Project overview

Bhagwati Celeste is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700034475. Bhagwati Celeste is located at Cts No 5543,5544,5537,5538,5648 To 5671,5672/1,5672/4,5672/9,To 5672/20,5673 To 5681. This is a New being developed by Sagar Homes.

Bhagwati Celeste has 1RK & Ground Floor Apartments with carpet areas ranging from 215 to 258 Sq.ft. Carpet. The Project has total 166 of which 137 are currently available for sale.

Bhagwati Celeste is being developed on a total land area of 38015 Sq.ft. Bhagwati Celeste has 4 Wings / Towers Bhagwati Celeste Building No 1 Wing A,Bhagwati Celeste Building No 1 Wing B,Bhagwati Celeste Building No 2,Bhagwati Celeste Building No 3

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Bhagwati Celeste
  • Location:
  • Cts No 5543,5544,5537,5538,5648 To 5671,5672/1,5672/4,5672/9,To 5672/20,5673 To 5681
  • Const. Stage:
    New
  • Possession:
    31 Mar 2027
Developer Details

  • Developer:
    Sagar Homes
  • Phone:
  • Address:
  • Ratna Niwas
Project RERA Details
MAHA REARA No: P51700034475
Project Type Others
RERA Project Status New
Architect Landmark Group
Funding Bank AXIS BANK
Proposed Possession 31 Mar 2027
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 11 Apr 2022
Last Retrived 26 Jul 2025
Bhagwati Celeste QR Code
Bhagwati Celeste
MahaRERA - P51700034475
Apartment Details & Configuration
TypeArea
1 BHK23.41 Sq.mts. ( 252 Sq.ft. )
1 BHK25.76 Sq.mts. ( 277 Sq.ft. )
1 BHK28.81 Sq.mts. ( 310 Sq.ft. )
1 BHK29.47 Sq.mts. ( 317 Sq.ft. )
2 BHK38.66 Sq.mts. ( 416 Sq.ft. )
2 BHK38.89 Sq.mts. ( 419 Sq.ft. )
2 BHK39.16 Sq.mts. ( 422 Sq.ft. )
Shop9.93 Sq.mts. ( 107 Sq.ft. )
Shop10.14 Sq.mts. ( 109 Sq.ft. )
Shop11.99 Sq.mts. ( 129 Sq.ft. )
Shop12.61 Sq.mts. ( 136 Sq.ft. )
Shop12.84 Sq.mts. ( 138 Sq.ft. )
Shop18.01 Sq.mts. ( 194 Sq.ft. )
1 BHK29.72 Sq.mts. ( 320 Sq.ft. )
1 BHK29.78 Sq.mts. ( 321 Sq.ft. )
2 BHK35.68 Sq.mts. ( 384 Sq.ft. )
2 BHK36.49 Sq.mts. ( 393 Sq.ft. )
Shop10.42 Sq.mts. ( 112 Sq.ft. )
Shop10.94 Sq.mts. ( 118 Sq.ft. )
1RK19.98 Sq.mts. ( 215 Sq.ft. )
1RK19.99 Sq.mts. ( 215 Sq.ft. )
1RK20.25 Sq.mts. ( 218 Sq.ft. )
Ground Floor23.93 Sq.mts. ( 258 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Bhagwati Celestelast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
As Per Approved Plan
Energy management
Na
Fire Protection And Fire Safety Requirements
As Per Approved Plan
Landscaping & Tree Planting
-
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
-
Solid Waste Management And Disposal
Na
Storm Water Drains
As Per Approved Plan
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
As Per Approved Plan
Water Supply
As Per Approved Plan
Buildings / Wings in Bhagwati Celeste
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Bhagwati Celeste by Sagar Homeslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

38015 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

166 apartments in total
Total
166
Booked
29
Available
137

Saleable Area Statistics (Sq. ft.)

49861 Total
Total
49861
Booked
6730
Available
43132
Total 166 apartments in project. 29 apartments booked. 17% apartments booked.
Total 49861 Sq.ft. saleable area. 6730 saleable area booked.
13% area booked.

