
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Electrical Meter Room To Be Provided
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
To Be Provided
Landscaping & Tree Planting100% completed
95% Complete
Tree Planting To Be Provided
Open Parking100% completed
95% Complete
To Be Provided
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
No Stp
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
To Be Provided
Street Lighting100% completed
95% Complete
To Be Provided On Internal Roads
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
Rain Water Harvesting To Be Provided
Water Supply100% completed
95% Complete
Water Supply To Be Obtained From Umc
Buildings / Wings in Daji Residency
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Daji Residency by Vw Realtylast updated on 28 Jul 2025 as per information obtained from MARA RERA.

39827 Sq. ft.

Project Area

3042 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

116 apartments in total
Total
116
Booked
50
Available
66

Saleable Area Statistics (Sq. ft.)

40016 Total
Total
40016
Booked
16827
Available
23189
Total 116 apartments in project. 50 apartments booked. 43% apartments booked.
Total 40016 Sq.ft. saleable area. 16827 saleable area booked.
42% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing ADec 20228101004
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.98 Sq.mts. ( 312 Sq.ft. )14
6 Booked42% Booked
42% Booked
1 BHK35.48 Sq.mts. ( 382 Sq.ft. )7
3 Booked42% Booked
42% Booked
2 BHK36 Sq.mts. ( 388 Sq.ft. )14
6 Booked42% Booked
42% Booked
35 total apartments / 15 apartments booked. 42% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BDec 20228101002
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.12 Sq.mts. ( 313 Sq.ft. )14
7 Booked50% Booked
50% Booked
1 BHK30.35 Sq.mts. ( 327 Sq.ft. )14
7 Booked50% Booked
50% Booked
2 BHK37.5 Sq.mts. ( 404 Sq.ft. )14
SHOP10.95 Sq.mts. ( 118 Sq.ft. )4
2 Booked50% Booked
50% Booked
46 total apartments / 18 apartments booked. 39% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CDec 20228101004
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.98 Sq.mts. ( 312 Sq.ft. )14
8 Booked57% Booked
57% Booked
1 BHK35.48 Sq.mts. ( 382 Sq.ft. )7
4 Booked57% Booked
57% Booked
1 BHK36 Sq.mts. ( 388 Sq.ft. )14
5 Booked35% Booked
35% Booked
35 total apartments / 17 apartments booked. 48% apartments booked.
Work Description in Building Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Vw Realty
for Project
Daji Residency
last updated on 28 Jul 2025 as per information obtained from MARA RERA.