Project overview

Besant Arti Chs Ltd is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800001350. Besant Arti Chs Ltd is located at Cts No H 140 Pt/ Final Plot No 54. This is a Ongoing being developed by Shamik Enterprises Pvt Ltd..

Besant Arti Chs Ltd has 2 BHK & 3 BHK Apartments with carpet areas ranging from 1221 to 1022 Sq.ft. Carpet. The Project has total 8 of which 0 are currently available for sale.

Besant Arti Chs Ltd is being developed on a total land area of 10115 Sq.ft. Besant Arti Chs Ltd has 1 Wings / Towers Shamik Elite

ProjectDeveloperLocationPossession
Evershine MadhuvanEvershine Builders Private Limited83B/131-12-2018 00:00:00
Deluxe ApartmentsWest Avenue Realtors Private LimitedFinal Plot No. 66/530-04-2021 00:00:00
LiliumJayshree BuildersCts No 171 B And 171 C Final Plot No 8230-12-2021 00:00:00
Bluemoon AnnexeMudassar Builders & Developers5070 5070/1 To 6 5071 5071/1 To 25 502730-09-2018 00:00:00
Santacruz Prakash Chs Ltd RedevelopmentPtr Corporations142 A -131-12-2018 00:00:00
Kismet ChslMidcity Landmarks LlpPlot No 63 Cts No G 43031-12-2019 00:00:00
KisnaShreeji Realties Private Limited47731-12-2019 00:00:00
Morya Business CentreMorya Ace207531-01-2023 00:00:00
New Santacruz Suchit Co Operative Housing Society Ltd.Shastriji Developers Llp400055, Mumbai Suburban31-12-2017 00:00:00
PremsagarAnkur Premises Developers LlpG/397/315-06-2021 00:00:00
Emerene HeightsRangoli Realtors & DevelopersCts No. H44331-05-2019 00:00:00
Two RosesPrakash EstatesPlot No 5 Cts No F/86631-12-2019 00:00:00
Unique ElitaAnkur Shubham DevelopersCts No.I/241, I/241/1 To 531-12-2018 00:00:00
Ratnadeep Ankur Premises Developers LlpH 167 E25-05-2022 00:00:00
Avenue 54Sumer Radius Realty Pvt Ltd40005431-12-2022 00:00:00
Om Jai Chsl - AugustusToughcon City Homes Private Limited243/130-12-2020 00:00:00
Redevelopment Of Shalaka Chs LtdDinaco Resorts Private LimitedCts No G-156 To 158 Plot No 32 Tps Ii Santacruz West31-12-2018 00:00:00
Moniz Shraddha HeightsK K Krishnan Construction Company Pvt Ltd2865 M/1 To 6, 3046, 3039, 2804 To 2809, 3093/1 To 7, 3039/1 To 8, 3053, 3047, 3052/1 To 2, 305230-03-2023 00:00:00
SudeshAnkur Premises Developers LlpG/396/624-02-2021 00:00:00
Rajkamal Raj ConstructionsF.P. No 91 Of T.P.I. Of Santacruz28-11-2021 00:00:00
M.K HeritageShaista Khan400054, Mumbai Suburban30-12-2022 00:00:00
JyotiV R AssociatesG 61631-03-2018 00:00:00
Laxmi PrabhaTerraferma Developers LlpPlot Bearing Cts No 56A30-06-2018 00:00:00
Ekta Sra ChsClassic Enterprises Vakola2943, 2938/1, 2942/1, 2939 To 2942, Cts No 2936 To 2938, 294401-08-2023 00:00:00
Bonavision HeightsA.B.EnterprisesMumbai Suburban, 40005531-12-2020 00:00:00
Riddhi PalaceBharat Enterprises1660 B-4, 1660 B-330-12-2021 00:00:00
New Laxmi ChhayaParmar And Sm Construction1660, 166131-07-2019 00:00:00
Acharat BaugAnkur Premises Developers LlpH/144 To H/14701-07-2024 00:00:00
Mayfair GnyanadeepMayfair Housing Private LimitedPlot No J/3 Manekji Gazdar Scheme Of Santacruz, Cts No 624/530-06-2025 00:00:00
PanoramaS Raheja Residency LlpPlot No J-6 Cts No G/428-A31-12-2025 00:00:00
Sigma EmeraldSigma Realtors (India) Private LimitedMumbai Suburban, Andheri, 40005531-08-2021 00:00:00
Pruthi AnnexeRaja Developers148/1B31-01-2021 00:00:00
Mantri ParijatPentagon Premises Private LimitedG32131-12-2018 00:00:00
Bhaveshwar Smriti Chs LtdSeasons Bachher Properties40005431-12-2022 00:00:00
Radhakunj ChsAum DevelopersG/37201-01-2019 00:00:00
Queens SquareAshirwad Buildhome Private Limtied536, 537, H/53530-06-2021 00:00:00
Anand Milan Co.Op. Housing Society LimitedAnand Milan Co.Op. Housing Society LimitedCts No 574135 Of Village Ghatkopar-Kirol31-03-2024 00:00:00
ArttezaSunvision EstatesFinal Plot No 18-19/20-2331-05-2024 00:00:00
Sanghvi EdgeSangvi Lifespace Private LimitedCts No 1 As Per Pr Card And Cts No 2/6 As Per Dp Remarks31-12-2026 00:00:00
Krishna EnclaveAsha Developers795 To 799, Cts No 190 To 42601-08-2023 00:00:00
Planning, Designing, Constuction And Obtaining Necessary Approvals For 72 Hig T/S On Lumpsum TurnkeyMaharashtra Housing And Area Development Authority5608/A / 158/2330-06-2018 00:00:00
127 Upper EastParanjape Schemes (Construction) LtdCts No. 2059 And 2073 Final Plot No. 127 Of Tps - V31-12-2019 00:00:00
Rudra ParadiseR-Stone Design And Build Private Limited116-24 And 116-25 A, Cts No 116 Part, 116-2331-01-2021 00:00:00
Redevelopment Of Link Palace Premises Co-Op Soc. Ltd. Phase IKolte-Patil Developers LimitedG/444 F P 100 Of Tps Iv Santacruz31-12-2017 00:00:00
IqraShubham DevelopersMasjid Road31-12-2018 00:00:00
Nd EnclaveN & D Constructions Llp50/531-12-2018 00:00:00
Transcon Ramdev PlazaTranscon Iconica Private Limited94 To 103 And 106 Pt30-12-2023 00:00:00
Adcon MeridianHi Sky RealtyFp 27A, Cts 171, Tps Iii31-12-2018 00:00:00
Pearl PalaceChandiwala Enterprises39/1 To 5, 285, 40/1 To 37, 40, 28430-12-2021 00:00:00
Redevelopment Of The Roopkala Chs LtdOrra Realtors Private Limited400054, Mumbai Suburban31-12-2017 00:00:00
Navkala BharatiLakshmiconstructionCts No.113 Final Plot No.16 Tps V31-10-2019 00:00:00
Shri Sadashiv ChslBhoomi Shashwat Estate Pvt. Ltd.Cts No. 233A, F. P. No. 4130-12-2021 00:00:00
Commerz 54Shree Vinayak Reality Private LimitedPlot No 22 23 Cts No H 44815-12-2022 00:00:00
ShikharPtr UniversalG-23101-04-2024 00:00:00
Ruparel PanacheRuparel Infra & Realty Pvt LtdH/283, H/285, H/284, H/293, H/28031-12-2025 00:00:00
Prabhat KunjLakshmiconstructionI/50/1 To 11, Final Plot No.66 Of Cts No.I/5030-06-2025 00:00:00
Vardhman Castle Phase IVenus Development CorporationSantacruz West31-12-2023 00:00:00
Parlashray ChslSai Ganesh Properties And Holdings LlpF P No. 520 Of Vile Parle Tps -V31-03-2024 00:00:00
Ekta TrinityEkta Housing Private LimitedCs No H/39930-12-2022 00:00:00
Akash Kiran Chs LtdShamik Enterprises Pvt Ltd.Cts No. 1958/ Final Plot No. 51730-06-2019 00:00:00
Imperia HomesGprs Realty7626/1, 383431-12-2019 00:00:00
KesarbanAmbrosial Developers Private LimitedFp No. 66-731-03-2018 00:00:00
Besant Arti Chs LtdShamik Enterprises Pvt Ltd.Cts No H 140 Pt/ Final Plot No 5430-06-2019 00:00:00
Golden Heights Gold Coin Builders3801, 3800, 379930-12-2023 00:00:00
Project Details
  • Project:
    Besant Arti Chs Ltd
  • Location:
  • Cts No H 140 Pt/ Final Plot No 54
  • Const. Stage:
    Ongoing
  • Possession:
    30 Jun 2019
Developer Details