Bhagwati Celeste Building No 1 Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bhagwati Celeste Building No 1 Wing AMar 202711101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK23.41 Sq.mts. ( 252 Sq.ft. )11
None Booked0% Booked
0% Booked
1 BHK25.76 Sq.mts. ( 277 Sq.ft. )11
1 BHK28.81 Sq.mts. ( 310 Sq.ft. )12
None Booked0% Booked
0% Booked
1 BHK29.47 Sq.mts. ( 317 Sq.ft. )8
2 BHK38.66 Sq.mts. ( 416 Sq.ft. )11
2 BHK38.89 Sq.mts. ( 419 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK39.16 Sq.mts. ( 422 Sq.ft. )10
None Booked0% Booked
0% Booked
Shop9.93 Sq.mts. ( 107 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop10.14 Sq.mts. ( 109 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop11.99 Sq.mts. ( 129 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop12.61 Sq.mts. ( 136 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop12.84 Sq.mts. ( 138 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop18.01 Sq.mts. ( 194 Sq.ft. )1
None Booked0% Booked
0% Booked
71 total apartments / 9 apartments booked. 12% apartments booked.
Work Description in Building Bhagwati Celeste Building No 1 Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress20% done
20% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress30% done
30% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
work-in-progress25% done
25% Booked
Slabs of Super Structure
work-in-progress65% done
65% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress40% done
40% Booked
Stilt Floor
work-in-progress70% done
70% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Bhagwati Celeste Building No 1 Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bhagwati Celeste Building No 1 Wing BMar 202712101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.81 Sq.mts. ( 310 Sq.ft. )12
1 BHK29.47 Sq.mts. ( 317 Sq.ft. )12
None Booked0% Booked
0% Booked
1 BHK29.72 Sq.mts. ( 320 Sq.ft. )12
1 BHK29.78 Sq.mts. ( 321 Sq.ft. )11
None Booked0% Booked
0% Booked
47 total apartments / 2 apartments booked. 4% apartments booked.
Work Description in Building Bhagwati Celeste Building No 1 Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress20% done
20% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress30% done
30% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
work-in-progress25% done
25% Booked
Slabs of Super Structure
work-in-progress65% done
65% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress40% done
40% Booked
Stilt Floor
work-in-progress85% done
85% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Bhagwati Celeste Building No 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bhagwati Celeste Building No 2Mar 20277101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK35.68 Sq.mts. ( 384 Sq.ft. )12
None Booked0% Booked
0% Booked
2 BHK36.49 Sq.mts. ( 393 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop10.42 Sq.mts. ( 112 Sq.ft. )2
None Booked0% Booked
0% Booked
Shop10.94 Sq.mts. ( 118 Sq.ft. )2
None Booked0% Booked
0% Booked
17 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Bhagwati Celeste Building No 2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress20% done
20% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress40% done
40% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress70% done
70% Booked
Stilt Floor
work-in-progress40% done
40% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Bhagwati Celeste Building No 3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bhagwati Celeste Building No 3Mar 20276100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1RK19.98 Sq.mts. ( 215 Sq.ft. )3
3 Booked100% Booked
100% Booked
1RK19.99 Sq.mts. ( 215 Sq.ft. )9
5 Booked55% Booked
55% Booked
1RK20.25 Sq.mts. ( 218 Sq.ft. )3
2 Booked66% Booked
66% Booked
1RK23.41 Sq.mts. ( 252 Sq.ft. )15
8 Booked53% Booked
53% Booked
Ground Floor23.93 Sq.mts. ( 258 Sq.ft. )1
None Booked0% Booked
0% Booked
31 total apartments / 18 apartments booked. 58% apartments booked.
Work Description in Building Bhagwati Celeste Building No 3Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress55% done
55% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress75% done
75% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
work-in-progress60% done
60% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress65% done
65% Booked
Stilt Floor
work-in-progress95% done
95% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Sagar Homes
for Project
Bhagwati Celeste
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation