Project overview
Construction Of Bldg No.18 At S No 392 And 376 Virar Bolinj is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000047059. Construction Of Bldg No.18 At S No 392 And 376 Virar Bolinj is located at Virar Olinj. This is a New Project being developed by Konkan Housing And Area Developement Board.
Construction Of Bldg No.18 At S No 392 And 376 Virar Bolinj has 1 BHK Apartments with carpet areas ranging from 453 to 453 Sq.ft. Carpet. The Project has total 59 of which 59 are currently available for sale.
Construction Of Bldg No.18 At S No 392 And 376 Virar Bolinj is being developed on a total land area of 17519 Sq.ft. out of which 17519 Sq.ft. i.e 100% is reserved for recreational purposes. Construction Of Bldg No.18 At S No 392 And 376 Virar Bolinj has 1 Wings / Towers Bldg No 18
| Project | Developer | Location | Possession |
-
Developer:
Konkan Housing And Area Developement Board
-
Phone:
-
Address:
-
Room No 169, Griha Nirman Bhavan, Mig Colony Road, Mhada, Kalanagar, 400051
| MAHA REARA No: |
P99000047059 |
| Project Type |
Residential |
| RERA Project Status |
New Project |
| Architect |
Nitin Patil |
| Funding Bank |
BANK OF MAHARASHTRA |
| Proposed Possession |
30 May 2023 |
| Revised Possession |
|
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
22 Sep 2022 |
| Last Retrived |
28 Jul 2025 |
Construction Of Bldg No.18 At S No 392 And 376 Virar Bolinj QR Code
Construction Of Bldg No.18 At S No 392 And 376 Virar Bolinj
MahaRERA - P99000047059
| Type | Area |
| 1 BHK | 42.08 Sq.mts. ( 453 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Construction Of Bldg No.18 At S No 392 And 376 Virar Bolinjlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space 100% completed
|
|
Bldg No 18 |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station100% completed
|
|
Bldg No 18 |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements70% completed
|
|
Bldg No 18 |
Landscaping & Tree Planting80% completed
|
|
Bldg No 18 |
|
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)70% completed
|
|
Bldg No 18 |
Solid Waste Management And Disposal
|
|
Na |
Storm Water Drains70% completed
|
|
Bldg No 18 |
Street Lighting100% completed
|
|
Bldg No 18 |
Treatment And Disposal Of Sewage And Sullage Water100% completed
|
|
Bldg No 18 |
Water Conservation, Rain water Harvesting100% completed
|
|
Bldg No 18 |
Water Supply100% completed
|
|
Bldg No 18 |
Buildings / Wings in Construction Of Bldg No.18 At S No 392 And 376 Virar Bolinj
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Construction Of Bldg No.18 At S No 392 And 376 Virar Bolinj by Konkan Housing And Area Developement Boardlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
59
apartments in total
Saleable Area Statistics (Sq. ft.)
26724
Total
Total 59 apartments in project. 0 apartments booked. 0% apartments booked.
Total 26724 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Bldg No 18 | May 2023 | 10 | 1 | 0 | 1 | 1 | 1 | 1 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 42.08 Sq.mts. ( 453 Sq.ft. ) | 59 | |
59 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Bldg No 18 | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Konkan Housing And Area Developement Board
for Project
Construction Of Bldg No.18 At S No 392 And 376 Virar Bolinj
last updated on
28 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |