Project overview

Avenue D Phase Iii 2 is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000023895. Avenue D Phase Iii 2 is located at 5, 5B. This is a New being developed by Venus Developers.

Avenue D Phase Iii 2 has 1 BHK Apartments with carpet areas ranging from 400 to 400 Sq.ft. Carpet. The Project has total 125 of which 125 are currently available for sale.

Avenue D Phase Iii 2 is being developed on a total land area of 68445 Sq.ft. out of which 21973 Sq.ft. i.e 32% is reserved for recreational purposes. Avenue D Phase Iii 2 has 3 Wings / Towers Avenue D Building No 19,Avenue D Building No 27,Avenue D Building No 28

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Avenue D Phase Iii 2
  • Location:
  • 5, 5B
  • Const. Stage:
    New
  • Possession:
    30 Dec 2023
Developer Details

  • Developer:
    Venus Developers
  • Phone:
  • Address:
  • Shanti Sadan
Project RERA Details
MAHA REARA No: P99000023895
Project Type Residential / Group Housing
RERA Project Status New
Architect Divyesh Shah
Funding Bank BANK OF MAHARASHTRA
Proposed Possession 30 Dec 2023
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 10 Jan 2020
Last Retrived 28 Jul 2025
Avenue D Phase Iii 2 QR Code
Avenue D Phase Iii 2
MahaRERA - P99000023895
Apartment Details & Configuration
TypeArea
2 BHK45.71 Sq.mts. ( 492 Sq.ft. )
1 BHK37.14 Sq.mts. ( 400 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Avenue D Phase Iii 2last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space75% completed
75% Complete
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Na
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting50% completed
50% Complete
Na
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)50% completed
50% Complete
Na
Solid Waste Management And Disposal
Na
Storm Water Drains50% completed
50% Complete
Na
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting25% completed
25% Complete
Na
Water Supply
Na
Buildings / Wings in Avenue D Phase Iii 2
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Avenue D Phase Iii 2 by Venus Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

68445 Sq. ft.

Project Area

21973 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

125 apartments in total
Total
125
Booked
0
Available
125

Saleable Area Statistics (Sq. ft.)

52832 Total
Total
52832
Booked
0
Available
52832
Total 125 apartments in project. 0 apartments booked. 0% apartments booked.
Total 52832 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.

Avenue D Building No 19

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Avenue D Building No 19Mar 202281010101
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK45.71 Sq.mts. ( 492 Sq.ft. )31
None Booked0% Booked
0% Booked
31 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Avenue D Building No 19Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress30% done
30% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Avenue D Building No 27

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Avenue D Building No 27Mar 202281010121
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK37.14 Sq.mts. ( 400 Sq.ft. )47
None Booked0% Booked
0% Booked
47 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Avenue D Building No 27Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress50% done
50% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress37% done
37% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress20% done
20% Booked
Sanitary Fittings within the flats / premises
work-in-progress20% done
20% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Avenue D Building No 28

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Avenue D Building No 28Mar 202281010121
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK37.14 Sq.mts. ( 400 Sq.ft. )47
None Booked0% Booked
0% Booked
47 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Avenue D Building No 28Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress29% done
29% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress80% done
80% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress80% done
80% Booked
Channel Partners
Channel Partners Registered by Developer
Venus Developers
for Project
Avenue D Phase Iii 2
last updated on 28 Jul 2025 as per information obtained from MARA RERA.