Project overview

Bafna Meadows Phase 1 is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000006123. Bafna Meadows Phase 1 is located at 409/3P 409/4P 827/16. This is a Ongoing being developed by Suvidha Realtors.

Bafna Meadows Phase 1 has 2 BHK & Shop Apartments with carpet areas ranging from 174 to 645 Sq.ft. Carpet. The Project has total 159 of which 16 are currently available for sale.

Bafna Meadows Phase 1 is being developed on a total land area of 83337 Sq.ft. out of which 8333 Sq.ft. i.e 10% is reserved for recreational purposes. Bafna Meadows Phase 1 has 5 Wings / Towers Aster,Blossom,Flora,Lavender,Orchid

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Bafna Meadows Phase 1
  • Location:
  • 409/3P 409/4P 827/16
  • Const. Stage:
    Ongoing
  • Possession:
    01 Dec 2018
Developer Details

  • Developer:
    Suvidha Realtors
  • Phone:
  • Address:
  • Vadgadi
Project RERA Details
MAHA REARA No: P99000006123
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Sai Rachana
Funding Bank
Proposed Possession 01 Dec 2018
Revised Possession 01 Dec 2018
Extended Possession
Litigations No Litigations
Last Modified 14 Aug 2017
Last Retrived 28 Jul 2025
Bafna Meadows Phase 1 QR Code
Bafna Meadows Phase 1
MahaRERA - P99000006123
Apartment Details & Configuration
TypeArea
2 BHK50.62 Sq.mts. ( 545 Sq.ft. )
2 BHK53.92 Sq.mts. ( 580 Sq.ft. )
2 BHK55.69 Sq.mts. ( 599 Sq.ft. )
2 BHK56.11 Sq.mts. ( 604 Sq.ft. )
Shop12.81 Sq.mts. ( 138 Sq.ft. )
Shop37.72 Sq.mts. ( 406 Sq.ft. )
1 BHK38.28 Sq.mts. ( 412 Sq.ft. )
1 BHK39.51 Sq.mts. ( 425 Sq.ft. )
1 BHK39.86 Sq.mts. ( 429 Sq.ft. )
1 BHK31.81 Sq.mts. ( 342 Sq.ft. )
1 BHK37.66 Sq.mts. ( 405 Sq.ft. )
2 BHK43.12 Sq.mts. ( 464 Sq.ft. )
2 BHK50.34 Sq.mts. ( 542 Sq.ft. )
2 BHK52.4 Sq.mts. ( 564 Sq.ft. )
2 BHK52.76 Sq.mts. ( 568 Sq.ft. )
1 BHK33.96 Sq.mts. ( 366 Sq.ft. )
1 BHK35.33 Sq.mts. ( 380 Sq.ft. )
1 BHK35.84 Sq.mts. ( 386 Sq.ft. )
1 BHK38.63 Sq.mts. ( 416 Sq.ft. )
1 BHK42.38 Sq.mts. ( 456 Sq.ft. )
2 BHK49.52 Sq.mts. ( 533 Sq.ft. )
Shop10.64 Sq.mts. ( 115 Sq.ft. )
Shop12 Sq.mts. ( 129 Sq.ft. )
Shop12.33 Sq.mts. ( 133 Sq.ft. )
Shop13.38 Sq.mts. ( 144 Sq.ft. )
Shop13.67 Sq.mts. ( 147 Sq.ft. )
Shop14.41 Sq.mts. ( 155 Sq.ft. )
Shop18.36 Sq.mts. ( 198 Sq.ft. )
Shop19.43 Sq.mts. ( 209 Sq.ft. )
2 BHK59.88 Sq.mts. ( 645 Sq.ft. )
Shop16.16 Sq.mts. ( 174 Sq.ft. )
Shop16.75 Sq.mts. ( 180 Sq.ft. )
Shop16.84 Sq.mts. ( 181 Sq.ft. )
Shop18.78 Sq.mts. ( 202 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Bafna Meadows Phase 1last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Work Not Started
Community Buildings
Work Not Started
Electrical Meter Room, Sub-Station, Receiving Station20% completed
20% Complete
Work In Progress
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting50% completed
50% Complete
Work In Progress
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)30% completed
30% Complete
Work In Progress
Solid Waste Management And Disposal
Na
Storm Water Drains20% completed
20% Complete
Work Done
Street Lighting20% completed
20% Complete
Work Not Started
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting50% completed
50% Complete
Work Not Started
Water Supply50% completed
50% Complete
Work In Progress
Buildings / Wings in Bafna Meadows Phase 1
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Bafna Meadows Phase 1 by Suvidha Realtorslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

83337 Sq. ft.

Project Area

8333 Sq. ft.

Recreational Open Space

Total 5

Wings / Towers in Project

Apartments Statistics

159 apartments in total
Total
159
Booked
143
Available
16

Saleable Area Statistics (Sq. ft.)