  • Developer:
    Shamik Enterprises Pvt Ltd.
  • Phone:
  • Address:
  • Deo Enclave Co. Op.Hsg. Soc. Ltd.
Project RERA Details
MAHA REARA No: P51800001350
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Hmj Architects
Funding Bank HDFC BANK
Proposed Possession 30 Jun 2019
Revised Possession 30 Jun 2019
Extended Possession 29 Dec 2020
Litigations No Litigations
Last Modified 13 Jun 2020
Last Retrived 26 Jul 2025
Besant Arti Chs Ltd QR Code
Besant Arti Chs Ltd
MahaRERA - P51800001350
Apartment Details & Configuration
TypeArea
2 BHK73.52 Sq.mts. ( 791 Sq.ft. )
3 BHK94.97 Sq.mts. ( 1022 Sq.ft. )
3 BHK113.45 Sq.mts. ( 1221 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Besant Arti Chs Ltdlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Only Meter Room
Energy management
Na
Fire Protection And Fire Safety Requirements
Yet To Be Commenced
Landscaping & Tree Planting
Na
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)40% completed
40% Complete
Only Sewerage Lines
Solid Waste Management And Disposal
Na
Storm Water Drains
Yet To Be Commenced
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Only Rain Water Harvesting
Water Supply
Yet To Be Commenced
Buildings / Wings in Besant Arti Chs Ltd
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Besant Arti Chs Ltd by Shamik Enterprises Pvt Ltd.last updated on 26 Jul 2025 as per information obtained from MARA RERA.

10115 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

8 apartments in total
Total
8
Booked
8
Available
0

Saleable Area Statistics (Sq. ft.)

8942 Total
Total
8942
Booked
8942
Available
0
Total 8 apartments in project. 8 apartments booked. 100% apartments booked.
Total 8942 Sq.ft. saleable area. 8942 saleable area booked.
100% area booked.

Shamik Elite

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Shamik EliteJun 2019101010040
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK73.52 Sq.mts. ( 791 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK94.97 Sq.mts. ( 1022 Sq.ft. )2
2 Booked100% Booked
100% Booked
3 BHK113.45 Sq.mts. ( 1221 Sq.ft. )5
5 Booked100% Booked
100% Booked
8 total apartments / 8 apartments booked. 100% apartments booked.
Work Description in Building Shamik EliteCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress40% done
40% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress60% done
60% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress60% done
60% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress60% done
60% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress40% done
40% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Shamik Enterprises Pvt Ltd.
for Project
Besant Arti Chs Ltd
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation