Project overview

Daisy Gardens Survey No 12 Phase I is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700009528. Daisy Gardens Survey No 12 Phase I is located at Survey No 12/12, 15/7 And 12/3 Cts No 33/10. This is a Ongoing being developed by Ankita Builders.

Daisy Gardens Survey No 12 Phase I has 1 BHK & 2 BHK Apartments with carpet areas ranging from 377 to 462 Sq.ft. Carpet. The Project has total 114 of which 73 are currently available for sale.

Daisy Gardens Survey No 12 Phase I is being developed on a total land area of 21528 Sq.ft. Daisy Gardens Survey No 12 Phase I has 3 Wings / Towers Building No 10,Building No 11,Building No 12

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Daisy Gardens Survey No 12 Phase I
  • Location:
  • Survey No 12/12, 15/7 And 12/3 Cts No 33/10
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2020
Developer Details

  • Developer:
    Ankita Builders
  • Phone:
  • Address:
  • Near Sapna Garden
Project RERA Details
MAHA REARA No: P51700009528
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Vitan Consultants
Funding Bank HDFC BANK
Proposed Possession 30 Dec 2020
Revised Possession 30 Dec 2020
Extended Possession 30 Jun 2024
Litigations No Litigations
Last Modified 01 Jul 2024
Last Retrived 26 Jul 2025
Daisy Gardens Survey No 12 Phase I QR Code
Daisy Gardens Survey No 12 Phase I
MahaRERA - P51700009528
Apartment Details & Configuration
TypeArea
1 BHK34.98 Sq.mts. ( 377 Sq.ft. )
1 BHK35.04 Sq.mts. ( 377 Sq.ft. )
2 BHK41.74 Sq.mts. ( 449 Sq.ft. )
2 BHK42.96 Sq.mts. ( 462 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Daisy Gardens Survey No 12 Phase Ilast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space55% completed
55% Complete
-
Community Buildings
-
Electrical Meter Room, Sub-Station, Receiving Station65% completed
65% Complete
-
Energy management65% completed
65% Complete
-
Fire Protection And Fire Safety Requirements70% completed
70% Complete
-
Landscaping & Tree Planting100% completed
95% Complete
-
Open Parking100% completed
95% Complete
0
Sewerage (Chamber, Lines, Septic Tank , STP)70% completed
70% Complete
-
Solid Waste Management And Disposal65% completed
65% Complete
-
Storm Water Drains70% completed
70% Complete
-
Street Lighting100% completed
95% Complete
-
Treatment And Disposal Of Sewage And Sullage Water50% completed
50% Complete
-
Water Conservation, Rain water Harvesting70% completed
70% Complete
-
Water Supply50% completed
50% Complete
-
Buildings / Wings in Daisy Gardens Survey No 12 Phase I
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Daisy Gardens Survey No 12 Phase I by Ankita Builderslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

21528 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

114 apartments in total
Total
114
Booked
41
Available
73

Saleable Area Statistics (Sq. ft.)

45018 Total
Total
45018
Booked
16307
Available
28711
Total 114 apartments in project. 41 apartments booked. 35% apartments booked.
Total 45018 Sq.ft. saleable area. 16307 saleable area booked.
36% area booked.

Building No 10

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 10Dec 20218101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK34.98 Sq.mts. ( 377 Sq.ft. )3
None Booked0% Booked
0% Booked
1 BHK35.04 Sq.mts. ( 377 Sq.ft. )28
None Booked0% Booked
0% Booked
2 BHK41.74 Sq.mts. ( 449 Sq.ft. )7
None Booked0% Booked
0% Booked
38 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building No 10Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress75% done
75% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress95% done
95% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress75% done
75% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress90% done
90% Booked
Stilt Floor
Completed 100% done
100% Booked

Building No 11

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 11Dec 20218101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK34.98 Sq.mts. ( 377 Sq.ft. )3
2 Booked66% Booked
66% Booked
1 BHK35.04 Sq.mts. ( 377 Sq.ft. )28
2 BHK41.74 Sq.mts. ( 449 Sq.ft. )7
None Booked0% Booked
0% Booked
38 total apartments / 5 apartments booked. 13% apartments booked.
Work Description in Building Building No 11Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress70% done
70% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress95% done
95% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress80% done
80% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress90% done
90% Booked
Stilt Floor
Completed 100% done
100% Booked

Building No 12

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 12Dec 20218101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK34.98 Sq.mts. ( 377 Sq.ft. )3
3 Booked100% Booked
100% Booked
1 BHK35.04 Sq.mts. ( 377 Sq.ft. )22
22 Booked100% Booked
100% Booked
2 BHK41.74 Sq.mts. ( 449 Sq.ft. )7
7 Booked100% Booked
100% Booked
2 BHK42.96 Sq.mts. ( 462 Sq.ft. )6
4 Booked66% Booked
66% Booked
38 total apartments / 36 apartments booked. 94% apartments booked.
Work Description in Building Building No 12Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Ankita Builders
for Project
Daisy Gardens Survey No 12 Phase I
last updated on 26 Jul 2025 as per information obtained from MARA RERA.