71770 Total
Total
71770
Booked
65251
Available
6519
Total 159 apartments in project. 143 apartments booked. 89% apartments booked.
Total 71770 Sq.ft. saleable area. 65251 saleable area booked.
91% area booked.

Aster

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
AsterJan 20185101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK50.62 Sq.mts. ( 545 Sq.ft. )8
8 Booked100% Booked
100% Booked
2 BHK53.92 Sq.mts. ( 580 Sq.ft. )8
8 Booked100% Booked
100% Booked
2 BHK55.69 Sq.mts. ( 599 Sq.ft. )14
14 Booked100% Booked
100% Booked
2 BHK56.11 Sq.mts. ( 604 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop12.81 Sq.mts. ( 138 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop37.72 Sq.mts. ( 406 Sq.ft. )2
None Booked0% Booked
0% Booked
35 total apartments / 32 apartments booked. 91% apartments booked.
Work Description in Building AsterCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Blossom

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
BlossomJan 20185101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK38.28 Sq.mts. ( 412 Sq.ft. )8
8 Booked100% Booked
100% Booked
1 BHK39.51 Sq.mts. ( 425 Sq.ft. )16
16 Booked100% Booked
100% Booked
1 BHK39.86 Sq.mts. ( 429 Sq.ft. )8
8 Booked100% Booked
100% Booked
32 total apartments / 32 apartments booked. 100% apartments booked.
Work Description in Building BlossomCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress50% done
50% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress50% done
50% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress85% done
85% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Flora

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
FloraJan 20185101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.81 Sq.mts. ( 342 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK37.66 Sq.mts. ( 405 Sq.ft. )8
7 Booked87% Booked
87% Booked
2 BHK43.12 Sq.mts. ( 464 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK50.34 Sq.mts. ( 542 Sq.ft. )4
2 Booked50% Booked
50% Booked
2 BHK52.4 Sq.mts. ( 564 Sq.ft. )4
3 Booked75% Booked
75% Booked
2 BHK52.76 Sq.mts. ( 568 Sq.ft. )3
3 Booked100% Booked
100% Booked
24 total apartments / 20 apartments booked. 83% apartments booked.
Work Description in Building FloraCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress72% done
72% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress67% done
67% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress67% done
67% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress50% done
50% Booked
Sanitary Fittings within the flats / premises
work-in-progress50% done
50% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress53% done
53% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress53% done
53% Booked
Stilt Floor
work-in-progress90% done
90% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress72% done
72% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Lavender

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
LavenderJan 20185101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK33.96 Sq.mts. ( 366 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK35.33 Sq.mts. ( 380 Sq.ft. )4
3 Booked75% Booked
75% Booked
1 BHK35.84 Sq.mts. ( 386 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK38.63 Sq.mts. ( 416 Sq.ft. )8
4 Booked50% Booked
50% Booked
1 BHK42.38 Sq.mts. ( 456 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK49.52 Sq.mts. ( 533 Sq.ft. )8
7 Booked87% Booked
87% Booked
Shop10.64 Sq.mts. ( 115 Sq.ft. )2
1 Booked50% Booked
50% Booked
Shop12 Sq.mts. ( 129 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop12.33 Sq.mts. ( 133 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop13.38 Sq.mts. ( 144 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop13.67 Sq.mts. ( 147 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop14.41 Sq.mts. ( 155 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop18.36 Sq.mts. ( 198 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop19.43 Sq.mts. ( 209 Sq.ft. )1
1 Booked100% Booked
100% Booked
44 total apartments / 37 apartments booked. 84% apartments booked.
Work Description in Building LavenderCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress68% done
68% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress50% done
50% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress53% done
53% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress53% done
53% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress68% done
68% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Orchid

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
OrchidJan 20185101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK59.88 Sq.mts. ( 645 Sq.ft. )16
15 Booked93% Booked
93% Booked
Shop16.16 Sq.mts. ( 174 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop16.75 Sq.mts. ( 180 Sq.ft. )2
1 Booked50% Booked
50% Booked
Shop16.84 Sq.mts. ( 181 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop18.78 Sq.mts. ( 202 Sq.ft. )2
2 Booked100% Booked
100% Booked
24 total apartments / 22 apartments booked. 91% apartments booked.
Work Description in Building OrchidCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Suvidha Realtors
for Project
Bafna Meadows Phase 1
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation