Project overview

Avirahi Homes Building 3 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800009582. Avirahi Homes Building 3 is located at Cts No 613-A-1. This is a Ongoing being developed by V.M.Associates.

Avirahi Homes Building 3 has 2 BHK, 3 BHK, Shop & shop Apartments with carpet areas ranging from 275 to 959 Sq.ft. Carpet. The Project has total 55 of which 3 are currently available for sale.

Avirahi Homes Building 3 is being developed on a total land area of 90956 Sq.ft. out of which 13652 Sq.ft. i.e 15% is reserved for recreational purposes. Avirahi Homes Building 3 has 2 Wings / Towers Wing F,Wing G

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Avirahi Homes Building 3
  • Location:
  • Cts No 613-A-1
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2018
Developer Details

  • Developer:
    V.M.Associates
  • Phone:
  • Address:
  • Bharat Baug
Project RERA Details
MAHA REARA No: P51800009582
Project Type Others
RERA Project Status Ongoing
Architect Ashok Gandhi
Funding Bank IDBI BANK
Proposed Possession 31 Dec 2018
Revised Possession 31 Dec 2018
Extended Possession 30 Oct 2020
Litigations No Litigations
Last Modified 17 Jun 2020
Last Retrived 26 Jul 2025
Avirahi Homes Building 3 QR Code
Avirahi Homes Building 3
MahaRERA - P51800009582
Apartment Details & Configuration
TypeArea
2 BHK67.8 Sq.mts. ( 730 Sq.ft. )
3 BHK91.92 Sq.mts. ( 989 Sq.ft. )
2 BHK67.97 Sq.mts. ( 732 Sq.ft. )
3 BHK89.11 Sq.mts. ( 959 Sq.ft. )
Shop273.45 Sq.mts. ( 2943 Sq.ft. )
shop25.59 Sq.mts. ( 275 Sq.ft. )
Shop28.6 Sq.mts. ( 308 Sq.ft. )
Shop51.54 Sq.mts. ( 555 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Avirahi Homes Building 3last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Ros Defined As Per Approved Plan
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Installed On Site
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Functional And Will Be Retested Before Occ
Landscaping & Tree Planting
Trees Will Be Planted As Per Tree Noc
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Connected To Sewer Line
Solid Waste Management And Disposal
Vermiculture Bin Will Be Installed Before Occ
Storm Water Drains100% completed
95% Complete
As Per Mcgm
Street Lighting100% completed
95% Complete
Completed As Per Mcgm
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Line Connected To Existing Sewer Line
Water Conservation, Rain water Harvesting100% completed
95% Complete
Installed
Water Supply100% completed
95% Complete
Permanent Water Connection On Occ
Buildings / Wings in Avirahi Homes Building 3
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Avirahi Homes Building 3 by V.M.Associateslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

90956 Sq. ft.

Project Area

13652 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

55 apartments in total
Total
55
Booked
52
Available
3

Saleable Area Statistics (Sq. ft.)

43520 Total
Total
43520
Booked
42694
Available
826
Total 55 apartments in project. 52 apartments booked. 94% apartments booked.
Total 43520 Sq.ft. saleable area. 42694 saleable area booked.
98% area booked.

Wing F

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing FJan 190011101201
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK67.8 Sq.mts. ( 730 Sq.ft. )11
11 Booked100% Booked
100% Booked
3 BHK91.92 Sq.mts. ( 989 Sq.ft. )11
11 Booked100% Booked
100% Booked
22 total apartments / 22 apartments booked. 100% apartments booked.
Work Description in Building Wing FCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing G

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing GJan 190011101201
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK67.97 Sq.mts. ( 732 Sq.ft. )11
11 Booked100% Booked
100% Booked
3 BHK89.11 Sq.mts. ( 959 Sq.ft. )11
11 Booked100% Booked
100% Booked
Shop273.45 Sq.mts. ( 2943 Sq.ft. )1
1 Booked100% Booked
100% Booked
shop25.59 Sq.mts. ( 275 Sq.ft. )8
5 Booked62% Booked
62% Booked
Shop28.6 Sq.mts. ( 308 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop51.54 Sq.mts. ( 555 Sq.ft. )1
1 Booked100% Booked
100% Booked
33 total apartments / 30 apartments booked. 90% apartments booked.
Work Description in Building Wing GCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
V.M.Associates
for Project
Avirahi Homes Building 3
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation